SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(J&K) 31

JAMMU AND KASHMIR HIGH COURT
Alok Aradhe, J.
Government of J. and K. - Petitioner
Versus
Hindustan Construction Company Ltd. & Ors. - Respondents
Arbitration Appeal No. 13 of 2016
Decided On : 22-03-2017

IMPORTANT POINT
– A possible view by Arbitrator

Headnote:Jammu and Kashmir Arbitration and Conciliation Act, 1997 – Section 34 – Challenge to arbitral award – Justice should not only be done but should also seem to be done – Unreasoned decisions may be just but they may be not appeared to be just to parties and reasoned conclusions on other hand will have appearance of justice – In absence of reasons, statutory right of appeal may become nugatory and higher forum will be at loss to understand working of mind of inferior Tribunal and it will not be possible for Court to decide whether there is any legitimately ground for Court to interfere with decision of body – Court would interfere with an award passed by Arbitrator if it is in violation of statute, interest of India, justice or morality, patent illegality, contravention of Act or terms of contract – A possible view by Arbitrator on facts has necessarily to pass muster as Arbitrator is ultimate master of quantity and quality of evidence to be relied upon when he delivers his arbitral award. An award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. (Paras 13 and 14)

       Result – Appeal disposed of with directions.

JUDGMENT :

Alok Aradhe, J.

In this appeal preferred under Section 37 of the Jammu and Kashmir Arbitration and Conciliation Act, 1997 (herein-after referred to as 'the Act-), the appellant has assailed the validity of order dated 2-4-2016 passed by the trial Court by which the application preferred by the appellant under Section 34 of the Act has been rejected and the award passed by the Arbitral Tribunal dated 28-12-2014 has been modified insofar as it pertains to grant of interest for the post award period to 6%. In order to appreciate the appellants challenge to the impugned award, few facts need mention which are stated infra:

2. The appellant issued Notice Inviting Tenders (NIT) on 15-3-2005 by which Tenders were invited for grant of contract for construction of Mughal Road from Bafliaz, District Poonch to Shopian (Pulwama) in the State of Jammu and Kashmir. The last date of submission of bid was 14-6-2015. The respondent submitted his bid in response to the aforesaid Notice Inviting Tenders (NIT), which was accepted and letter of acceptance was issued on 14-9-2005. Thereafter an agreement dated 8-2-2006 was executed. Under the agreement, the date of commencement of the work in question was 1-3-2006 and the contract was to be executed within a period of three years i.e. upto 28-2-2009. The total contract price as per the original agreement was Rs. 214,40,00,000/-. The relevant extract of general conditions of the contract are reproduced below :

'2. The Intended Completion Date for the whole of the works is 3 years after the start of work.'(Cl. 1-1-17 & 27)

'Clause 3.1 of Part I-GCC. 'The language of contract and the law governing the Contract are stated in Contract Data."

'Clause 8(a) of Contract Data reads as 'the law which applies to the Contract is the law of Union of India (Cl.3.1)."

'Clause 11 Employer's Risks.

11.1 The Employer is responsible for the excepted risks, which are (a) insofar as they directly affect the execution of the works in the Employer's country the risks of war invasion act of foreign enemies, rebellion, revolution, insurrection or military or usurped power civil war riot commotion or disorder (unless restricted to the Contractor's employees) natural calamities and contamination from any nuclear fuel or nuclear waste or radioactive toxic explosive or (b) a cause due solely to the design of the Works other than the Contractor's design.'

'Clause 17. The works to be completed by the Intended Completion Date.

17.1 The Contractor may commence execution of the works on the start date and shall carry out the works in accordance with the programme submitted by the Contractor as updated with the approval of the Engineer and complete them by the Intended Completion Date.'

'Clause 21. Possession of the site.

21.1 The Employer shall give complete possession of the site to the contractor fifteen days in advance of the construction programme.'

'Clause 27. Extension of the Intended completion date.

27.1 The Engineer shall extend the intended completion date if a compensation event occurs or a variation is issued which makes it impossible for completion to be achieved by the intended completion date without the contractor taking steps to accelerate the remaining works which would cause the contractor to incur additional cost.'

'Clause 40. Compensation Events.

40.1 The following shall be compensation events unless they are caused by the contractor:

(a) The Engineer orders a delay or delays exceeding a total of 30 days.

(b) The effects on the contractor of any of the Employer's Risks.

40.2 If a compensation event would prevent works being completed before the Intended completion date the Intended completion date shall be extended. The Engineer shall decide whether and by how much the intended completion date shall be extended.'

3. From the perusal of the aforesaid relevant clauses of the agreement, it is evident that in the event of 'compensation events-or' delays in completion of the works-as envisaged by clauses 11, 12 and 40, the co



































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top