HIGH COURT OF JUDICATURE FOR RAJASTHAN, BENCH AT JAIPUR
AUGUSTINE GEORGE MASIH, SAMEER JAIN, JJ.
Alok Agarwal, S/o. Late Shri Shyam Sundar Agarwal – Petitioner
Versus
State Of Rajasthan, Through Sub-Registrar and Anr. – Respondents
D.B. Civil Writ Petition No. 5769 Of 2014
Decided On : 21-09-2023
Stamp Duty - Development Agreement - Rajasthan Stamp Act, 1998 - Section 65
Fact of the Case:
The petitioner challenged an order imposing stamp duty, arguing that the agreement was nullified due to non-compliance with its conditions. The respondents raised a preliminary objection regarding the maintainability of the petition, citing the availability of an alternative remedy under Section 65 of the Rajasthan Stamp Act, 1998.
Finding of the Court:
The court reiterated the principle that if an alternative and efficacious remedy is available, the courts would not exercise their supervisory jurisdiction. It found that the order impugned was passed after duly considering the agreement and that an alternative remedy was available to the petitioner under Section 65 of the Act.
Issues: The issues involved disputed questions of fact, especially regarding the nature of the agreement and the nature of the land, which the court deemed should be decided by the appellate authority as per the evidence.
Ratio Decidendi: The court held that the petitioner must avail the alternative statutory remedy under Section 65 of the Rajasthan Stamp Act, 1998, before invoking writ jurisdiction, especially when the petitioner failed to establish that the alternative remedy was not efficacious.
Final Decision: The court disposed of the writ petition, granting the petitioner liberty to avail the alternative statutory remedy under Section 65 of the Act within a specified period, and directing the appellate authority to dispose of the matter within a specified timeframe.
ORDER :
1. By way of the present petition, a challenge is made to the order impugned dated 31.03.2014 passed in Case No. 267/2014 titled as State (through Sub-Registrar, Jaipur-4) vs. Alok Agarwal & Anr. whereby stamp duty of Rs. 6,15,93,340/-along with surcharge of Rs. 61,59,340/-and penalty of Rs. 22,47,320/-totaling Rs.7,00,00,000 (7 crores) has been raised against the petitioner.
2. The concise and ineluctable factual matrix, necessary for discerning the issue at hand, is noted herein-under:-
2.1. That the petitioner is the owner of agricultural land comprising an area of 9 Bighas and 11 Biswas.
2.2. That on 07.06.2010, qua the said land, the petitioner entered into a ‘development agreement’ with a company namely, M/s. Sunny Arcade Private Ltd.
2.3. That the said agreement was divided into two distinct parts. The first part of the agreement provided that the developer would furnish a security deposit of Rs. 2 crores in favour of the petitioner by way of post-dated cheques (PDCs). Moreover, the developer would also initiate and complete proceedings under Section 90-B of the Rajasthan Land Revenue Act along with getting the land use of the said property changed and thereafter, obtain the patta of the total land within a period of 24 months from the date of signing of the said agreement. It was only upon successfully completing the aforementioned requisites, that the approval of construction would be granted. In essence, the agreement stipulated that if the preceding tasks, as noted above, were not duly carried out within a period of 24 months, then in such an eventuality, the agreement as entered between the parties, would be a nullity. Whereas, if the said tasks were carried out, then the agreement would be governed by the second part of the agreement, providing for the development and construction on the subject land.
3. In this background, learned counsel for the petitioner submitted that though styled as a ‘development agreement’, the subject agreement was divided into two distinct parts, as noted above. Therefore, the said agreement in the first instance was not a development agreement, but an agreement divided into two parts wherein the fulfillment of the first part would effectuate or activate the second part, the latter wherein alone constituted the ‘development agreement’. Thus, in essence, the agreement was an agreement which was contingent and was to take effect in future and on happening of certain contingencies as no rights were meant to flow to the developer till the conditions of the first part were fulfilled. Accordingly, as the first part of the said agreement was not duly complied/completed within a period of 24 months as required, the agreement in toto was nullified, thereby, not giving rise to the second part, which in essence was the ‘development agreement’. The said agreement became null and void. Therefore, there was no requirement upon the petitioner to pay stamp duty, in the absence of any development and/or construction being carried out on the subject land/property. In support of the said agreement becoming a nullity, learned counsel submitted that even the cheques (PDCs) paid as security, were returned back to the developer, upon the lapse of the period of 24 months as provided in the first part of the agreement.
4. Furthermore, learned counsel argued that the order impugned dated 31.03.2014 deserves to be quashed and set aside, as the Additional Collector (Stamps) did not consider the nature of the document/agreement which was in fact not a ‘development agreement’ covered under Article 5(bbbb) or 5(e) but an agreement otherwise covered under Article 5(c). Therefore, the liability to pay stamp duty has been incorrectly crystallized qua the petitioner, despite the agreement being a nullity. Lastly, learned counsel also averred that the remedy of revision available to the petitioner under Section 65 of the Rajasthan Stamp Act, 1998 (hereinafter, Act of 1998) is ineffective and illusory, especially on
Hardev Asnani vs. State of Rajasthan reported in 2011 (11) SCR 599
Availability of alternative and efficacious remedy under Section 65 of the Rajasthan Stamp Act, 1998, precludes the exercise of supervisory jurisdiction by the courts.
The power to impound an instrument under Section 33A of the Maharashtra Stamp Act, 1958, is strictly confined to the Registering Officer who registered the document, and cannot be exercised after the....
The Collector of Stamps must assess whether the properties under the Development Agreement and General Power of Attorney are identical to determine the applicable stamp duty under the Maharashtra Sta....
Power under Section 33A of Maharashtra Stamp Act vests exclusively in Registering Officer; superior officers lack jurisdiction to impound. Prior certification under Section 32 attains finality unless....
The nature of the instrument, whether it was an agreement for sale or a development agreement, did not affect the applicability of the proviso to section 48(1) of the Stamp Act. The court emphasized ....
The court affirmed that a statutory remedy under the Rajasthan Stamp Act must be exhausted before seeking writ relief, emphasizing no violation of natural justice occurred.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.