SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 175

IN THE HIGH COURT OF DELHI AT NEW DELHI
ANIL KSHETARPAL, AMIT MAHAJAN, JJ.
Deepak Builders And Engineers Limited – Appellant
Versus
M/S Engineering Projects (India) Ltd. – Respondent
FAO (COMM) 185 of 2024 & CM APPL. 54337 of 2024
Decided On : 20-02-2026

Advocates Appeared:
For the Appellant : Mr. Varun Chugh & Mr. Mayank Kaushik, Advs..
For the Respondent: Mr. Debarshi Bhadra, Adv.

Claims in arbitration must adhere to statutory limitation periods; failure to comply renders them non-maintainable, emphasizing the strict nature of limitation under arbitration law.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Appeal against the judgment setting aside an arbitral award - Claims were barred by limitation as per the Limitation Act, 1963 - The court emphasized that limitation must be strictly adhered to, preventing stale claims from being revived. (Paras 16, 30, 32)

(B) Judicial Review - The court's role under Section 34 is limited to ensuring that awards are not affected by patent illegality or jurisdictional errors rather than re-evaluating merits. (Paras 22, 28)

Facts of the case:
The Appellant contested an order that set aside an arbitral award for claims that were deemed time-barred, with the final bill submitted in 2008 and arbitration invoked in 2015.

Findings of Court:
The learned District Judge correctly found that the claims were barred by limitation, emphasizing the public policy rationale behind this principle.

Issues: The key issue was whether the learned District Judge was justified in dismissing the appeal based on the limitation of claims under the Arbitration and Conciliation Act.

Ratio Decidendi: The court ruled that the claims being ex facie barred by limitation permitted the District Judge's intervention, even in the absence of a timely objection before the arbitrator, as the law cannot be overridden by consent or inaction.

Result: Appeal dismissed.

Judgement Key Points

Key Points: - Arbitral claims must adhere to statutory limitation periods; failure makes them non-maintainable (!) (!) (!) . - The court’s role under Section 34 is limited to ensuring awards are not affected by patent illegality or jurisdictional errors, not re-evaluating merits (!) (!) (!) . - An award granting relief on claims barred by limitation suffers from patent illegality and can be set aside under Section 34 (!) (!) . - Limitation is a substantive defence grounded in statute and cannot be waived by omission or inaction (!) (!) . - The learned District Judge’s finding that claims were ex facie barred was based on undisputed documentary material and did not involve re-appreciation of evidence (!) (!) . - The appellate power under Section 37 is narrower than under Section 34 and does not permit re-appreciation of merits (!) (!) (!) .

What is the court's role under Section 34 of the Arbitration and Conciliation Act, 1996?

When are arbitral claims deemed non-maintainable due to limitation?

Can an award be set aside on the ground of patent illegality for non-compliance with the Limitation Act?


Table of Content
1. section 37 of a&c act and its implications (Para 1 , 2 , 15)
2. factual background on the contract between appellant and respondent (Para 4 , 5 , 6 , 7 , 9 , 12 , 14)
3. arguments presented by the parties regarding limitation (Para 17 , 18 , 19 , 20)
4. court's analysis of jurisdiction under section 37 (Para 21 , 22 , 30)
5. legal principles regarding limitation in arbitration (Para 23 , 24 , 26 , 28 , 38 , 42)
6. final decision and dismissal of appeal (Para 53 , 54)

JUDGMENT :

ANIL KSHETARPAL, J.

1. Through the present Appeal under Section 37 , [ ] of the Arbitration and Conciliation Act, 1996, [A&C Act], the Appellant assails the correctness of the judgment dated 16.05.2024 [hereinafter referred to as ‘Impugned Order’], passed in ARBTN-248/18, whereby the learned District Judge allowed the Petition filed by the Respondent under Section 34 , [ ] of the A&C Act [hereinafter referred to as ‘ Petition’] and set aside the Arbitral Award dated 13.07.2018 [hereinafter referred to as ‘the Award’] passed by the learned Sole Arbitrator.

2. The learned District Judge, by way of the Impugned Order, has held that the Award suffers from patent illegality on account of the claims being barred by limitation under the Limitation Act, 1963, Limitation Act

3. Accordingly, the principal issue which arises for consideration before this Court is whether the learned District Judge was justified in interfering with the Award under Section 34 on the ground of limitation, particularly in the absence of a timely objection before the learned Arbitrator.

FACTUAL MATRIX

4. In order to appreciate the controversy involved in the present Appeal, the relevant facts, in brief, are required to be noticed.

5. The Respondent invited tenders for civil and internal electrical work for planning, designing, and construction of a Zonal Office Building for Punjab National Bank at Ludhiana, Punjab [hereinafter referred to as ‘work’]. On 12.01.2006, EPIL issued a letter of award bearing LOI No. NRO/CON/494-TEC/0245 for construction, to the Appellant.

6. It is the case of the Appellant that the work stood completed in all respects on 30.06.2008, however, the date of completion of the work as per the agreement was 11.04.2007. On 08.09.2008, the Appellant raised its final bill for an amount of Rs.25,72,035.87/-, payable within 6 months. In the said bill, it was noted that the gross amount was subject to statutory deductions against taxes, cess, etc.

7. On 07.11.2008, the Respondent released a sum of Rs.4,98,849/- to the Appellant while withholding an amount of Rs.20,73,187/- on account of alleged service tax, labour cess, security deposit and other deductions.

8. Subsequently, correspondence ensued between the parties with regard to the deductions so made. The Respondent addressed a letter dated 04.02.2009 to the Labour Commissioner, Punjab, seeking clarification regarding the applicability of labour cess for construction completed before 11.11.2008. In response, the Labour Commissioner, vide communication dated 19.02.2009, clarified that the State Government has not taken a decision on levying labour cess on projects completed before 11.11.2008.

9. In the context of the Impugned Order assailed before this Court, the correspondence dated 07.03.2009, 03.08.2009 and 07.07.2011 is relevant. Vide letter dated 07.03.2009, the Respondent stated that the final bill dated 08.09.2008 had been certified and paid, subject to certain deductions towards labour cess, service tax and commissioning charges, and that 50% of the retention money had been released. The claim for interest was denied, and the issue of labour cess was stated to be under consideration with Punjab National Bank.

10. By letter dated 03.08.2009, the Respondent stated that the building had not yet been handed over to Punjab National Bank and, therefore, the Appellant’s assertion of completion in all respects was disputed. It was further stated that tax-related issues were under consideration and that the claim

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top