SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ker) 2133

IN THE HIGH COURT OF KERALA AT ERNAKULAM
C. JAYACHANDRAN, J.
 
Sudheesh A.T., S/o. Thankachan – Petitioner
Versus
The Director of Mining And Geology Department, Government of Kerala and Ors. – Respondents
WP(C) No. 9795 Of 2023, WP(C) No. 13492 Of 2023, WP(C) No. 19300 Of 2023, WP(C) No. 27035 Of 2023, WP(C) No. 4510 Of 2024, WP(C) No. 10121 Of 2024, WP(C) No. 18741 Of 2024, WP(C) No. 19999 Of 2024, WP(C) No. 20487 Of 2024, WP(C) No. 26197 Of 2024, WP(C) No. 27291 Of 2024, WP(C) No. 28314 Of 2024, WP(C) No. 29509 Of 2024, WP(C) No. 29919 Of 2024, WP(C) No. 31355 Of 2024, WP(C) No. 31398 Of 2024, WP(C) No. 35059 Of 2024, WP(C) No. 15219 Of 2025, WP(C) No. 19599 Of 2025, WP(C) No. 21958 Of 2025, WP(C) No. 21964 Of 2025.
Decided On : 07-08-2025
 

Advocates Appeared:
For the Petitioner: Sri. Philip J. Vettickattu, Smt. Sajitha George, Smt. Neenu Bernath.
For the Respondents: Sri. V. Girishkumar, Senior Panel Counsel, M.P. Sreekrishnan, SC, T.P. Sajan, Special Government Pleader (Forest).

Environmental clearances requiring wildlife clearance within a specified distance must comply with established guidelines, and petitioners are not liable for additional wildlife clearance as mandated by SEIAA.

Headnote:(A) Environmental Clearance - Conditions imposed by State Environmental Impact Assessment Authority (SEIAA) - Wildlife Clearance required within 10 km of Wildlife Sanctuaries - Supreme Court Orders on similar conditions significant for current writ petitions - Petitioners seek similar relief as granted by Supreme Court in G.V-III Order dated 29.05.2025. (Para 1, 5, 10)

(B) Environmental and Forest Clearances - Adherence to Office Memorandum dated 17.05.2022 not stayed, but cannot operate independently - Conditions for quarrying operations within specified distance from Wildlife Sanctuary must consider established guidelines - No merit in objections raised against petitioners similar treatment. (Para 6, 10)

Facts of the case:
Petitioners in multiple writ petitions contest conditions required for Environmental Clearance, notably the necessity for Wildlife Clearance within 10 km of designated wildlife sanctuaries, referencing Supreme Court’s past rulings to argue for relief.

Findings of Court:
Court declares that petitioners are not liable to obtain wildlife clearance and quashes the condition in respective Environmental Clearances requiring it; directs further processing of quarry lease applications without the said clearance.

Issues: Whether the conditions imposed by SEIAA regarding wildlife clearance conflict with established Supreme Court rulings on similar matters.

Ratio Decidendi: The court distinguishes the authority of SEIAA’s conditions from past Supreme Court rulings and finds having no merit in respondents' argument not to allow quarrying activities near protected areas within the defined distances.

Result: Writ Petitions allowed.

Table of Content
1. environmental clearance conditions for mining projects (Para 1 , 2 , 3)
2. arguments on the applicability of supreme court orders (Para 4 , 5)
3. court's interpretation of supreme court directives (Para 6 , 7 , 8 , 9)
4. quashing of unnecessary wildlife clearance requirements (Para 10)

COMMON JUDGMENT :

In this batch of 21 cases, all the writ petitioners essentially seek the same relief, which pertains to a condition incorporated in the Environmental Clearance issued by the State Environmental Impact Assessment Authority ('SEIAA' for short). One such condition, incorporated in the case of petitioner in W.P.(C) No.28314/2024, is extracted here below:

“Condition No.5: Since, the project is located within 10km of Peechi Vazhani Wild Life Sanctuary and Chimmony Wild Life Sanctuary, the project proponent has to obtain Wild Life Clearance from the SCNBWL as per the OM dated 17/05/20225 of MoEF & CC as per the directions in the Hon’ble Supreme Court judgment dated 26/04/2023 in I.A.13177 of 2022 before the commencement of mining”.

In respect of a similar condition imposed in the Environmental Clearance issued by SEIAA, the Hon’ble Supreme Court passed a recent Order dated 29.05.2025 in I.A.Nos.132289/2025, 132290/2025 and 138819/2025 in W.P.(C) No.202/1995. As per the said Order, the operations in the Petitioner’s quarry, which is located 7.5 km away from the Peechi-Vazhani Wildlife Sanctuary, were permitted, repelling the objections of the Ministry of Environment, Forest and Climate Change ('MoEF & CC', for short) in this regard. The petitioners herein seek similar treatment in accord with the said Order of the Supreme Court.

2. Heard the learned counsels for the petitioners; learned Standing Counsel for SEIAA,; learned Central Government Counsel for MoEF & CC; learned Special Government Pleader (Forest) and the learned Government Pleader. Perused the records.

3. As regards the interpretation of the said Order, considerable arguments were advanced by the respective parties. While the petitioners contend that similar condition, imposed by the SEIAA in the Environmental Clearance is the subject matter of these Writ Petitions, wherefore, the above Order dated 29.05.2025 of the Hon'ble Supreme Court would squarely govern the situation, learned Standing Counsel for SEIAA would submit that the above Order cannot substitute the requirements of O.M. dated 17.05.2022 of the MoEF & CC, as also, the directions contained in the earlier Orders passed by the Hon'ble Supreme Court in the same Writ Petition.

4. This Court will straight away refer to the objections raised by the learned Standing Counsel for SEIAA. Learned Standing Counsel would submit that three Orders have been passed by the Hon'ble Supreme Court in In Re: T.N.Godavarman Thirumulpad v. Union of India and Others . The first is one dated 3rd June, 2022 (hereinafter referred to as ‘G.V-I’). Reference to various paragraphs of G.V-I is required and it is clarified that the paragraph numbers being referred hereunder are as contained in the Order (G.V-I) downloaded from the Supreme Court portal. Learned Standing Counsel invited the attention of this Court to paragraph no.44 of G.V-I Order, which contains several directions. As per paragraph no.44(a), a minimum distance of 1 km is prescribed as Eco-Sensitive Zone (ESZ) measured from the demarcated boundary of a Protected Forest (National Park or Wildlife Sanctuary) for conducting the activities prescribed in the Guidelines dated 09.02.2011. Paragraph no.44(b) deals with the situations, where ESZ has already been prescribed by law, which goes beyond 1 km buffer zone. In such cases, the wider buffer zone prescribed under the statutory instrument for the particular National Park or Wildlife Sanctuary has to be maintained. Paragraph no.44(d) is a complete prohibition for mining within the National Parks and Wildlife Sanctuaries. Paragraph no.44(e) deals with activities already undertaken within 1 km or the extended buffer zone of a W

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top