IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
Anoop Kumar Dhand, J.
State Of Rajasthan Through Executive Engineer – Appellant
Versus
M/s R.R. Constructions Company Through S.K. Damani – Respondent
S.B. Civil Miscellaneous Appeal No. 3552/2016
Decided On : 13-10-2022
Arbitration - Appeal - Section 37 of the Arbitration and Conciliation Act, 1996 - [DEVELOPMENT OF ROAD - ARBITRATION - 1996 ACT, SECTION 34] - The court dismissed the appeal under Section 37 of the Arbitration and Conciliation Act, 1996, as the directions issued by the Arbitrator were found to be just and reasonable. The court cited the limited jurisdiction provided to the court under Section 34 of the Act and referred to relevant case laws to support its decision.
Fact of the Case:
The appellant issued a tender notice for the development of a road, and a dispute arose between the parties regarding the payment. The matter was referred to the Arbitrator, who directed the appellant to pay a certain amount with interest. The appellant submitted objections under Section 34 of the Act, which were rejected by the Court below.
Finding of the Court:
The Court found that the directions issued by the Arbitrator were just and reasonable, considering the contract and the amount involved. It cited the limited jurisdiction provided to the court under Section 34 of the Act and referred to relevant case laws to support its decision.
Issues: Dispute over payment for road development, rejection of objections under Section 34 of the Arbitration and Conciliation Act, 1996.
Ratio Decidendi: The court's decision was influenced by the limited jurisdiction provided to the court under Section 34 of the Act and the just and reasonable nature of the directions issued by the Arbitrator.
Final Decision: The appeal filed by the appellant was dismissed, and all pending applications were also dismissed. The Court directed the appellant to prepare a new demand draft in favor of the respondent within two months.
JUDGMENT
1. Instant appeal has been preferred by the appellant under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ’the Act of 1996’) against the order dated 14.03.2016 passed by the Court of Additional District Judge No. 3, Jaipur Metropolitan, Jaipur (for short, ’the Court below’) by which the objections filed by the appellant against the award dated 16.12.2003 have been rejected.
2. The facts, in brief, of the case are that the appellant issued a tender notice dated 23.01.1991 for the development of the Sikar Road in four lane from Military Canteen to Municipal Limit 237 KM to 247 KM. The tender offered by the respondent was accepted and thereafter the work order was issued in favour of the respondent and the agreement was also executed. The work was to be commenced with effect from 26.03.1991 and it was supposed to be completed till 25.03.1992. The respondent had completed the work of amount of Rs. 34,51,573 when the amount was released the dispute arose between the parties and in terms of the agreement clause mentioned in the agreement the matter was referred to the Arbitrator for resolving the dispute between the parties. After considering the documents, facts and material available on the record the Learned Arbitrator passed an award in favour of the respondent directing the appellant to pay an amount of Rs. 71,573/- with interest @ 12% per annum with effect from 20.06.1995 till 15.12.2003 and thereafter, further direction was issued to pay interest @ 18 % per annum from the date of the award till the date of actual payment .
3. Feeling aggrieved and dis-satisfied by the impugned award dated 16.12.2003, the appellant submitted objections before the Court of Additional District Judge No.3, Jaipur Metropolitan Jaipur under Section 34 of the Act of 1996 and those objections were rejected by the Court below vide order dated 14.03.2016 by observing that the interest was awarded by the Tribunal looking to the commercial contract between the parties.
4. Feeling aggrieved by the aforesaid order dated 14.03.2016, the appellant has submitted the instant appeal before this Court on a limited submission that the interest @ 18% per annum awarded by the Arbitrator from the date of passing of the award till the actual date of payment is excessive.
5. Perusal of the impugned award indicates that the dispute arose between the parties in the year 1995 and when the same was not resolved then the matter was referred to the Arbitrator and after considering the evidence and material available on the record, the Arbitrator directed the appellant to pay an amount of Rs. 71,573 with interest @ of 12 % per annum with effect from 20.06.1995 till 15.12.2003 that is the day prior to passing of the award and direction was issued to the appellant to pay interest @ 18 % per annum from the date of the award that is 16.12.2003 till the actual date of payment. The directions issued by the Arbitrator appears to be just and reasonable looking to the contract and the amount involved and the Court below has not committed any error in rejecting the objections submitted by the appellant. As per the judgment of the Hon’ble Apex Court in the case of Project Director, National Highways Vs. M. Hakeem and Another: reported in (2021) 9 SCC 1, a limited jurisdiction has been provided to the Court under Section 34 of the Act of 1996. The Hon’ble Apex Court in the case of M.Hakeem (Supra) has held that the Court should not modify the award unless and until illegality is there, in para 48 which has been observed as under:-
"48. Quite obviously if one were to include the power to modify an award in Section 34, one would be crossing the Lakshman Rekha and doing what, according to the justice of a case, ought to be done. In interpreting a statutory provision, a Judge must put himself in the shoes of Parliament and then ask whether Parliament intended this result. Parliament very clearly intended that no power of modification of an award exi
The limited jurisdiction provided to the court under Section 34 of the Arbitration and Conciliation Act, 1996, and the just and reasonable nature of the directions issued by the Arbitrator influenced....
The main legal point established in the judgment is the limited scope for interference with arbitral awards under the Arbitration and Conciliation Act, 1996, and the discretion of the Arbitrator in a....
The court upheld the principle that arbitral awards should not be interfered with unless there is a clear violation of public policy or a patent illegality.
The court confirmed that judicial interference in arbitral awards is limited to specific grounds, emphasizing respect for the arbitral process and the finality of awards.
Setting aside arbitral award – Illegality must go to root of matter and cannot be of a trivial nature.
The court affirmed that judicial intervention in arbitral awards is limited to grounds of public policy or patent illegality, emphasizing respect for the Arbitrator's findings.
The court emphasized the importance of substantiating claims regarding the excessiveness of interest rates and the need to provide evidence of prevailing interest rates when challenging arbitration a....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.