SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Raj) 425

HIGH COURT OF JUDICATURE FOR RAJASTHAN, BENCH AT JAIPUR
SANJEEV PRAKASH SHARMA, ACJ., BIPIN GUPTA, J.
M/s Shalimar Electrical, Through Satatwdhari Shri Satynarayan, S/o. Late Shri Ramchandra Ajmera - Appellant 
Versus 
M/s Kanchan India Limited, Through Managing Director – Respondent
D.B. Civil First Appeal No. 318 of 2020
Decided On : 21-05-2026

Advocates Appeared:
For the Appellant : Mr. Nirmal Solanki with Ms. Pragya Pandey
For the Respondents: Mr. Rajendra Sharma.

The grant of pre-suit interest is discretionary and equitable. A party who remains inactive for a prolonged period without justification cannot claim interest for that duration, as the law aids only the vigilant, not those who neglect their rights.

Headnote:(A) Civil Procedure - Interest on decree - Discretion of court - Grant of pre-suit interest is essentially discretionary and equitable in nature unless specifically governed by a contractual stipulation or statutory mandate - Appellate Court ought not to interfere with discretionary orders unless the discretion has been exercised arbitrarily, capriciously or contrary to settled legal principles. (Paras 11, 14)

(B) Legal Maxim - “Vigilantibus non dormientibus jura subveniunt” - Law assists those who are vigilant and not those who sleep over their rights - A claimant failing to assert rights or demand performance within a reasonable time, remaining inactive for years, cannot claim interest for the period of such dormancy - The court remains justified in restricting interest from the date of the formal demand. (Paras 8, 12, 13)

Facts of the case:
The plaintiff-appellant filed a suit for recovery of money for goods supplied. The trial court decreed the suit in part, awarding a specific amount with interest from the date of the legal notice. The appellant challenged the judgment, seeking interest from the date of supply of goods rather than the date of the legal notice, citing a delay in payment as the basis for the grievance.

Findings of Court:
The appellate court determined that the trial court properly exercised its discretion. The appellant had remained silent for several years after the alleged liability arose, and no justifiable explanation for this inaction was provided. The court refused to award interest for the period of the appellant's self-imposed dormancy.

Issues: Whether the trial court erred in awarding interest from the date of the formal demand notice instead of the date of the supply of goods, and whether the appellant's delay in initiating recovery proceedings precludes a claim for interest during the dormant period.

Ratio Decidendi: The court applied the maxim that the law aids the vigilant and not the indolent, holding that a party cannot benefit from their own inaction. Since no specific contractual term mandated interest from the date of supply, the trial court's decision to grant interest from the formal demand date was equitable and legally sound.

Result: Appeal dismissed.

Table of Content
1. summary of facts and trial court findings regarding payment dispute. (Para 1 , 2 , 3)
2. appellant's arguments regarding the commencement date for interest calculation. (Para 4 , 5)
3. respondent's counterarguments on contractual disputes and interest discretion. (Para 6)
4. doctrine of laches: courts may deny pre-notice interest for periods of claimant inactivity. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16)

JUDGMENT :

Bipin Gupta, J.

1. The present Civil First Appeal has been preferred by the plaintiff-appellant assailing the judgment dated 23.10.2019, passed by learned Commercial Court, Ajmer, in Civil Suit No. 189/2018 (124/2014) CIS No. 123/2018, whereby the suit instituted by the plaintiff-appellant for recovery of amount has been partly decreed in its favour.

2. The controversy, in a narrow compass, is that a suit came to be filed by the plaintiff-appellant against the defendant- respondent for recovery of amount to the tune of Rs.10,24,017/-, contending therein that on 18.03.2008, the plaintiff-appellant, who was a dealer of M/s. Schneider Electric India Pvt. Ltd., received a purchase order from the defendant-respondent for supply of electric switchgear worth Rs. 60,43,356/-. The supplies were effected from 22.04.2008 till 19.05.2008. However, the defendant-respondent did not take delivery of the goods and, therefore, the plaintiff-appellant was compelled to store the goods at its premises/godown. Upon being asked the reason for not taking delivery of the goods, the defendant-respondent replied that the requirements had changed and, therefore, a fresh purchase order would be placed according to the new requirements.

2.1 On 13.08.2008, a fresh purchase order was issued for material amounting to Rs.44,51,000/-. In compliance with the fresh purchase order, material worth Rs.44,00,000/- was supplied from 20.08.2008 to 10.12.2008. However, the defendant- respondent paid only an amount of Rs.40,00,000/-. Thus, a remaining amount of Rs. 4,00,000/- was due and payable.

2.2 The plaintiff-appellant, in his plaint, claimed that in its books of account, against the said purchase order, a principal amount along with agreed interest amounting to Rs.8,30,774/- was outstanding. It was also pleaded that, against the purchase order dated 18.03.2008, since the material was not taken by the defendant-respondent, the plaintiff-appellant had to pay a penalty to M/s. Schneider Electric India Pvt. Ltd., amounting to Rs.1,93,243/-. Thus, a suit was filed for recovery of total amount of Rs.10,24,017/-.

2.3 The defendant-respondent filed a detailed written statement admitting the fact of the purchase order for supply of switchgear worth Rs.60,43,356/-. It was further contended that the material supplied pursuant to the subsequent purchase order was not of standard quality and, therefore, a debit note of Rs.4,00,000/- was issued to the plaintiff-appellant. It was also contended that the penalty allegedly paid by the plaintiff-appellant to M/s. Schneider Electric India Pvt. Ltd., amounting to Rs.1,93,243/-, could not be recovered from the defendant-appellant, in absence of any privity of contract. On the aforesaid grounds, dismissal of the suit was prayed for by the defendant-respondent.

3. On the basis of the pleadings of the parties, the learned Commercial Court framed as many as eleven issues which reads as under:

3.1 In support of its pleadings, the plaintiff-appellant examined two witnesses and produced various documents in evidence. On the other hand, the defendant-respondent examined only one witness in support of his case.

3.2 Issue Nos.1 and 3 were decided in favour of the plaintiff. Issue No.2 was decided against the plaintiff. Issue No. 4 was partly allowed in favour of the plaintiff wherein the it was held entitled to receive the outstanding amount of Rs.4,00,000/- along with agreed interest @ 24% from the date of service of notice i.e. 01.12.2011. Issue No. 5 was decided against defendant. Issue No. 6 was partly allowed i

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top