THE GAUHATI HIGH COURT, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
DEVASHIS BARUAH, J.
On The Death Of Birendra Kumar Saikia, His Legal Heirs Namely- Mrs Pranati Saikia – Appellant
Versus
Ajit Chandra Bora, S/o. Late Milaram Bora – Respondent
RSA No.175 of 2012
Decided On : 25-03-2025
| Table of Content |
|---|
| 1. procedural context and factual origin of the suit for specific performance. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. defendant's contention regarding the cancellation of the agreement and framing of trial issues. (Para 8 , 9 , 10 , 11) |
| 3. appraisal of findings by trial and first appellate courts regarding agreement validity and performance readiness. (Para 12 , 13 , 14 , 15 , 16 , 17) |
| 4. assessment of the necessity of determining the first substantial question of law regarding third-party injury. (Para 18 , 19 , 20) |
| 5. acceptance of partial refund constitutes non-readiness under section 16(c) of the specific relief act. (Para 21 , 22 , 23 , 24 , 25 , 26 , 27) |
| 6. doctrine of frustration is inapplicable if not specifically pleaded or supported by evidence. (Para 28) |
| 7. setting aside appellate judgment and restoring trial court's decision to dismiss the suit. (Para 29 , 30 , 31) |
JUDGMENT :
DEVASHIS BARUAH, J.
Heard Mr. A. Dhar, the learned counsel appearing on behalf of the appellants and Mr. C. Goswami, the learned counsel appearing on behalf of the respondent.
2. This is an appeal filed under Section 100 of the Code of Civil Procedure, 1908 (for short ‘the Code’) challenging the judgment and decree dated 19.05.2012 passed by the learned Civil Judge and Assistant District Judge, Jorhat (hereinafter referred to as ‘the learned First Appellate Court’) in Title Appeal No.7/2011 whereby the judgment and decree dated 14.02.2011 passed by the learned Munsiff No.2, Jorhat (hereinafter referred to as ‘the learned Trial Court’) in Title Suit No.11/2008 was reversed.
3. It is seen from the records that vide an order dated 04.12.2012, the Coordinate Bench of this Court had admitted the instant appeal by formulating three substantial questions of law. The said three substantial questions of law are reproduced herein under:
“1. Whether the decree passed in a suit for specific performance of an agreement could be enforced which involves injury to the property of a third party?
2. Whether demanding refund and acceptance of advance money of an agreement vitiate “willingness” of the party to perform the obligation of the promise?
3. Whether an agreement is dissolved by the doctrine of frustration when the entire performance of the agreement becomes substantially impossible?”
4. For the purpose of deciding as to whether the three substantial questions of law which are formulated by the Coordinate Bench of this Court vide the order dated 04.12.2012 are involved in the present appeal, this Court takes note of the facts which led to the filing of the instant appeal.
5. For the purpose of convenience, the parties herein are referred to in the same status as they stood before the learned Trial Court.
6. An agreement dated 14.12.2006 admittedly was entered into between the plaintiff and the defendant for sale of a plot of land which was specifically described in Schedule-A to the plaint at a consideration of Rs.50,000/-. The case of the plaintiff is that the plaintiff had paid an amount of Rs.20,000/- on the date of execution of the deed of agreement for sale and the remaining amount of Rs.30,000/- was to be paid at the time of execution of the registered deed of sale. It is the specific case of the plaintiff that the plaintiff had requested the defendant to execute the deed of sale and receive the remaining amount of Rs.30,000/- but the defendant did not take any steps in that regard. As such, a legal notice was also issued 07.09.2007 asking the defendant to execute the deed of sale within a period of 30 days from the date of receipt of the said notice. However, the defendant did not take any steps. It is under such circumstances, the plaintiff instituted the suit being Title Suit No. 79/2007 before the Court of the Munsiff No.1 at Jorhat.
7. In the said suit, the plaintiff sought for a decree for specific performance of the agreement dated 14.12.2006 thereby directing the defendant to execute and register the deed of sale in favour of the plaintiff in re
Proof of sale agreement and advance insufficient for specific performance without continuous readiness and willingness under Section 16(c); denying contract precludes forfeiture; additional appellate....
Time is of the essence in specific performance agreements; the plaintiff must prove readiness and willingness to execute the contract, which was not established in this case.
(1) Though, principle that time is not essence of contract in a suit for specific performance of immovable property deserves its consideration in appropriate cases, said principle cannot be applied a....
The burden of proof lies on the party disputing the validity of a written contract, and the conduct of the parties and the plaintiff's readiness and willingness are essential for specific performance....
The plaintiff's failure to file the suit within the limitation period and to prove readiness and willingness to perform the contract resulted in dismissal of the specific performance claim.
The plaintiff must demonstrate continuous readiness and willingness to perform a contract for specific performance; failure to do so justifies dismissal of the suit.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.