SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ker) 2868

IN THE HIGH COURT OF KERALA AT ERNAKULAM
P.M.Manoj, J.
Navas Kacheery And Ors. – Petitioners
Versus
State Of Kerala And Ors. – Respondents
WP(C) NO. 33681 OF 2019, WP(C) NO. 2168 OF 2019
Decided On : 08-09-2025

Advocates Appeared:
For the Petitioner: Sri.K.C.Santhoshkumar, Smt.K.K.Chandralekha, Smt.Anupama Johny, Smt.K.S.Sudha, Sri.Sree Govind
For the Respondent: Sri.K.K.Chandran Pillai (Sr.), Sri.Mahesh V Ramakrishnan, Smt.S.Ambily, Smt.Namitha Nambiar, Sri.Saji Thomas, Shri.Micky Thomas, Smt.M.Meena John, Sc, , Sri.E.G. Gorden, Sr. Govt. Pleader.

Exemptions from building rules must comply with procedural requirements; failure to provide natural justice in administrative decisions warrants judicial intervention.

Headnote:(A) Kerala Municipality Building Rules, 1999 - Rule 3C - Exemption granted under Rule for reconstruction - Petitioner’s challenge against the exemption and building permit issued is based on allegations of misrepresentation and lack of compliance with mandatory building rules. Findings indicate the procedure was violated and allow for interpretation regarding the decision's legality considering public interest and compliance. (Paras 3, 11, 23, 40)

(B) Natural Justice - Cancellation of occupancy certificate without hearing - The court emphasized that the cancellation was arbitrary, lacking adherence to procedural requirements, thus infringing principles of natural justice. (Paras 38, 39)

Facts of the case:
Two writ petitions were filed challenging exemptions granted under building rules and the resultant occupancy certificate for a reconstruction project. Issues arose regarding compliance with Kerala Municipality Building Rules, 1999.

Findings of Court:
The exemption order was granted without appropriate approval from the municipal council and documented misrepresentation.

Issues: Legality of the exemption granted and subsequent building permits, and cancellation of the occupancy certificate.

Ratio Decidendi: The court held that the exemption was improperly obtained and that the cancellation of the occupancy certificate contravened natural justice by failing to provide a hearing.

Result: The court quashed the cancellation order of the occupancy certificate and dismissed one of the writ petitions.

Table of Content
1. jurisdiction of high court over local building ordinance (Para 1 , 3 , 4)
2. claim of lack of locus standi in challenging the administrative action (Para 9 , 10)
3. exemptions from building rules and natural justice considerations (Para 11 , 12 , 22)
4. requirements for the issuance and cancellation of occupancy certificates (Para 35 , 36)
5. decision to quash the cancellation of the occupancy certificate (Para 40)

JUDGMENT :

P.M.Manoj, J.

Originally, three writ petitions came up for consideration today, i.e., WP(C) No. 237/19, 2168/2019 and 33681 of 2019. The first writ petition among these was preferred, challenging an order of exemption granted under Rule 3C of the Kerala Building Rules, 1999 as per GO(Rt) No.1617/2018/LSGD dated 14.06.2018. Whereas the second writ petition challenges the same order and also the consequential building permit issued by the Kannur Municipal Corporation, and the report submitted by the Kannur Municipal Corporation before the Chief Town Planner for consideration of the exemption to be granted. On the other hand, the beneficiary of the above orders has preferred the third writ petition challenging the order of cancellation of occupancy certificate which was issued on completion of the construction pursuant to the exemption order and the building permit so issued.

2. Since the counsel appearing for the petitioner in W.P.(C) No.237/2019 had relinquished the vakalath, and despite repeated postings there was no representation for the petitioner, the said writ petition was dismissed for non-prosecution. Accordingly, only the remaining two writ petitions are required to be adjudicated.

3. It is the case of the petitioner in WP(C) No. 2168 of 2019 that the exemption granted under Rule 3C of the Kerala Municipality Building Rules, 1999 (for short ‘KMBR,1999’) to respondents 4 to 8 as per Ext.P11 and the Building permit issued as per Ext.P12 on the basis of Ext.P10 recommendation by the Municipal Corporation to the Chief Town Planner are in violation of the relevant provisions KMBR, 1999.

4. The case projected by the petitioner is that an extent of 0.70 Ares (70 Mt. Squares) of property in Re-survey 66/4 of Edakkad Village and Kannur karar Desom along with a two-storied tiled building having building Nos.EP 10/238-243 was purchased by respondents 4 to 8 as per Ext.P1 sale deed from Kachayi Puthiya Purayil Beepathu. While the said property was in possession of the aforementioned Beepathu, a small extent was taken by the Government for widening of the road. The remaining property alone was sold to respondents 4 to 8. Thereafter, no portion was taken from respondents 4 to 8 for the purpose of widening of the road. It is further contended that the said building collapsed due to heavy rain while it was in their possession. Due to the specific nature of the property, it was not possible to reconstruct the building in compliance with the provisions of KMBR, 1999. However, without obtaining any permit from the 2nd respondent Municipality, they started constructing the building on 18.06.2017. The petitioner challenged the same by instituting O.S. No.277/2017 before the Munsiff’s Court, Kannur, seeking a decree of permanent prohibitory injunction. An application for temporary injunction was also filed as I.A. No.1439/2017, which was allowed, restraining the respondents from proceeding with the construction.

5. The Corporation also filed a written statement admitting that the construction had been carried out by respondents 4 to 8 without any permit, and that upon noticing the same, a stop memo was issued. It was further stated that the Corporation could not grant a permit for the proposed construction with the existing specifications. Respondents 4 to 8 herein also preferred written statement contending that the property was taken over from them for widening of the road.

6. It is further contended that the said building was a commercial building. However, respondents 4 to 8 preferred an application before t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top