SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Raj) 141

HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
Mukesh Rajpurohit, J.
The State of Rajasthan through the Collector - Appellant
Versus
M/s Rama Road Career - Respondent
S.B. Civil First Appeal No. 179 of 1997
Decided On : 16-01-2026

Advocates Appeared:
For the Appellant : Mr. L.K Purohit

The court ruled that limitation for civil recovery suits cannot be extended by prior administrative recovery actions, and the absence of proper authorization for a plaintiff represents a fatal defect in contractual litigation.

Headnote:(A) Code of Civil Procedure, 1908 - Section 96 - Limitation Act, 1963 - Article 11 - Civil suit for recovery of Rs. 2,05,882/- was dismissed on the grounds of limitation and lack of authority of the plaintiff to institute the suit - Contract of transportation was operative from 26.03.1983 to 30.06.1983; suit filed on 19.01.1993 was barred by limitation. (Paras 1-16)

(B) Limitation - The Court held that correspondence under the Rajasthan Public Demands Recovery Act does not extend limitation for filing a civil suit, as such proceedings are executive in nature and not civil. (Paras 10-12)

(C) Authority to sue - The suit must be instituted by a duly authorised representative of the State; absence of proof of delegation of authority to file the suit invalidates the proceedings.

Facts of the case:
The appellants, having a contract for transporting cement, filed a civil suit for recovery after the defendant allegedly failed to deliver the goods and subsequently stored them unauthorizedly, leading to their seizure. The plaintiffs claimed the suit was within the limitation period, which the trial court denied. (Paras 1-4)

Findings of Court:
The trial court's dismissal of the suit was based on the expiration of the limitation period and lack of authority of the plaintiff to institute the suit, affirming that the plaintiffs failed to justify the delay or provide necessary authorizations. (Paras 12-13)

Issues: The principal issues addressed were whether the suit was barred by limitation and whether the second plaintiff had the authority to sue on behalf of the State. (Paras 5-6)

Ratio Decidendi: The court reiterated that limitation is strict, especially under Article 11, and that administrative actions do not extend civil limitations. Furthermore, it emphasized the necessity of authorization for a party to sue on behalf of the State. (Paras 10-14)

Result: The appeal was dismissed, affirming the trial court's judgment and decree. (Paras 15-16)

Table of Content
1. overview of the case and contract details. (Para 1 , 2)
2. arguments and counterclaims from both parties. (Para 3 , 4)
3. court's analysis on limitation and authority to sue. (Para 6 , 11)
4. discussion on the procedural aspects and need for proper authority. (Para 10 , 12 , 13)
5. conclusion affirming the trial court's decision. (Para 15 , 16)

JUDGMENT :

Mukesh Rajpurohit, J.

1. This civil first appeal under Section 96 of the Code of Civil Procedure, 1908 has been preferred by the appellants-plaintiffs against the Judgment and Decree dated 23.07.1997 passed by the Additional District Judge, Phalodi in Civil Regular Suit No.68/1993 titled as “State of Rajasthan & Anr. vs. M/s Rama Road Career”, whereby civil suit for recovery of Rs. 2,05,882/- filed by the appellants-plaintiffs was dismissed.

2. The facts which are germane for the present first appeal, in nutshell, are that appellants-plaintiffs instituted a civil suit for recovery of Rs. 2,05,882/- against the respondent-defendant before the court of Additional District Judge, Phalodi (hereinafter referred to as “trial court”), which was registered as Civil Original Suit No. 68/1993 (State of Rajasthan & Anr. vs. M/s Rama Road Career). It was pleaded in the suit that as per Contract No. 6 of the year 1983–84, plaintiffs allotted work of transporting 1250 M.T. cement from Nimbahera to Ramdevra to defendant-firm. Under the contract, defendant-firm received 5100 bags of cement, however, due to defendant’s act of storing cement bags at Ahinsa Nagar, Chittorgarh Chungi Naka without authorization, District Supply Officer, Chittorgarh seized cement on 02.07.1983. The defendant neither informed plaintiff about seizure nor obtained prior permission of plaintiffs for storage. Despite repeated requests by the plaintiffs, defendant failed to complete the transportation work. By letter dated 20.11.1983, defendant was informed that if the work was not completed, recovery would be made at double rates. Since the cement was not transported as per contract, Executive Engineer, 20th Division, Phalodi, by letter dated 31.10.1984, requested the District Collector, Jaisalmer to recover Rs.2,05,882/- from defendant-firm. But no action was taken despite reminders, including a final reminder dated 29.04.1990. Therefore, present suit was filed by plaintiffs seeking a decree of Rs.2,05,882/- along with interest against defendant-firm.

3. Respondent-defendant filed written statement denying averments made in the suit and pleaded that contract for cement transportation was under the orders of the Rajasthan Canal Project, 20th Division and that 5100 bags of cement were dispatched to Ramdevra, required to reach by 30.06.1983. When consignment reached Chittorgarh, route ahead was found blocked. Due to compulsion, cement was stored in a rented godown at Ahinsa Nagar, Chittorgarh. District Supply Officer, Chittorgarh, illegally seized cement bags on 02.07.1983. Despite efforts, no cooperation was given by the Executive Engineer, 20th Division, Rajasthan Canal Project to get the goods released. Because of the seizure, timely delivery became impossible. On 10.05.1984, appellate authority ordered release of the cement but no departmental representative came for inspection, resulting in deterioration of cement quality. It was further contended that delay occurred due to negligence of the State Government and departmental authorities. In the additional pleas, it was pleaded that suit was barred by limitation, that Plaintiff No. 2 had no authority to file the suit and that no person was duly authorized by the State Government to institute the suit. The defendant detailed expenses and losses, stating that value of cement was Rs.1,70,850/-, freight charges Rs.1,41,192/-, legal and seizure- related expenses Rs.5,000/-, godown rent Rs.7,500/-, security deposit Rs.25,000/- and chowkidar expenses Rs.1,400/-, totaling Rs.1,80,092/-. After adjustment of Rs.1,70,850/- towards cost of cement, defendant claimed ent

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top