SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(HP) 263

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
Romesh Verma, J.
Jai Pal - Appellant
Versus
Nirmla Devi - Respondent
RSA No.30 of 2024
Decided On : 23-03-2026

Advocates Appeared:
For the Appellant :Mr. Devender K. Sharma, Advocate.
For the Respondent:Mr. Sushant Vir Singh Thakur, Advocate.

In second appeals, courts will not interfere with concurrent findings of fact by lower courts on encroachment claims, absent perversity or substantial question of law, particularly when Local Commissioner report confirms no encroachment.

Headnote:(A) Specific Relief Act, 1963 - Sections 38 and 39 - Suit for permanent prohibitory and mandatory injunction by co-sharer alleging forcible construction encroaching on suit land by overlapping slab, covering exposed steel pillars without setbacks, and dismantling 4-inch high brick wall erected to prevent rainwater flow - Defendant denied encroachment, claimed plaintiff failed to leave space and constructed haphazardly - Local Commissioner inspected site, directed parties to construct on own property, found compliance on revisit, no encroachment by either - Trial court dismissed suit; first appeal affirmed; second appeal dismissed as concurrent findings of fact supported by Commissioner report, no perversity or substantial question of law. (Paras 24, 25, 26, 27)

(B) Civil Procedure - Second Appeal - Scope - High Court will not interfere with pure findings of fact by lower courts unless perversity shown or substantial question of law arises; allegations of factual nature dealt concurrently below cannot be re-appreciated. (Paras 13, 26)

Facts of the case:
Co-sharers jointly owned land where adjacent houses constructed with connected slabs from ground to first floor. Plaintiff claimed reduced pillar size from 12x12 to 9x12 inches leaving 3-inch space with 4-inch brick wall for rainwater control; alleged defendant dismantled wall, built touching exposed steel and overlapping. Defendant claimed purchased earlier, completed construction first, no space left by plaintiff, only covering own staircase for water drainage; Local Commissioner found no encroachment.

Findings of Court:
Plaintiff's site plan unreliable as defendant's slabs unmeasured; oral evidence disbelieved; Local Commissioner report clinches no encroachment or dismantling; suit a neighbourly dispute without proof.

Issues: Whether defendant interfering in suit land by forcible construction; whether required to remove such construction; suit maintainability, cause of action, concealment of facts.

Ratio Decidendi: Lower courts properly appreciated evidence, relied on Local Commissioner report negating encroachment; concurrent factual findings binding in second appeal absent perversity or question of law; plaintiff failed to substantiate claims.

Result: Second appeal dismissed.

Table of Content
1. plaintiff claims defendant's construction encroaches shared slabs. (Para 2 , 4 , 5 , 15)
2. defendant denies encroachment; alleges plaintiff's improper construction. (Para 6)
3. lower courts frame issues, dismiss suit and first appeal. (Para 7 , 8 , 9 , 10 , 11)
4. second appeal: misappreciation vs. concurrent fact findings. (Para 12 , 13 , 14)
5. plaintiff witnesses support pillar reduction and interference. (Para 16 , 17)
6. defendant witnesses confirm no encroachment per lc directions. (Para 18 , 19 , 20 , 21)
7. lc report decisive; discredits plaintiff's site plan, wall claim. (Para 22 , 23 , 24 , 25)
8. no perversity; no interference in second appeal findings. (Para 26 , 27)

JUDGMENT :

Romesh Verma, J.

The present appeal arises out of judgment and decree, as passed by learned Additional District Judge, Sarkaghat, District Mandi, H.P. dated 23.12.2023, whereby the appeal filed by the present appellant was dismissed and the judgment and decree as passed by the learned Civil Judge( Senior Division), Court No.1, Sarkaghat, District Mandi, H.P. dated 31.3.2023 was affirmed.

2. Brief facts of the case are that the present appellant/plaintiff filed a suit in the Court of learned Civil Judge (Senior Division), Court No.1, Sarkaghat, District Mandi, H.P. on 6 th September, 2014, for permanent prohibitory and mandatory injunction under Sections 38 and 39 of the Specific Relief Act, 1963. It was averred in the plaint that the land comprised in Khewat Khatauni No.130/165, bearing Khasra No.518, land measuring 00-22-60 hects. is situated at Mouza Dharmpur/97, Tehsil Sarkaghat, District Mandi, H.P. The suit land is jointly owned and possessed by the plaintiff/appellant and defendant/respondent along with other co-sharers. The house of the plaintiff/appellant is consisting of two floor, including ground and first floor, and adjoining house is of defendant/respondent. The construction of slabs of plaintiff and defendant houses are connected with each other, however, the plaintiff in order to earmark the extent and boundary of his slabs as well as his first floor, left 3 inches portion of constructed slabs by changing the size and dimension of existing pillars of ground floor of size 12X12 inches to first floor in size 9x12 inches. The plaintiff has made about 4 inche in height bricks wall on the above left area of slabs for the purpose of stopping the flow of water of his house’s slabs towards the slabs of defendant.

4. It was averred that the defendant/respondent has got no right, title and interest to interfere in any manner over the suit property as well as over the slab of the plaintiff and any unwarranted act and deed on the part of defendant/respondent qua the suit property of the plaintiff/appellant amounts to aggression and evasion on her part over the suit property. In order to harm and cause prejudice to the plaintiff/appellant, the defendant/respondent has engaged the mason and labourer on the spot and has undertaken forceful construction. The said construction is of such a nature that it is touching with the exiting exposed steel of pillars of plaintiff/appellant’s house without leaving any necessary space and setbacks. In case the defendant/respondent succeeded in raising the construction in that event the existing steel pillars are going to be covered by the construction of the defendant/respondent and ultimately, the construction of the defendant will come over the suit property and virtually it will cover the area of the plaintiff.

5. The defendant was requested to stop the construction over the suit property, however, being a headstrong persons, he did not adhere to the request of the plaintiff and threatened the plaintiff to implicate him in a false case. Though, local Panchayat was involved in order to resolve the controversy in question by amicable means, but the defendant being headstrong person refused to listen to the request of Panchayat members. Therefore, the plaintiff filed a suit for permanent prohibitor

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top