IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
Satyen Vaidya, J.
M/s R.K. Construction Co. - Appellant
Versus
The State of H.P. and another - Respondents
R.S.A. No. 351 of 2016
Decided On : 08-12-2022
Arbitration and Conciliation Act, 1996 - Section 34 - Limitation Act, 1963 - Section 14, (1) - Code of Civil Procedure, 1908 - Rule 2 of Order XXIII - Contractor - Grant of Increased Amount - Agreement Clause - Suit was contested by defendants on grounds that claim under Clause 10-C of agreement, submitted by plaintiff, could not be entertained and admitted by defendants as claim had been preferred by plaintiff without any detailed documentary evidence – There was no proof that plaintiff had submitted his claim under Section 10-C of agreement to competent authority, who could decide on issue of grant of increased amount to contractor - Para 19
Finding of the Court :
There was no proof regarding enhancement of costs of material and/or labour wages - Plaintiff also failed to place on record any material to prove that he in fact had incurred enhanced costs - Further, there was no proof that the plaintiff had submitted his claim under Section 10-C of agreement to competent authority, who could decide on issue of grant of increased amount to contractor - Concurrent findings of fact recorded by both Courts below cannot be faulted with - Rather, such findings are borne from material on record - Plaintiff had further contended that defendants had admitted before Arbitrator that amount of enhanced costs was Rs.4,03,200/ - Contention so raised on behalf of plaintiff also deserves to be rejected for reason that no such admission has been proved on record by bringing necessary evidence to such effect - Moreover, plaintiff cannot draw any advantage of alleged admission as award, if any, based on such admission, has been set-aside by learned Single Judge of this Court by holding claim under Clause 10-C to be not arbitrable.
Result: Appeal fails.
JUDGMENT :
(Satyen Vaidya, J.)
1. By way of instant Regular Second Appeal, judgment and decree dated 03.03.2016, passed by learned Additional District Judge (II), Shimla, H.P. in Civil Appeal No.16-S/13 of 2015 affirming judgment and decree dated 28.06.2014 passed by learned Civil Judge (Senior Division), Shimla, H.P. in Civil Suit No. 31/1 of 2011/2009, has been assailed.
2. On 10.08.2016, the appeal was admitted for hearing on following substantial questions of law:
(ii) Whether the learned Courts below have failed to appreciate the arbitration agreement in its true perspective and the conclusions arrived at by the learned Courts below are perverse?
3. The parties hereinafter shall be referred to by the same status as they held before the learned trial Court. The appellant herein was the plaintiff and the respondents herein were the defendants.
4. Plaintiff sued defendants for recovery of Rs.9,00,000/- with interest pendente lite and future at the rate of 24% per annum. The suit was filed on the premise that plaintiff had executed the work of construction of new MLA Hostel at Vidhan Sabha “Block-P”, in pursuance to contract awarded to him by the defendants. Though the completion of work was delayed, but the defendants had acquiesced by allowing extension of time. Plaintiff had raised certain claims against the defendants and had invoked the arbitration clause of the work contract. The Arbitrator had passed an award in his favour under various heads including a sum of Rs.3,80,217/- on account of price escalation under clause 10-C of the agreement. The respondents had preferred objections, under Section 34 of the Arbitration and Conciliation Act, 1996, before this Court. All other claims of plaintiff were upheld except the aforesaid claim of Rs. 3,80,217/- on the ground that Clause 10-C of the agreement between the parties was outside the scope of the Arbitrator’s jurisdiction.
5. Plaintiff, thus filed the suit for the above stated amount of Rs.3,80,217/- alongwith interest at the rate of Rs.24% per annum. The suit amount was, accordingly, calculated at Rs.9,00,000/-
6. The suit was contested by the defendants on the grounds that the claim under Clause 10-C of the agreement, submitted by the plaintiff, could not be entertained and admitted by the defendants as the claim had been preferred by the plaintiff without any detailed documentary evidence.
7. Learned trial Court framed the following issues:-
2. Whether the suit of the plaintiff is not maintainable? OPD
3. Whether the suit of the plaintiff is time barred? OPD
4. Relief.
8. Issue No.1 was decided in negative and all other issues were decided in affirmative. The suit of the plaintiff was accordingly dismissed. Learned trial Court held that the plaintiff had failed to prove the facts necessary for supporting his claim under Clause 10-C of agreement. In addition, the claim of the plaintiff was held to be barred by limitation.
9. The case of plaintiff met the same fate in first appeal. Learned lower appellate Court dismissed the appeal vide impugned judgment and decree. It was concurrently held that the plaintiff had failed to establish his claim under Clause 10-C of the agreement.
10. I have heard learned counsel for the parties and have also gone through the records of the case carefully.
11. It is not in dispute that the completion of work got delayed, however, the extension of time was allowed by the defendants. Plaintiff preferred a claim, before the Arbitrator, on account of price escalation under Clause 10-C of the agreement. The Arbitrator awarded a sum of Rs.3,80,217/- for price escalation. Since, learned Single Judge of this Court had set-aside the award passed by the Arbitrator to the extent it allowed the claim o
Section 14 of Limitation Act, reads as Exclusion of time of proceeding bona fide in court without jurisdiction.
The court affirmed that claims in arbitration must be asserted within the limitation period, and undue delays in invoking arbitration can render claims invalid.
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
The main legal point established is that the existence of an arbitration agreement does not preclude a party from filing a suit, and the applicability of the Limitation Act, 1963 to determine the tim....
The main legal point established in the judgment is that claims under a works contract must be made within the prescribed period of limitation, and an award based on no evidence and being perverse ca....
Claims in arbitration must adhere to statutory limitation periods; failure to comply renders them non-maintainable, emphasizing the strict nature of limitation under arbitration law.
Arbitration Agreement – Award -Scope of interference by the courts into the award is quite limited. A court considering an application under Section 30 of the Act neither sits in appeal over an award....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.