IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
SANDEEP SHARMA, J.
Gaurav Mehta - Appellant
Versus
The State of Himachal Pradesh and Others - Respondents
Civil Writ Petition No. 15611 of 2024
Decided On : 07-01-2025
| Table of Content |
|---|
| 1. petitioner seeks release of funds. (Para 1) |
| 2. work done but payment delayed. (Para 2) |
| 3. court's call for reasons on non-payment. (Para 3 , 4 , 5) |
| 4. disputes on payment subject to arbitration. (Para 6) |
| 5. jurisdiction established for writ petition despite disputed facts. (Para 7) |
| 6. writ jurisdiction may address contractual disputes. (Para 8 , 9) |
| 7. no dispute on work executed; payment must be made. (Para 10) |
| 8. petition allowed; payment ordered. (Para 11 , 12) |
JUDGMENT :
Sandeep Sharma, J.
1. By way of present writ petition, petitioner has prayed for following main relief:
“(a) That this Hon’ble Court may be pleased to issue writ of mandamus directing the respondents to immediately release the 1st & Final Bill of the work done as prepared by the Assistant Engineer, Nankhari i.e. respondent No. 4 (Annexure P-3) and Memorandum of Payment (Annexure P-4) as prepared by the Executive Engineer (B&R) Division Rampur Bushahr amounting to Rs. 41,41,918/- alongwith commercial rate of interest @ 12.75%.”
2. Precisely, the grouse of the petitioner, as has been highlighted in the petition and further canvassed by Mr. Sunil Mohan Goel, learned Senior Counsel representing the petitioner is that though petitioner herein has successfully completed the work of construction awarded to him vide letter 15.09.2023, for an amount of Rs.41,41,918/-, but yet he is not being paid amount due to him. To substantiate factum with regard to completion of work as well as preparation of final bill, Mr. Goel, learned Senior Counsel representing the petitioner specifically invited attention of this Court to Annexures P-3 and P-4, perusal whereof clearly reveals that Site Engineer, after being satisfied with the quality of work done by petitioner, prepared final bill amounting to Rs.42,87,250/- in the month of March, 2024, but more than ten moths have passed, amount is not being released on one pretext or the other. In terms of afore final bill prepared and verified by Assistant Engineer, the Executive Engineer, HPPWD, though authorized payment for sum of Rs.41,41,918/-, but till date, amount has not been credited in the bank account of the petitioner.
3. Vide order dated 19.12.2024, this Court had specifically called upon learned Additional Advocate General to ascertain that why despite there being completion of work, amount is not being released. Vide aforesaid order, this Court had further called upon respondents/State to file short reply affidavit within one week specifically detailing therein reasons for non-release of payment in favour of the petitioner, despite his having completed the work.Neither short reply has been filed nor amount has been released.
4. Mr. Vishal Panwar, learned Additional Advocate General, on instructions, states that Site Engineer after being satisfied with the quality of work, has already prepared the final bill, but on account of paucity of funds, amount has not been released till date. He states that Public Works Department has already taken-up the matter with the Government of Himachal Pradesh for release of funds and as and when funds are made available, bill submitted by the petitioner shall be cleared.
5. Though in the case at hand, no reply has been filed, but taking note of averments contained in the petition, which is duly supported by way of an affidavit, as well as documents annexed therewith, coupled with the fair statement given by learned Additional Advocate General, this Court finds that petitioner herein has already completed the work and department, after being satisfied with the quality of work, has already prepared the bill, if it is so, amount to which petitioner is entitled, as indicated in the final bill, deserves to be released.
6. Though it is not in dispute inter se parties, that in terms of agreement arrived inter se parties, dispute if any, qua non payment of bill is to be adjudicated by the arbitrator, if any, appointed with the consent of parties or as per direction issued by the Court under Sect
ABL International Ltd. Vs. Export Credit Guarantee Corpn. of India Ltd.
Food Corporation of India v. SEIL Ltd.
M/s. Burmah Construction Company v. The State of Orissa & Ors.
Writ petitions against State entities for payment of due amounts are maintainable even with disputed facts; contract completion obligates the State to release funds promptly.
Writ petitions against State for contractual obligations are maintainable even with disputed facts; non-payment of dues despite work completion warrants judicial intervention.
A writ petition can be maintained against the State for contractual obligations even in the presence of disputed facts, ensuring fair treatment under Article 14.
Writ petitions against the State for contractual obligations are maintainable even with disputed facts; courts can direct payment when liability is clear.
Writ jurisdiction is not suitable for resolving contractual disputes involving disputed facts; such matters should be adjudicated in civil courts or through arbitration.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.