IN THE HIGH COURT OF KERALA AT ERNAKULAM
Sathish Ninan, J.
Kerala Water Authority and other - Appellants
Versus
Joy.K.Mathew - Respondent
RFA No. 193 of 2005
Decided On : 08-01-2024
(A) Contract Law - Breach of Contract - The plaintiff entered into a contract for construction, which was not completed within the stipulated time. The defendants completed the work through another contractor. The plaintiff claimed damages for the work done. The trial court awarded Rs. 1,89,312/- which was found to be unsubstantiated. (Paras 2, 4, 8)
(B) Damages - The defendants did not quantify any damages resulting from the alleged breach by the plaintiff. The absence of a counterclaim or set-off by the defendants was noted. (Paras 7, 8)
Facts of the case:
The plaintiff entered into a contract for construction but failed to complete it on time, leading the defendants to hire another contractor. The plaintiff sought damages for the work done.
Findings of Court:
The trial court's award of Rs. 1,89,312/- was modified to Rs. 1,61,861/- based on the defendants' calculations and the absence of a counterclaim.
Issues: The main issue was whether the plaintiff was entitled to the claimed amount and if the trial court's findings were substantiated.
Ratio Decidendi: The court found that the plaintiff was entitled to payment based on the expert's assessment and the lack of a counterclaim from the defendants.
Result: The appeal is allowed in part, modifying the amount payable to the plaintiff.
JUDGMENT :
Sathish Ninan, J.
The decree for damages is under challenge by the defendants in the suit.
2. On 22.09.1994, the plaintiff entered into Ext.A1 contract with the defendants for construction of an inspection bungalow. The period fixed for completion was 12 months. Admittedly, the plaintiff did not complete the construction within the period. Subsequently the defendants completed the work employing another contractor. According to the plaintiff, the default occurred due to the conduct of the defendants in varying the plan and also the delay in providing the varied plan. The plaintiff claimed that there has been enhancement in the cost and is entitled for hike in rates. The suit is for the value of the works done by the plaintiff.
3. The defendants denied the plaint allegations. It was contended that the plaintiff is at fault for having committed breach of the contract. The alleged variation in plan etc was denied.
4. The trial court granted a decree for realisation of Rs. 1,89,312/- with interest. The same is under challenge.
5. I have heard the learned counsel on either side.
6. Both the plaintiff and the defendants blame each other for having committed breach of the contract. According to the plaintiff, there had been variation in the plan and there was delay in providing such plan. The allegation is denied by the defendants. Admittedly, the work was not completed by the plaintiff within the time and the defendants caused it to be completed through another contractor.
7. It is relevant to note that, though the defendants allege that the plaintiff committed breach of contract, there is no claim raised against him for damages. The damages if any, resulted to the defendants consequent to such breach has not been quantified. The defendants do not have a case that the damages caused to them consequent on the breach committed by the plaintiff has been appropriated. There is no plea of set off or counter claim.
8. The total work that was done by the plaintiff has been assessed by an expert Commissioner issued in O.S.No.264 of 1995, an earlier suit filed by the plaintiff against the defendants in relation to the very same work. The said suit was filed at a point of time when steps were taken by the defendants to re-tender the work. Ext.A30 is the report. Based on such measurement, the defendants have calculated the amounts payable to the plaintiff. Going by the calculations stated by the defendants, the balance amount remaining to be paid to the plaintiff is Rs. 1,61,861/-. The finding of the trial court that the amount payable to the plaintiff is Rs. 1,89,312/- is not substantiated by materials. As noticed earlier, in the absence of any claim of appropriation, set off or counter claim, the plaintiff is entitled for payment of the said amount. The decree and judgment of the trial court, insofar as it allows the plaintiff to realise Rs. 1,89,312/- is liable to be interfered with to the above extent. No other interference is called for.
Resultantly, the appeal is allowed in part. The decree and judgment of the trial court will stand modified, allowing the plaintiff to realise Rs. 1,61,861/-, with interest thereon at the rate of 6% per annum from 07.02.1997 (date of suit notice) till realisation, from the defendants and their assets. No costs.
The plaintiff is entitled to payment for work done despite breach allegations, as the defendants failed to substantiate their claims for damages.
When a construction contract's work valuation is assessed by a court-appointed expert with the consent of both parties, and the valuation matches the agreed contractual rates, the appellate court wil....
A contractor is entitled to a portion of extra costs incurred due to delays when both parties share responsibility.
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
Parties must adhere to contract terms, and failure to substantiate claims of loss due to alleged breaches leads to liability for unpaid dues.
The court upheld that a party may be compensated for work done despite absence of a written contract when the other party benefits, reinforcing principles of unjust enrichment under Section 70 of the....
The completion time as the essence of the contract and the discharge of financial liabilities by specific payment mentioned in the agreement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.