SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Gau) 2196

THE GAUHATI HIGH COURT, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
DEVASHIS BARUAH, J.
Krishna Kanta Das, S/o. Late Dehiram Das – Petitioner 
Versus
The State Of Assam, Represented By The Additional Chief Secretary To The Government Of Assam, Public Health Engineering Department And Ors. – Respondents 
WP(C) 2504 of 2024 
Decided On : 03-11-2025

Advocates Appeared:
For the Petitioner: Ms. B. Chowdhury, Adv.
For the Respondents: Mr. I. Borthakur, SC, PHE

The principle of delay and laches precludes a litigant from being entertained for judicial relief when there is excessive delay without adequate justification, impacting the rights of other parties.

Headnote:(A) Constitution of India - Article 226 - Writ jurisdiction - Petition dismissed due to inordinate delay of 8 years in approaching the Court without adequate explanation - The Court emphasized that delay and laches may hinder equitable jurisdiction and can lead to injustice, as drawn from the Supreme Court’s observation. (Paras 5-6)

(B) Delay and laches - A litigant's inaction for a prolonged period without justification reflects negligence and may affect others’ rights, as reiterated in the context of the petitioner's undue delay. (Paras 6-8)

Facts of the case:
The petitioner sought a direction for payment of dues for works completed, supported by work orders issued in January 2016. However, the petition was filed after 8 years with no justifiable explanation for the delay, leading to difficulties in verification by the Respondents.

Findings of Court:
The Court determined that the petition should not be entertained due to the excessive delay in filing, which compromises the ability to verify claims effectively.

Issues: The main issue was whether a significant delay in seeking judicial intervention constitutes grounds for dismissing a writ petition.

Ratio Decidendi: The Court concluded that the principle established in the cited Supreme Court case regarding delay and laches was applicable. The petitioner’s procrastination warranted dismissal of the writ petition, underscoring that the court’s equitable jurisdiction does not extend to indolent litigants.

Result: Writ petition dismissed.

Table of Content
1. petitioner's claim for payment after work completion. (Para 2 , 3 , 4)
2. delays affect the rights of the respondents. (Para 5)
3. court analysis of delay and laches. (Para 6 , 7 , 8)
4. writ petition dismissed; right to approach civil court remains. (Para 9 , 10)

JUDGMENT :

DEVASHIS BARUAH, J.

Heard Ms. B. Chowdhury, the learned counsel appearing on behalf of the Petitioner and Mr. I. Borthakur, the learned Standing counsel appearing on behalf of the PHE Department.

2. The Petitioner herein has sought for a direction from this Court thereby directing the Respondents to pay an amount of Rs.5,73,806/- on account of the same being due to the Petitioner for the works completed by the Petitioner.

3. It is relevant to take note of that the Petitioner herein claims the said amount on the basis of various work orders issued to the Petitioner on 05.01.2016, 20.01.2016 and 29.01.2016. It is stated that the works were duly completed by the Petitioner and in that regard have enclosed a Work Completion Certificate of one such work. However the said Completion Certificate is not dated.

4. The materials on record also do not show what steps were taken by the Petitioner for the purpose of realization of the said amount alleged to be due to the Petitioner. It was only in the year 2023 that too in the month of November, a joint representation was submitted by various contractors to the PHE Department including the Petitioner and as the Respondent Authorities have not given any favourable response, the Petitioner has approached this Court by filing the present writ petition.

5. Mr. I. Borthakur, the learned Standing counsel appearing on behalf of the PHE Department submits that taking into account that the Petitioner has approached this Court after 8 years and there is no materials showing that there is any completion in respect to the various work orders enclosed, it is difficult on the part of the Respondents to carry out the verifications at this late juncture. The learned Standing counsel further submitted that in respect of certain alleged dues, filing of a writ petition after almost a decade takes away a valuable right of the Respondents to have a defence inasmuch as the relevant records would not be available for making necessary verification. He, therefore, submitted that this is a case wherein this Court ought not to entertain the writ petition in view of the judgment of the Supreme Court in the case of Chennai Metropolitan Water Supply and Sewerage Board and Others vs. T.T. Murali Babu reported in (2014) 4 SCC 108 , wherein the Supreme Court clearly observed that a litigant cannot be permitted to behave like “Kumbhakarna”. Paragraph Nos. 16 and 17 of the said judgment are reproduced herein below:-

16. Thus, the doctrine of delay and laches should not be lightly brushed aside. A writ court is required to weigh the explanation offered and the acceptability of the same. The court should bear in mind that it is exercising an extraordinary and equitable jurisdiction. As a constitutional court it has a duty to protect the rights of the citizens but simultaneously it is to keep itself alive to the primary principle that when an aggrieved person, without adequate reason, approaches the court at his own leisure or pleasure, the court would be under legal obligation to scrutinise whether the lis at a belated stage should be entertained or not. Be it noted, delay comes in the way of equity. In certain circumstances delay and laches may not be fatal but in most circumstances inordinate delay would only invite disaster for the litigant who knocks at the doors of the court. Delay reflects inactivity and inaction on the part of a litigant — a litigant who has forgotten the basic norms, namely, “procrastination is the greatest thief of time” and second, law does not permit one to sleep and rise like a phoenix. Delay does bring in hazard and causes injury to the lis.

17. In the case at hand, though there has been four years' delay in approach

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top