SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Raj) 2386

HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
SANJEEV PRAKASH SHARMA, CJ, MANEESH SHARMA, J.
Suresh Jain, S/o Late Sh. Ram Chandra Jain - Appellant
Versus
RP Chaudhary, Son of Shri Gadadhar Prasad Choudhary - Respondent
D.B. Civil Miscellaneous Appeal No. 1839 OF 2021
Decided On : 25-11-2025 

Advocates Appeared:
For the Appellant : Mr. R.K. Agarwal, Sr. Adv. Assisted By Mr. Adhiraj Modi
For the Respondent: Mr. Aditya Kumar Mitruka With Mr. Ritik Jain, Mr. Chitransh Mathur

In contempt proceedings, the court requires absolute proof of violations due to their penal nature; any doubt favors the accused.

Headnote:(A) Code of Civil Procedure, 1908 - Order 39 Rule 2A - Contempt of Court - Appeal regarding interim order violation - The appeal was filed against the order of the Commercial Court for contempt proceedings initiated due to alleged construction violations post interim order. The court found insufficient evidence of violation and allowed the appeal. (Paras 1-19)

(B) Arbitration and Conciliation Act, 1996 - Section 17 - The enforcement of interim measures - The court discussed the standards of proof required in contempt proceedings, clarifying that absolute proof is needed due to the penal nature of such proceedings and reaffirmed the principles of strict evidence. (Paras 12-13)

Facts of the case:
The appellant was accused of violating an interim order prohibiting further construction. The respondent claimed violations through various complaints and photographic evidence. However, the evidence was insufficient to prove actual violations after the stated order.

Findings of Court:
The court did not find credible evidence of a breach of the interim order and emphasized the burden of proof in contempt proceedings. The original contempt orders were set aside.

Issues: The main issues addressed were whether the appellant violated the interim order and the applicability of contempt claims without established proof of such violation.

Ratio Decidendi: The court ruled that in contempt proceedings, a high standard of proof is necessary, and any doubt must favor the alleged contemnor. The absence of clear evidence negated the contempt findings.

Result: The present Civil Miscellaneous Appeal is allowed. The order passed by the learned Commercial Court dated 24.08.2021 read with correction order dated 13.09.2021 are set aside.

Table of Content
1. background and procedural history of the case. (Para 1 , 2 , 3 , 4)
2. arguments regarding the violation of interim order. (Para 5 , 6 , 7)
3. court's examination of evidence and legal standards. (Para 8 , 9 , 10 , 11 , 12 , 13)
4. considerations on the maintainability of the appeal. (Para 14 , 15 , 16 , 17 , 18)
5. final ruling and outcome of the appeal. (Para 19 , 20)

ORDER :

1. Heard the learned counsel for the parties at length and also considered the statement of the complainant recorded during the contempt proceedings initiated under Order 39 Rule 2A Code of Civil Procedure, 1908 (hereinafter referred to as ‘CPC’).

2. The case set up on the application moved under Order 39 Rule 2A CPC was that the appellant had made further construction after an interim order was passed by the learned Commercial Court No.1, Jaipur (hereinafter referred to as ‘Commercial Court’) on 02.07.2019 and, therefore, has violated the order passed by the Commercial Court. The learned Commercial Court proceeded to examine the application moved under Order 39 Rule 2A CPC and evidence was led on behalf of the respondent/applicant. After the cross-examination was conducted, the Commercial Court proceeded to pass the impugned order on 24.08.2021, which was subsequently corrected vide order dated 13.09.2021 and it was directed to attach the property of the appellant and also send the appellant to civil jail for a period of 15 days for committing contempt of the order dated 02.07.2019.

3. The present appeal was filed by the appellant wherein he stated that on 02.07.2019, an order was passed by the Commercial Court to maintain the status quo with regard to new constructions only and alienation. It is his submission that so far as the property is concerned, no new construction was done after passing of the order dated 02.07.2019. However, with a view to coerce the appellant, an application was moved immediately on 05.07.2019 under Order 39 Rule 2A CPC.

4. It is submitted that the dispute between the appellant and the respondent is relating to a development agreement entered into between the parties where the appellant was the developer and respondent was the land owner. The respondent had invoked the arbitration agreement and the Arbitral Tribunal consisting of a Sole Arbitrator had rejected the application filed by the respondent under Section 17 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as ‘the Act of 1996’), seeking an interim prayer for disallowing any further construction.

5. Learned Senior Counsel appearing on behalf of the appellant submits that the interim prayer under Section 17 of the Act of 1996 was thereafter allowed to the extent as noticed above by the Commercial Court and the appellant was restrained from making any alienation or making any new construction only. Thus, the existing construction was not required to be disturbed, however, in the garb of the said order, the contempt proceedings were wrongfully initiated against the appellant.

6. Per contra, learned counsel appearing for the respondent submits that the application filed was a genuine case of violation of the interim order passed by the Court on 02.07.2019 in the presence of their own counsels. The appellant proceeded to make further construction, to which, an F.I.R. was registered by the respondent with the local Police Station and thereafter the contempt application under Order 39 Rule 2A CPC for committing contempt was moved before the concerned Commercial Court. He asserts that there has been further construction after 02.07.2019 and the punishment awarded by the Commercial Court in the order passed on 24.08.2021/13.09.2021, do not warrant any interference.

7. He has also objected to the maintainability of the present appeal and relies on the judgment passed in the case of Amazon.Com NV Investment Holdings LLC vs. Future Retail Limited and Others 2022 1 SCC 209

8. We have considered the submissions and carefully gone through the record as

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top