IN THE HIGH COURT OF DELHI AT NEW DELHI
ANIL KSHETARPAL, AMIT MAHAJAN, JJ.
Deepak Builders And Engineers Limited – Appellant
Versus
M/S Engineering Projects (India) Ltd. – Respondent
FAO (COMM) 185 of 2024 & CM APPL. 54337 of 2024
Decided On : 20-02-2026
Key Points: - Arbitral claims must adhere to statutory limitation periods; failure makes them non-maintainable (!) (!) (!) . - The court’s role under Section 34 is limited to ensuring awards are not affected by patent illegality or jurisdictional errors, not re-evaluating merits (!) (!) (!) . - An award granting relief on claims barred by limitation suffers from patent illegality and can be set aside under Section 34 (!) (!) . - Limitation is a substantive defence grounded in statute and cannot be waived by omission or inaction (!) (!) . - The learned District Judge’s finding that claims were ex facie barred was based on undisputed documentary material and did not involve re-appreciation of evidence (!) (!) . - The appellate power under Section 37 is narrower than under Section 34 and does not permit re-appreciation of merits (!) (!) (!) .
| Table of Content |
|---|
| 1. section 37 of a&c act and its implications (Para 1 , 2 , 15) |
| 2. factual background on the contract between appellant and respondent (Para 4 , 5 , 6 , 7 , 9 , 12 , 14) |
| 3. arguments presented by the parties regarding limitation (Para 17 , 18 , 19 , 20) |
| 4. court's analysis of jurisdiction under section 37 (Para 21 , 22 , 30) |
| 5. legal principles regarding limitation in arbitration (Para 23 , 24 , 26 , 28 , 38 , 42) |
| 6. final decision and dismissal of appeal (Para 53 , 54) |
JUDGMENT :
ANIL KSHETARPAL, J.
1. Through the present Appeal under Section 37 , [ ] of the Arbitration and Conciliation Act, 1996, [A&C Act], the Appellant assails the correctness of the judgment dated 16.05.2024 [hereinafter referred to as ‘Impugned Order’], passed in ARBTN-248/18, whereby the learned District Judge allowed the Petition filed by the Respondent under Section 34 , [ ] of the A&C Act [hereinafter referred to as ‘ Petition’] and set aside the Arbitral Award dated 13.07.2018 [hereinafter referred to as ‘the Award’] passed by the learned Sole Arbitrator.
2. The learned District Judge, by way of the Impugned Order, has held that the Award suffers from patent illegality on account of the claims being barred by limitation under the Limitation Act, 1963, Limitation Act
3. Accordingly, the principal issue which arises for consideration before this Court is whether the learned District Judge was justified in interfering with the Award under Section 34 on the ground of limitation, particularly in the absence of a timely objection before the learned Arbitrator.
FACTUAL MATRIX
4. In order to appreciate the controversy involved in the present Appeal, the relevant facts, in brief, are required to be noticed.
5. The Respondent invited tenders for civil and internal electrical work for planning, designing, and construction of a Zonal Office Building for Punjab National Bank at Ludhiana, Punjab [hereinafter referred to as ‘work’]. On 12.01.2006, EPIL issued a letter of award bearing LOI No. NRO/CON/494-TEC/0245 for construction, to the Appellant.
6. It is the case of the Appellant that the work stood completed in all respects on 30.06.2008, however, the date of completion of the work as per the agreement was 11.04.2007. On 08.09.2008, the Appellant raised its final bill for an amount of Rs.25,72,035.87/-, payable within 6 months. In the said bill, it was noted that the gross amount was subject to statutory deductions against taxes, cess, etc.
7. On 07.11.2008, the Respondent released a sum of Rs.4,98,849/- to the Appellant while withholding an amount of Rs.20,73,187/- on account of alleged service tax, labour cess, security deposit and other deductions.
8. Subsequently, correspondence ensued between the parties with regard to the deductions so made. The Respondent addressed a letter dated 04.02.2009 to the Labour Commissioner, Punjab, seeking clarification regarding the applicability of labour cess for construction completed before 11.11.2008. In response, the Labour Commissioner, vide communication dated 19.02.2009, clarified that the State Government has not taken a decision on levying labour cess on projects completed before 11.11.2008.
9. In the context of the Impugned Order assailed before this Court, the correspondence dated 07.03.2009, 03.08.2009 and 07.07.2011 is relevant. Vide letter dated 07.03.2009, the Respondent stated that the final bill dated 08.09.2008 had been certified and paid, subject to certain deductions towards labour cess, service tax and commissioning charges, and that 50% of the retention money had been released. The claim for interest was denied, and the issue of labour cess was stated to be under consideration with Punjab National Bank.
10. By letter dated 03.08.2009, the Respondent stated that the building had not yet been handed over to Punjab National Bank and, therefore, the Appellant’s assertion of completion in all respects was disputed. It was further stated that tax-related issues were under consideration and that the claim
UHL Power Co. Limited v. State of Himachal Pradesh
Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction Co. Ltd.
ONGC Ltd. Western Geco International Ltd.
Numaligarh Refinery Ltd. v. Daelim Industrial Co. Ltd.
Tata Hydro-Electric Power Supply Co. Ltd. v. Union of India
Claims in arbitration must adhere to statutory limitation periods; failure to comply renders them non-maintainable, emphasizing the strict nature of limitation under arbitration law.
The court affirmed that claims in arbitration must be asserted within the limitation period, and undue delays in invoking arbitration can render claims invalid.
Arbitral awards are upheld where the claims are barred by pre-existing certificates and where the burden of proof lies with the claimant to substantiate additional work claims.
The statutory limitation period under Section 34(3) of the Arbitration and Conciliation Act is inflexible, and applications filed beyond this period cannot be entertained.
The limitation period for an application under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond specified timelines, maintaining strict adherence to legal provisions.
The court emphasized that judicial interference with arbitral awards is strictly limited, focusing only on issues of public policy or jurisdictional errors and cannot re-evaluate the merits of the aw....
The court affirmed that a promise to pay a time-barred debt under Section 25(3) of the Indian Contract Act can revive the claim, and the Arbitrator's findings were not subject to re-evaluation under ....
The period for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond the prescribed period, as the Act is a self-contained special law and t....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.