SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2019 Supreme(HP) 1718

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
JYOTSNA REWAL DUA, J.
Tarun Mahindroo - Petitioner
Versus
H.P. Power Corporation Limited - Respondent
Arbitration Case No. 71 of 2017
Decided on : 23-08-2019

Advocates:
Advocate Appeared:
For the Petitioner:Mr. Suneet Goel, Advocate.
For the Respondent:Mr. Sunil Mohan Goel, Advocate.

The main legal point established in the judgment is that the application of the Hudson formula for loss of profit and overheads must be supported by evidence of actual damages suffered by the claimant, and it must align with the specific provisions of the contract agreement.

Headnote:

Hudson Formula - Construction Contract - Arbitration & Conciliation Act 1996, Section 34 - 36.1, 36.2 - The court discussed the application of the Hudson formula for loss of profit and overheads on account of prolongation of the contract. It highlighted the specific provisions of the contract agreement and the lack of evidence to support the claim, ultimately influencing the court's decision to dismiss the petition.

Fact of the Case:

The petitioner/claimant sought to challenge an award passed by the Arbitrator under Section 34 of the Arbitration & Conciliation Act 1996. The main point of contention was whether loss of profits and overheads due to prolongation of the contract could be awarded solely based on the Hudson formula without evidence of actual damages suffered by the claimant.

Finding of the Court:

The court found that the claimant failed to provide evidence of actual damage suffered due to the prolongation of the contract, and the specific provisions of the contract agreement did not support the claim for loss of profit and overheads. As a result, the court dismissed the petition.

Issues: The key issue was whether the claimant's reliance on the Hudson formula without evidence of actual damages was sufficient to support the claim for loss of profit and overheads on account of prolongation of the contract.

Ratio Decidendi: The court's decision was influenced by the lack of evidence to support the claim, the specific provisions of the contract agreement, and the inapplicability of the Hudson formula in the absence of proof of actual damage suffered by the claimant.

Final Decision: The court dismissed the petition, finding it devoid of merit, and disposed of any pending applications.

JUDGMENT :

Jyotsna Rewal Dua, J.

Feeling aggrieved against the award passed by the learned Arbitrator, instant petition under Section 34 of the Arbitration & Conciliation, Act 1996, has been preferred by the petitioner/claimant.

The main point to be adjudicated in this case is:- whether loss of profits and over heads on account of prolongation of the contract, can be awarded merely on the basis of Hudson formula without the claimant leading any evidence, be it oral or documentary in respect of loss, damages suffered by him.

2. The factual position of this case, can be summarized as under:-

2(i) The respondent awarded construction work of =Bachelor Accommodation at Sunder Nagar, District Mandi (Civil Work, Internal WS, SI and Electrical Installation)' to the petitioner/claimant vide letter of award dated 25.07.2011 (Annexure C-1). The contracted value of the work was Rs.1,96, 03,299/-. The work was to be completed within 18 months from 21st day after issuance of letter of award dated 25.07.2011. Annexure C-2, contained the terms and conditions governing the contract duly executed by the parties.

2(ii) Various representations of claimant, addressed to the respondent, in respect of the contract work have been enclosed at Annexure C-3 (colly). The details of the same can be summed up hereunder:-

I) Letter dated 31.08.2011 to the effect that work at site has been stopped by BBMB, on the ground that land belongs to BBMB. Request was made for revised handing over of the site to the claimant/contractor.

II) Letter dated 07.11.2011 is a reminder of previous letter dated 31.08.2011, with respect to handing over the possession of the site to the claimant.

III) Letter dated 09.2.2012, written in continuation to the previous letters that site had still not been handed over to the contractor, resultantly, huge loss on account of setting of cement, payments of chowkidars for watch and ward of material stacked at site stores and indirect losses due to prolongation is being caused to the claimant/contractor. Request was made for handing over the possession of the site for starting and completing the work in time.

IV) Letter dated 09.04.2012, to the effect that the possession of the site had still not been handed over to the contractor. Therefore, extension in time by nine months was requested by the claimant. This was followed by representation dated 07.01.2013 on the same lines.

V) Letter Dated 15.09.2014, intimating that the extension of time for completion of the project granted by the respondent up to 15.08.2014, had lapsed, however, the site had still not been handed over to the claimant. Therefore, the second extension to time from 15.08.2014 to 14.02.2016, i.e. for a period of 18 months, was sought for.

VI) Letter dated 04.10.2014, to the effect that despite repeated requests, second time extension had not been granted and accordingly, prayer was made for extending the time period for completing the work.

VII) Letter dated 23.06.2016, requesting the respondent either to appoint the Arbitrator under Clause-33 of the Contract or to provide the site for construction of the building.

2(iii) On 16.12.2016, notice (Annexure C-4), under Clause 36 of the agreement, was issued by the respondent to the claimant, intimating that despite best efforts of the respondent, the land ownership issues for undertaking the construction of the project work, could not be resolved, therefore, it was decided by the respondent to abandon the work.

2(iv) The Arbitrator was appointed by the order of this Court on 08.03.2017. Claimant preferred his claim before learned Arbitrator under following heads:-

Sr. No.

Heads

Amount claimed

1.

Loss of profit and over heads on account of prolongation of contract.

Rs. 29,40,495/-

2.

Refund of security.

Rs. 10,000/-

3.

Refund of earnest money.

Rs. 3,43000/-

4.

Cost of Arbitration Proceedings.

Rs

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top