IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
G.S. SANDHAWALIA, C.J., RANJAN SHARMA, J.
State of HP and others - Appellants
Versus
Harish Chander and others - Respondents.
LPA No. 224 of 2025
Decided on : 08-05-2025
(A) Constitution of India - Article 300A - Land Acquisition - Directions issued to the State to initiate acquisition proceedings and pay just compensation for land utilized for road construction without proper acquisition process - The court emphasized the necessity of compensation for landowners whose land was used without due process. (Paras 1, 6, 12)
(B) Voluntary Surrender of Land - The court found no evidence of voluntary surrender of land by the petitioners, thus reinforcing the principle that property cannot be taken without compensation. (Paras 7, 12)
Facts of the case:
The petitioners, rustic villagers, claimed compensation for land used for road construction since 2016, arguing that no proper acquisition process was followed despite similar cases being compensated. (Paras 2, 3)
Findings of Court:
The court ruled that the State failed to provide evidence of voluntary surrender and must compensate the petitioners as per Article 300A. (Paras 6, 12)
Issues: The main issues included whether the land was voluntarily surrendered and the State's obligation to compensate landowners under Article 300A. (Paras 6, 12)
Ratio Decidendi: The court held that the absence of written consent from landowners and the lack of a proper acquisition process necessitated compensation, reaffirming that property rights must be protected. (Paras 6, 12)
Result: Appeal dismissed.
JUDGMENT :
G.S. Sandhawalia, C.J.
Consideration is sought in the present Letters Patent Appeal to the judgment passed by the learned Single Judge in CWP No. 10652/2023 decided on 24.10.2024, whereby the learned Single Judge issued directions to the appellant/State to initiate acquisition proceedings within four weeks under the relevant statute of the land of the petitioners and pay just and fair compensation to them. The land having been utilized as such in the year 2006, led to the said direction being passed by the learned Single Judge as such for construction of the Beulia-Koel-Sanog road. The learned Single Judge relied upon the judgments inState of Himachal Pradesh vs. Umed Ram Sharma (1986) 2 SCC 68, and Hari Krishna Mandir Trust vs. State of Maharashtra and others (2020) 9 SCC 356 for the grant of necessary relief while falling back on Article 300A of the Constitution of India and while repelling the argument raised that the land had been utilized on account of the consent of the land owners that they would not seek compensation.
2. A perusal of the pleadings in the writ petition would go on to show that the construction of the road was done in the year 2014-2015 and compensation was not paid. Similarly situated person, namely, Sheela Tegta had approached this Court by filing CWP No. 360 of 2016 which was allowed on 21.08.2023 (Annexure P-2).
3. The pleaded case of the petitioners was that the road was made motorable and functional in the year2016 but till date, the compensation has not been paid and representation had then been submitted on 06.11.2023 (Annexure P-3) giving facts of the similarly situated persons, namely, Sheela Tegta. It has been submitted that the petitioners are rustic villagers and could not be divested of their land and their constitutional rights as enshrined under Article 300A of the Constitution and no decision had been taken on the said representation.
4. The stand of the State as such was that there was voluntary surrender of land and a huge amount of Rs.246.290 crore had been spent to construct the road.
5. A perusal of the writ record would go on to show that the road was being constructed under the World Bank Scheme and administrative approval and expenditure sanction had been accordingly given. Plea of delay and laches as such was taken. It was the stand of the respondents that since the villagers have consented to the construction of the road, therefore, the remedy was to approach the Civil Court and therefore, there is admission regarding the conversion and usage of the land of the petitioners. The distinction sought to be done from Sheela Tegta’s case was without any basis as the facts of that case were different.
6. It is pertinent to notice that State has in its reply never taken a plea that they had preferred any appeal in the case of Sheela Tegta (supra) and therefore, when the similarly situated persons had been granted compensation for the same purpose, we do not find any valid reason why other similarly situated land owners could be deprived of the same benefits on the principle enshrined under Articles 14 and 300A of the constitution.
7. Another aspect is that nothing has been brought on record that the State had taken any written consent from the land owners. It is also not their case that such consent was taken but documents were not traceable. Therefore, onus lies upon the State in what manner it has used the land/property of the petitioners as such for public purpose without having initiating any process for acquisition of the land.
8. In the rejoinder (sic-replication), filed by the petitioners, it was pleaded that there was no evidence on record that respondents had utilized the land of the petitioners by initiating any process for acquisition under the land Acquisition Act and that procedure had been initiated for acquisition of their land. The State as such could not deprive the persons of their property without due process or authorization and further that the plea of delay and
AI
The court affirmed that landowners are entitled to compensation under Article 300A when their land is utilized for public purposes without proper acquisition procedures.
Landowners are entitled to compensation for land utilized for public purposes unless there is clear evidence of voluntary surrender, as mandated by Article 300-A of the Constitution.
The State must compensate landowners for land used in public projects without formal acquisition, emphasizing the necessity of due process.
Landowners cannot be deprived of property rights without lawful authority, and the burden of proof lies with the State to demonstrate voluntary donation of land.
Landowners have a constitutional right to compensation for land utilized for public projects, and claims cannot be dismissed based on implied consent or delay in seeking redress.
Landowners are entitled to due process and compensation for property utilized by the State without formal acquisition, as under Article 300A of the Constitution.
Landowners cannot be deprived of their property without due process and just compensation, regardless of implied consent due to prolonged silence on compensation claims.
The court ruled that landowners are entitled to compensation for land utilized for public projects without proper acquisition, emphasizing constitutional rights and the invalidity of claims of volunt....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.