SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ker) 2325

IN THE HIGH COURT OF KERALA AT ERNAKULAM
NITIN JAMDAR, C.J., BASANT BALAJI, J.
Cochin Port Trust, Represented By Its Chief Engineer - Appellant 
Versus 
East India Engineers, Represented By Its Proprietor Vineeth Sharama - Respondent 
Arb.A No. 9 of 2022
Decided on : 25-07-2025

Advocates:
Advocate Appeared:
For the Appellant : SRI K ANAND, SMT.LATHA ANAND, SRI.M.N.RADHAKRISHNA MENON, SRI.K.R.PRAMOTH KUMAR, SRI.S.VISHNU (ARIKKATTIL), SRI.RADHAKRISHNA PILLAI B, SHRI.SIDHARTH P.S., SHRI.BHARATH MURALI
For the Respondent: SMT.NIDHI JACOB, SRI.SUKUMAR NAINAN OOMMEN, SRI.SHERRY SAMUEL OOMMEN

An arbitral award can be set aside if it is patently illegal and contrary to public policy, especially when it exceeds the Arbitrator's jurisdiction by applying rates not stipulated in the contract.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Appeal against dismissal of petition to set aside arbitration award - The court found the award patently illegal and against public policy, as it exceeded jurisdiction by applying DSR 2014 rates not included in the contract. The award was set aside in part. (Paras 24, 40)

(B) Judicial Review - The scope of judicial interference in arbitral awards is limited; courts may only intervene on specific grounds outlined in Section 34, including patent illegality and conflict with public policy. (Paras 15, 38)

Facts of the case:
The Appellant challenged an arbitration award favoring the Respondent concerning a contract for construction works, asserting that the Arbitrator made an erroneous award by applying rates not stipulated in the contract. (Paras 1-2)

Findings of Court:
The award was found to exceed the Arbitrator's authority and was based on rates not included in the contract, rendering it patently illegal. (Paras 24, 40)

Issues: Whether the Commercial Court correctly exercised its jurisdiction under Section 34 of the Act to set aside the arbitral award. (Paras 15, 40)

Ratio Decidendi: The court ruled that the Arbitrator's reliance on DSR 2014 rates was a clear contravention of the contractual terms, justifying the setting aside of the award. (Paras 24, 40)

Result: Appeal partly allowed; the invalid portion of the award was set aside.

Table of Content
1. challenge to arbitration award (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8)
2. arguments on jurisdiction and grounds for setting aside award (Para 10 , 11 , 12 , 13 , 14)
3. analysis of patent illegality and public policy (Para 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40)
4. partial allowance of appeal based on severability (Para 41)

JUDGMENT :

Basant Balaji, J.

1. This Appeal challenges the dismissal of O.P.(Arb.) No.70 of 2020 by the Commercial Court, Ernakulam. The Original Petition, filed by the Appellant (then Petitioner) against the Respondent under Section 34 of the Arbitration and Conciliation Act, 1996, (the Act) sought to overturn an arbitration award dated 26 March 2018.

2. Tenders were floated by the Appellant for the installation of a 200 MM Dia Ductile Iron Pumping Line (Part 1) and road rectification works (Part 2) at various locations within Willington Island. The Appellant’s estimates for these works were Rs.1,61,78,681/- for Part 1 and Rs.27,03,012/- for Part 2. The Respondent submitted the lowest bid for Part 1 at Rs.1,81,73,600/-, which was 12.33% above the estimate. However, for Part 2, the Respondent quoted Rs.9,76,363/-, a figure 63.88% below the estimated cost. A notable discrepancy was observed in the Respondent’s bid for Item No.5 of Part 2, which is the main item, with an estimated value of Rs.8,95,141/-, was quoted at 86.83% below the estimate. Given the contractual payment terms, which allowed for the release of 90% of the quoted amount upon the completion of Part 1, the Appellant became concerned that the Respondent’s low bid for Part 2, particularly for Item No. 5, would render the existing security deposit grossly inadequate to ensure the completion of Part 2 by other agencies in the event of the Respondent’s non-performance. To mitigate this risk, a meeting was convened on 20 April 2015, during which the Respondent unconditionally assented to the retention of a sum equivalent to Rs.12 lakhs or 7% of the quoted amount, whichever was greater. Based on this critical undertaking, the Appellant proceeded to award the work to the Respondent via a work order dated 14 May 2015.

3. The contractual period was subsequently extended on multiple occasions, with the Appellant expressly reserving its right to claim Liquidated Damages (LD) as per Clause 2 of the General Conditions of Contract (GCC). For Part 2 of the works, the Appellant was obligated to supply only granite red stone, as the rubble recovered from the existing soling was to be utilized for the new soling work, with the Appellant supplying only the deficit quantity.

4. During the execution of Part 1 work, the Appellant issued Annex.R6, notifying the Respondent that the extended contract period had expired on 18 April 2016, and directing the immediate completion of road rectification works prior to the monsoon season. In response, the Respondent, via Annex.C12, asserted that Part 2 works would be performed if the rates were enhanced based on DSR 2014 plus 46%, and requested a consent letter to that effect. The Appellant issued another communication, Annex.R7 dated 6 May 2016, demanding completion of the works and cautioning that failure to comply would compel the Appellant to terminate the contract at the Respondent’s risk and cost. The Respondent, in Annex.C13 dated 13 May 2016, reiterated its position, confirming that work would resume upon receipt of a consent letter reflecting the revised DSR 2014 plus 46% rates.

5. On 27 September 2016, through Annex.C8, the Respondent formally requested the Appellant to appoint an Arbitrator in accordance with Clause 25 of the Conditions of Contract, simultaneously advising that all activities were halted pending the proposed arbitration. As a result of the Respondent’s cessation of Part 2 work, the Appellant issued a show cause notice dated 17 October 2016.

6. In its reply, Annex.R53 dated 21 October 2016, the Respondent ag

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top