IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
MAHESH CHANDRA TRIPATHI, PRASHANT KUMAR, JJ.
State of Uttar Pradesh and Others - Appellants
Versus
M/S Virat Construction - Respondent
Appeal Under Section 37 of Arbitration and Conciliation Act 1996 No. 590 of 2023
Decided On : 25-10-2024
Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Appeal against arbitral award - The award was upheld by the Commercial Court, rejecting the State's application under Section 34 - The court emphasized that the scope of interference is limited to grounds of public policy or patent illegality - The Arbitrator's findings were detailed and based on evidence presented - The appeal was dismissed for lack of merit. (Paras 9, 10, 41, 45)
Facts of the case:
The appeal arose from an arbitral award concerning a construction contract where delays were attributed to the State's failure to provide materials and logistics, leading to financial losses for the contractor.
Findings of Court:
The court found no grounds for interference with the Arbitrator's award, which was detailed and well-reasoned, and upheld the Commercial Court's decision.
Issues: The main issues included whether the award was contrary to public policy and if the Arbitrator had acted beyond the scope of the contract.
Ratio Decidendi: The court reiterated that it does not sit in appeal over the merits of the award and can only intervene if the award is patently illegal or shocks the conscience of the court.
Result: Appeal dismissed.
JUDGMENT :
M.C. Tripathi, J.
1. Heard Sri Manish Goyal, learned Additional Advocate General assisted by Sri Devansh Rathore, learned Additional Chief Standing Counsel for the State-appellants and Sri Jagat Narayan Mishra, learned counsel for the opposite party.
2. The instant appeal under Section 37 of 1996 Act, [Arbitration and Conciliation Act, 1996] has been filed seeking quashing of the impugned judgment and order dated 14-02-2023 passed by the Presiding Officer, Commercial Court, Jhansi in Arbitration Case No. 31 of 2022 (State of U.P. Vs. M/S Virat Construction), arising out of Arbitration Case decided between the parties by the Sole Arbitrator on 03-05-2022.
Relevant factual aspects and background
3. A tender was invited on 01-08-2008 by the appellants for the construction of Head Regulator at Km.0.410 of Margin Bandh to protect the Banda City from the flood of Cane River. In response to it, the contractor/opposite party no.2/claimant applied and his bid was found to be responsive, when tender was opened on 10-09-2008. Accordingly, the tender was awarded to the claimant and letter of acceptance was issued on 07-11-2008. In accordance with the letter of acceptance dated 07-11-2008, the claimant was required to submit the balance security money plus stamp duty within ten days, which was duly complied by him. Thereafter both the parties entered into a contract agreement on 22-11-2008. As per the contract agreement the cost of the work was Rs.4,96,92,893.00 only. The date of commencement of the work was given as 22-11-2008 and the period of completion of the work was nine (09) months, hence the stipulated date of completion was given as 21-08-2009.
4. It is claimed by the opposite party no.2/claimant that since the time for execution of the contract was only nine months, so he immediately mobilised his equipments, machines, labours, staffs and other construction materials to the site with sincere intention to complete the work within stipulated time. However, he could not start the work because the appellants failed to finalise the logistics of the work before execution of the contract. The appellants also failed to issue the stock materials namely cement and tor steel of different dia within stipulated time. The failure to finalise the logistics resulted in a prolonged delay and also resulted in a financial loss to the claimant.
5. The work remained suspended/closed at various times, due to which the claimant’s staff, labours and machinery remained idle at work site without doing any work, and this was duly intimated to the appellants by the claimant. The effect of this delay was that the project started after lapse of six months and this delay could not be attributed to the contractor. Because of this inordinate delay and various other issues, the claimant claims that he had suffered a huge loss, which resulted into a dispute between the parties. As per the agreement, the matter was referred to the Arbitrator.
6. As per agreement, the Chief Engineer (Betwa) Irrigation and Water Resources, Department of U.P., Jhansi, who was actually the project proponent, appointed a Sole Arbitrator vide order dated 05-02-2021 for adjudication of the dispute. After the Arbitrator entered into the reference, the claimant had filed the statement of claims and the appellants filed the statement of defence. Thereafter, pleadings were complete, evidences were adduced and the parties were heard.
7. The Sole Arbitrator had considered the pleadings of the parties and contractual terms and conditions. He had also considered the oral/written arguments and legal submissions made by both the parties. He also considered the agreement and the provisions of I.D. Form No.111, which formed part of the contract as well as general conditions of the contract. He had also examined Clause 2 (A) of I.D. Form No.111, which stipulated that the time is the essence of contract. The Sole Arbitrator also considered and examined Clause-5 (Extension of time) of I.D. Form No.111
Associate Builders vs. Delhi Development Authority
Reliance Infrastructure Ltd. Vs. State of Goa
Delhi Airport Metro Express Private Limited Vs. Delhi Metro Rail Corporation Limited
Haryana Tourism Ltd. Vs. Kandhari Beverages Ltd.
State of Maharashtra Vs. Hindustan Construction Co. Ltd.
MMTC Limited v. Vedanta Limited
Ganesh Trading Co. v. Moji Ram
The court affirmed that judicial intervention in arbitral awards is limited to grounds of public policy or patent illegality, emphasizing respect for the Arbitrator's findings.
The court reaffirmed the limited scope of judicial review of arbitral awards under Sections 34 and 37 of the Arbitration and Conciliation Act, emphasizing that courts cannot reappraise evidence or in....
The appeal was allowed, reinstating the arbitrator's award which concluded that the termination of the contract was illegal due to failure in fulfilling mutual obligations concerning site availabilit....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
A tribunal must follow natural justice principles, allowing parties to present evidence; failure to do so renders an award susceptible to being set aside.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.