SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(Ker) 1353

IN THE HIGH COURT OF KERALA AT ERNAKULAM
K. SURENDRA MOHAN, MARY JOSEPH, JJ.
Infopark (Kerala) - Appellants
Vs.
Billmoria & Company Ltd., Mumbai - Respondent
Arb. A. No. 39 of 2011
Decided On : 06-12-2017

Advocates Appeared:
For the Appellant : Anil Thomas, K.V. Reshmi
For the Respondents: K.L. Varghese, Ranjith Varghese, Rahul Varghese, Santha Varghese

The court's decision emphasized the limited scope of interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for findings to be supported by the materials on record.

Headnote:

Arbitration - Construction Contract - Arbitration and Conciliation Act, 1996 - Section 34 - The court dismissed the Original Petition seeking to set aside an arbitral award, holding that the Arbitrator had entered findings supported by the materials on record. The appellant contended that the Arbitrator had erred in holding the appellant responsible for the delay. The respondent disputed the contentions and argued that the scope of interference with an award under Section 34 of the Act was limited. The District Court found that the appellant had no case that the subject matter of the dispute was not capable of settlement by the Arbitrator or that the award was in conflict with the public policy of India. The court held that the Arbitrator had gone into the terms of reference properly and had entered findings that were supported by the materials on record. The court found no grounds to interfere with the award or the order of the District Judge.

Fact of the Case:

The appellant, a fully owned Government Society, filed an Original Petition under Section 34 of the Arbitration and Conciliation Act, 1996 seeking to set aside an award passed by the Arbitrator. The Arbitrator found initial delay on the part of the appellant in handing over the site and in supplying the drawings of the work, and directed the amounts recovered as liquidated damages to be refunded. The appellant contended that the delay was caused by the respondent's deficiency in management and planning. The District Court dismissed the Original Petition, holding that the Arbitrator's findings were supported by the materials on record.

Finding of the Court:

The District Court found that the Arbitrator had entered findings supported by the materials on record and that the appellant had no grounds to set aside the award. The court held that the scope of interference with an award under Section 34 of the Act was limited and declined to interfere with the award.

Issues: The main issues were whether the Arbitrator's findings were supported by the materials on record and whether the appellant had grounds to set aside the award under Section 34 of the Act.

Ratio Decidendi: The court held that the Arbitrator's findings were supported by the materials on record and that the appellant had no grounds to set aside the award under Section 34 of the Act.

Final Decision: The appeal was dismissed with costs.

JUDGMENT :

K. Surendra Mohan, J.

1. This appeal is directed against an order dated 27/01/2011 in Arb. O.P. No. 1726 of 2009. The Original Petition was filed by the appellant herein under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act' for short) seeking to set aside an award passed by the Arbitrator on 25/08/2009. As per the order appealed against, the District Court has dismissed the Original Petition holding that there were no grounds to set aside the arbitral award. The aggrieved appellant is before us. The appellant is a fully owned Government Society. It has an Info Park at Kakkanad, Ernakulam District. The work of construction of an IT building, having an area of 2 lakhs sq. ft. and a service yard of 17600 sq.ft spread over ground plus nine floors was awarded to the respondent Contractor as per work order dated 25/08/2003, they being the lowest tenderer. Though the time limit for completion of the work was specified as nine months, the period was subsequently extended and the construction was finally completed only in October, 2005. After completion of the work, the respondent filed O.S. No. 729 of 2006 before the Sub Court, Ernakulam putting forward a number of claims against the appellant. During the pendency of the suit, the parties agreed to have the disputes settled through arbitration. Accordingly, both parties submitted the agreed terms of reference. The name of Justice K. John Mathew, a retired Judge of this Court, was suggested by both parties. The Sub Court thereupon appointed Justice K. John Mathew as Arbitrator and referred the terms agreed to by both parties, for arbitration.

2. The Arbitrator entered upon the reference, considered the respective contentions of the parties and passed an award dated 25/08/2009. As per the award, the Arbitrator found that there was initial delay on the part of the appellant in handing over the site and in supplying the drawings of the work. Therefore, the action of the appellant in levying and recovering liquidated damages from the respondent was found to be unjustified. Accordingly, the amounts so recovered were directed to be refunded. The Arbitrator further found that the Contractor was entitled to escalation of price with respect to steel and therefore held the respondent entitled to recover an amount of Rs. 30,87,655/-. It was challenging the said award under Section 34 of the Act that Arb.O.P. No. 1726 of 2009 was filed, as stated above.

3. It was contended on behalf of the appellant that, the finding of the Arbitrator holding the appellant responsible for the delay was wrong. According to the appellant, it was the respondent who was responsible for the delay. The delay was caused mainly due to the deficiency in management of the construction and the project by the respondent. There was no advance planning even for procurement of crucial items like, reinforcement steel, electrical equipments, fire fighting equipments etc. The entire work was given on sub-contract to others and the co-ordination between them was very bad. The construction equipments used were very old and resulted in break down on many occasions. The labour force was inadequate and the work was carried out only during day time though the contract had stipulated for working during the night also, since the entire work was to be completed within 9 months. A floor of 25000 sq.ft was cast in 12 or 13 pieces. A contractor with adequate resources could have cast 20000 to 25000 sq.ft in a single continuous pore. It was contended that day-to-day work of planning had no relation to the overall execution plan. Only a limited quantity was planned and executed on daily basis. On many occasions even that could not be achieved. Delay occurred in the procurement and installation of the electrical equipments, firefighting equipment and fire alarm system. There was delay in procurement of reinforcement steel. Similar delays occurred in other matters also. It was therefore contend


































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top