IN THE HIGH COURT OF KERALA AT ERNAKULAM
Ziyad Rahman A.A., J.
K Muhammad Haji - Petitioner
Versus
Kerala Road Fund Board Project Management - Respondent
WP(C) NO. 48193 OF 2025
Decided On : 10-03-2026
| Table of Content |
|---|
| 1. petitioner's challenge to the bidding process (Para 1 , 2) |
| 2. petitioner's qualifications and discrepancies in respondent's tender (Para 3 , 4) |
| 3. respondents' objection and documentary evidence (Para 5 , 6) |
| 4. counter affidavits and detailed explanations provided by the respondents (Para 7 , 8 , 9) |
| 5. prime contractor definition and its implications on contract qualifications (Para 10 , 11) |
| 6. conditions for valid tender documentation and completion accuracy (Para 12 , 13) |
| 7. judicial review standards in tender disputes (Para 14 , 15) |
| 8. acceptability of bank guarantees and compliance with requirements (Para 16 , 17) |
| 9. financial turnover and its acceptance by the evaluation committee (Para 18 , 19) |
| 10. judicial restraint in tender decision-making (Para 20 , 21 , 22 , 23) |
JUDGMENT :
Ziyad Rahman A.A., J.
This writ petition is submitted by a registered contractor being aggrieved by the proposal to finalize the bidding process notified as per Ext.P1, in favour of the 3rd respondent, as according to the petitioner, the 3rd respondent is not possessing the necessary qualification as contemplated in the notice inviting tender (NIT).
2. The facts which led to the filing of this writ petition are as follows:
The 1st and 2nd respondents published a tender notification dated 30.10.2025, inviting bids for carrying out the work “KIIFB-AIRPORT LINK-IMPROVEMENTS TO CHORUKALA- BAVUPARAMBA- MANICHERIKADAU-CHEKKIYATTUKAVUMAYYIL - ETTEYAR KOLOLAM- CHALODE ROAD KM 0/000 TO 22/550 AND TALIPARAMBA TAGORE VIDYANIKETHAN-ALLAMKULAM-SIRSYED COLLEGE- BRANDHANKUNNU ROAD KM 0/000 TO 2/660 IN KANNUR DISTRICT” The petitioner and the 3rd respondent along with some other persons submitted tenders in respect of the same. In the said tender process, when the financial bids were evaluated, the petitioner was declared as L2 whereas, the 3rd respondent was declared as L1. Exhibit P3 is the result published on 18.12.2025.
3. According to the petitioner, even though the petitioner fulfilled all the requirements regarding the qualification as contemplated in Ext.P1-NIT and Ext.P2 tender documents published by the 1st respondent, the 3rd respondent did not qualify the said requirements on several grounds. In the writ petition, the petitioner highlighted the discrepancies with regard to the qualifications of the 3rd respondent, which are as follows:
(i) The 3rd respondent failed to show the previous experience as contemplated under clause 2.2. of the tender documents, which provided previous experience to the tune of 40% of the value of the current work as an essential pre-qualification which must have been in relation to a work conducted by the bidder as a prime contractor for Government/semi Government clients during the last five years ending last day of the month previous to the month in which the bid applications are invited. According to the petitioner, as per the bid documents submitted by the petitioner, as evidenced by Ext.P4, the experience certificate dated 10.11.2025 was produced. The same contains two works namely; (1) Rebuild Kerala Initiative (RKI-12) Upgrading of Uruvachal-Manakkai_Valayal-Keezhallur- Therur- Palayod- Vallaparamba – Karimbala – Kodoliparam- Cholakkari Nerammal – Maruthayi Road (Total 18.46 km) in Kannur District on EPC Mode- executed under Engineering Projects (India) Ltd. (EPI) with an accepted PAC of Rs.98.91 crore and 97.15% completion, performance rated as Good and (2) KIIFB – Improvements to Meppadi-Chooramala Road in Wayanad District- executed under KRFB-PMU (Agreement No.56/PWD004- 103/PD.PMU-KRFB/2018-19 dated 5.11.2018) with a sanctioned PAC of Rs.39.23 crore, completed satisfactorily as certified by the Project Director, KRFB). According to the petitioner, the completion certificate produced by the 3rd respondent for the 1st work was only a provisional certificate dated 10.3.2025. As per the same, 97.15% of the work alone was completed and the same was issued subject to the condition that, the contractor has agreed and a
Surguja Bricks Industries Company (M/s.) v. State of Chhattisgarh
Judicial review of tender decisions should respect the expertise of evaluation committees unless evidence of arbitrariness or unreasonableness is demonstrated.
Point of Law : Tender /Contract - allocation of full marks for the 'Financial Criteria' was not sustainable, for want of relevant documents submitted along with the Tender and this by itself would di....
The evaluation of tender bids must comply strictly with the qualifications defined in the tender, and any deviation or submission of erroneous documents leads to disqualification.
The person claiming justice and equity must come with clean hands.
Government contract – Tender - The judicial review on State administrative activities is limited inasmuch as the Constitutional Courts do not sit on appeal as to whether the decision is good and soun....
Judicial review in tender matters is limited to assessing procedural fairness, not the merits of the tender conditions, which are determined by the tendering authority.
The court upheld the tendering authority's discretion in setting eligibility criteria, emphasizing limited judicial review focused on procedural fairness rather than the merits of the decision.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.