IN THE HIGH COURT OF KERALA AT ERNAKULAM
ANIL K. NARENDRAN, P.G. AJITHKUMAR, JJ.
KERALA STATE CIVIL SUPPLIES CORPORATION LTD. – Appellant
Versus
THE ASSISTANT PROVIDENT FUND COMMISSIONER EMPLOYEES PROVIDENT FUND ORGANISATION, THIRUVANANTHAPURAM – Respondent
W.A. No. 971 of 2023
Decided On : 22-08-2024
EMPLOYEES' PROVIDENT FUNDS - Sections 7Q, 14B, 8F(3) of the Employees’ Provident Funds and Miscellaneous Provisions Act, 1952 - The court discussed the provisions of Sections 7Q and 14B of the Act, emphasizing that while damages can be imposed for delayed payments, the authority must consider the circumstances surrounding the delay. The interpretation of 'may recover' in Section 14B was pivotal, indicating that discretion must be exercised in determining damages, which should not exceed 25% but can be lower based on the employer's justification for delay.
Fact of the Case:
The Kerala State Civil Supplies Corporation Ltd. and its Regional Manager were challenged by a notice issued for belated payments of provident fund contributions. After various legal proceedings, the respondent imposed damages under Section 14B of the Act, which the appellants contested, arguing that the respondent failed to exercise discretion appropriately and did not consider their reasons for delay.
Finding of the Court:
The court found that the respondent did not adequately consider the bona fides of the appellants' reasons for delay in payment. It held that while the imposition of damages was justified, the rate should reflect the circumstances, leading to a reduction of the damages from the previously imposed rate to 15%.
Issues: Whether the respondent exercised discretion appropriately in imposing damages under Section 14B of the Act, and whether the reasons for delay in payment were considered adequately.
Ratio Decidendi: The court reiterated that while mens rea is not required for imposing damages under Section 14B, the authority must consider the genuineness of the reasons for delay when determining the quantum of damages. The discretion to impose damages must be exercised judiciously, taking into account the specific circumstances of each case.
Final Decision: The court varied the impugned judgment, allowing the writ petition to the extent of reducing the damages imposed under Section 14B to 15% and directed recalculation of the amount accordingly.
JUDGMENT :
P.G. AJITHKUMAR, J.
1. The judgment dated 31.01.2023 dismissing W.P.(C) No. 2084 of 2012 is under challenge in this appeal filed under Section 5(i) of the Kerala High Court Act, 1958. The Kerala State Civil Supplies Corporation Ltd, and its Regional Manager, Thiruvananthapuram are the appellants.
2. The respondent issued a notice dated 24.09.2004 to the appellants by exercising the powers conferred under Sections 7Q and 14B of the Employees’ Provident Funds and Miscellaneous Provisions Act, 1952 (the Act) owing to the belated payment of provident fund contribution, employees’ family pension fund contribution, deposit linked insurance fund contribution, administrative charges and inspection charges for the period from March, 1997 to February, 2003. The interest component was Rs.1,21,366/-and damages was Rs.3,50,736/-totalling Rs.4,72,102/-. After considering the objection raised about the computation, the amount was refixed as per Ext. P3 order dated 16.12.2004 as Rs.2,58,159/-i.e., 68,536 under Section 7Q and Rs.1,89,623/-under Section 14B of the Act. Against that order an appeal was preferred before the Provident Fund Appellate Tribunal, New Delhi. However, the respondent initiated action under Section 8F(3) of the Act for recovery of the amount.
3. The petitioner therefore approached this Court by filing W.P.(C) No. 871 of 2005. This Court vide judgment dated 10.01.2005 directed the appellants to deposit the interest portion within a week and directed the Appellate Tribunal to dispose of the appeal within three months. In compliance with the direction, interest portion was deposited. The appellate Tribunal vide order dated 31.12.2005 dismissed the appeal which was assailed in this Court by filing W.P.(C) No. 19336/05. This Court vide Ext.P4 judgment dated 16.02.2011 set aside the order and remanded the case back to the Commissioner. As directed in Ext.P4 judgment of this Court, the respondent held a personal hearing and passed order dated 02.06.2011, which is Ext.P5. Challenging that order the appellants filed the present writ petition. It was contended that the Ext.P5 was not sustainable in law on the ground that the respondent failed to understand the words 'may recover' occurring in Section 14B of the Act and omitted to exercise its discretion. The materials on record substantiated that there was no malafide action or inaction on the part of the appellants in not depositing the contribution in time and therefore the damages as prescribed under Section 14B of the Act in total should not have been imposed. It was contended that the respondent did not consider such aspects while issuing Ext.P5 order.
4. The learned Single Judge relying on the principle of law laid down by the Apex Court in Horticulture Experiment Station Gonikoppal, Coorg v. Regional Provident Fund Organization, (2022) 4 SCC 516 held that there was no merit in the writ petition. The resultant dismissal of the writ petition is under challenge in this appeal.
5. Heard the learned Standing Counsel for the appellants and the learned Standing Counsel for the respondent.
6. The interest that was found due on account of the delayed remittance of the provident fund contribution and other remittances, under Section 7Q of the Act was already paid. Of course, that was in terms of the direction of this Court as per the judgment in W.P.(C) No. 871 of 2005. The challenge now is confined to the damages imposed under Section 14B of the Act in terms of Ext.P5.
7. The essential contention is that this Court in terms of Ext.P4 judgment directed the respondent to consider objectively the objections the appellants have raised, but Ext.P5 sans any such consideration. The learned Standing Counsel for the appellants would submit that the law laid down in the Horticulture Experiment Station (2022) 4 SCC 516 was not applied appropriately and that resulted in the dismissal of the writ petition. The learned Standing Counsel places reliance on the decision of the High Court of Karnat
Central Board of Trustees v. Bake N. Joy, Hot Bakery
Hindustan Times Ltd. v. Union of India and others
Horticulture Experiment Station Gonikoppal, Coorg v. Regional Provident Fund Organization
Regional Provident Fund Commissioner v. HMT Ltd. W.A. No. 587 of 2016
Standard Furniture, Calicut v. Registrar EPF Appellate Tribunal and another
AI
The discretion of the Provident Fund Commissioner in imposing damages under Section 14B must consider the bona fides of the employer's reasons for delay, and damages can be set at a rate lower than t....
For the imposition of damages under Section 14B of the Employees Provident Fund and Miscellaneous Provisions Act, 1952, the establishment of mens rea is not a mandatory requirement. Once a delay in r....
Financial difficulties do not justify delayed remittance of provident fund contribution, and lack of mens rea is not a sufficient defense.
The court established that while imposing damages under the Act, the circumstances around the delay should be considered, rather than imposing 100% damages mandatorily.
Damages for delayed payment under the EPF Act cannot exceed the amount of arrears, and interest cannot be levied on penal amounts without statutory authority.
Employers are liable to pay damages for delayed contributions to the provident fund, assessed based on beneficiary losses, irrespective of the reasons for delay.
Mens rea is not required for imposing damages under Section 14B of the Act; damages can be levied based on default in payment of provident fund contributions.
Damages under S.14B of the Employees' Provident Funds Act are penal and not compensatory, allowing for mechanical imposition up to 25% without ascertaining actual loss.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.