IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
JYOTSNA REWAL DUA, J.
The State of H.P. & Anr. - Petitioners
Versus
Ramesh Kumar - Respondent
CWP No. 9172 of 2013
Decided On : 16-03-2023
Industrial Disputes Act, 1947 - Section 25F, G and H - Retrenchment of workman - Services were terminated - Re-engagement with continuity of service - State has taken exception to award passed by learned Labour Court-cum-Industrial Tribunal Dharamshala H.P., whereby retrenchment of respondent-workman was set aside – Abandonment or relinquishment of service is always a question of intention and normally such an intention cannot be attributed to an employee without adequate evidence in that behalf. [Para 5(iii)]
Finding of the Court: Muster-roll of respondent-claimant was produced by petitioner as Ext.RW1/A - As per this muster-roll respondent had worked for 78 days in year 2005 and 92 days in year 2006 - Admittedly, respondent-claimant did not complete 160 days of working in tribal area in a block of 12 calendar months preceding from date of his termination - Thus, it was rightly observed in award that provisions of Section 25F of Act were not breached - It was not open for corporation to contend that appellant had not completed 240 days service - Moreover, it is settled law that for attracting applicability of Section 25-G of Act, workman is not required to prove that he had worked for a period of 240 days during twelve calendar months preceding termination of his service and it is sufficient for him to plead and prove that while effecting retrenchment, employer violated the rule of 'last come first go' without any tangible reason - Petitioner has failed to point out any error in impugned order passed by learned Labour Court - For foregoing reasons, no interference is called for in impugned award passed.
Result: Petition dismissed.
JUDGMENT :
Jyotsna Rewal Dua, J.
State has taken exception to the award passed on 27.06.2012 by the learned Labour Court-cum-Industrial Tribunal Dharamshala H.P., whereby retrenchment of the respondent-workman was set aside. State was directed to re-engage the respondent forthwith. He was also held entitled to the seniority and continuity in service from the date of his illegal termination i.e. 1.11.2006 except back wages. The award also directed the State to regularize the services of the respondent as per policies framed by the Government of Himachal Pradesh from time to time.
2. Facts
2(i) The appropriate Government sent following reference on 12.07.2010 to the learned Labour Court for adjudication:-
2(ii) The respondent in his claim petition pleaded that he was appointed as a Beldar w.e.f. April 2004 at HPPWD Division Pangi at Killar, District Chamba, H.P. He had been working continuously as such. His services were orally terminated by the petitioner on 1.11.2006. He made several requests to the State-petitioner for his re-engagement but despite availability of work and funds, the petitioner paid no heed to his requests. Respondent in his claim petition further made a grievance that several persons, who were his juniors had been continuing on their job on daily wages in the same division, but his employer (present petitioner) in breach of Section 25F, 25G and 25H of the Industrial Disputes Act (hereinafter referred to as the Act) refused to re-engage him. Respondent further averred that he had completed 160 days of continuous daily wage services in the preceding 12 calendar months in the tribal area of Pangi division. The break, if any, in his service is owing to the inclement weather conditions of the tribal division. Respondent prayed for relief of his re-engagement with continuity of his service, back wages and consequential benefits. Prayer was also made for regularization of his services.
2(iii) The employer (petitioner) in its reply took up the stand that the respondent was engaged as daily waged Beldar during the year 2005. He worked for 78 days in the year 2005 and 92 days in the year 2006. Thereafter he left the job of his own and resultantly lost his seniority. The gist of the stand taken by the petitioner before the learned Labour Court was that the services of the respondent had not been terminated but he had abandoned the service at his own will. It was further pleaded that no junior persons to the respondent had been engaged by the petitioner.
2(iv) The claimant appeared in the witness box as PW-1. He reiterated his case as projected in the claim petition. He denied having abandoned the job in September 2006. The petitioner examined the then Executive Engineer, as RW-1. This witness produced the mandays chart of the respondent (Ex.RW1/A). According to this witness, the claimant had left the job on his own in September 2006 and never returned thereafter. The witness, however, admitted the suggestion given to him during the cross-examination that no notice was ever served upon the claimant after he had allegedly left the job. He also admitted to be correct that claimant had never been given any opportunity thereafter by the petitioner for coming to work.
2(v) On considering the respective stand of the parties, learned Labour Court passed the award on 27.06.2012. Reference was answered in the following terms:-
It is settled law that for attracting applicability of Section 25-G of Act, workman is not required to prove that he had worked for a period of 240 days during 12 calendar months preceding terminatio....
The central legal point established in the judgment is the interpretation and application of the definition of 'retrenchment' under Section 2(oo)(bb) of the Industrial Disputes Act in determining the....
Non-renewal of contract does not amount to retrenchment under Section 2(oo)(bb) of the I.D. Act.
In cases of wrongful termination, reinstatement with continuity of service and backwages is the normal rule, and the employer should not be relieved of the burden to pay the employee's dues.
Point of law :Labour Law - There is no proof that the workman has worked for 240 days and, therefore, it was held by the Labour Court that there is no proof that the workman was working continuously ....
The main legal point established in the judgment is that the Petitioner failed to prove that the termination was in violation of Section 25-H of the I.D. Act.
In illegal termination cases involving daily-wage workers, reinstatement is not automatic; compensation and circumstances of employment should be evaluated.
Termination of employment found illegal due to lack of due process; procedural adherence under the Industrial Disputes Act is mandatory, leading to reinstatement or monetary compensation.
Termination of service It cannot be presumed that any junior is considered without there being any evidence on record and the learned Single Judge has therefore rightly come to the conclusion that th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.