SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(J&K) 873

IN THE HIGH COURT OF JAMMU AND KASHMIR AT SRINAGAR
SANJEEV KUMAR, J.
M/S NKG Infrastructure - Appellant
Versus
GRANCO Industries and anr. - Respondent
AA No.39 of 2017, MP No.1 of 2017
Decided on : 05-06-2017

Advocate Appeared:
For the Appellant :Mr. Jehangir Iqbal Ganie, Sr. Advocate with M/S Mr.Syed Faisal Qadri, Moksha Kazmi, Tejaswi Shetty, Vaseen Aslam, Akash Johari & Raj Mohan Gupta, Advocates.
For the Respondent:Mr. Mohsin Qadri, Advocate.

Important Point – Order passed by Court under Section 9 of Arbitration Act falls in realm of discretionary relief.

Headnote:Jammu & Kashmir Arbitration and Conciliation Act, 1997 – Section 9 – Interim measure – When an application under Section 9 of Act is filed before commencement of arbitral proceedings, there has to be manifest intention on part of applicant to take recourse to arbitral proceedings in immediate future – Standards laid down in Code of Civil Procedure for regulating grant of interim relief may not be applicable to proceedings under Section 9 of Act stricto sensu but underlying principles are applied by Courts to pass interim orders to protect subject matter of arbitration – Order passed by Court under Section 9 of Act falls in realm of discretionary relief and appellate Court would not substitute its view in the matter merely on the ground that in its opinion the facts of case call for a different conclusion – As long as view of trial Court is a possible view and same does not suffer from any perversity, appellate Court would be loath to interfere. (Paras 4, 6, 11, 14 and 22)

       Result – Appeal allowed.

JUDGMENT :

1. The appellant, a company incorporated under the provisions of Companies Act, 1956 having its corporate office in Gaziabad (U.P.), is in appeal against the order dated 25.11.2017 passed by the Principal District Judge, Srinagar (hereinafter referred to as “the Court below”) in an application filed by respondent No.1 under Section 9 of the Jammu & Kashmir Arbitration and Conciliation Act, 1997 (hereinafter referred to as “the Act”).

2. The factual antecedents leading upto the filing of this appeal, as are necessary for the disposal of this appeal, may be summed up in the following manner:-

The Chief Engineer, 31 Zone C/o 56 APO vide his letter No. 180869/142-E8 dated 24.12.2010 bearing Contract No.CESZ-06/2010-11 awarded a contract to the appellant-Company for construction of dwelling units and allied services for married accommodation project map phase-II at LSRC Leh. The appellant entered into a Memorandum of Understanding with one firm, namely, M/S G.R.Nagvi and Co. for carrying out the work aforesaid. The firm M/s G.R.Nagvi and Co. amalgamated with respondent No.1-Company, as a result whereof all assets and liabilities of M/S G.R.Nagvi and Co. were taken over by the respondents. As per the terms and conditions of the MOU, the appellant-Company was entitled to 3% of the amount of the work and the rest of the amount was to go to respondent No.1. The MOU was to remain valid till the successful completion of the work.

It was the case of the respondent No.1 before the Court below that both the parties acted upon the terms and conditions and executed the work after adhering to the payment arrangement as decided by the parties. Thereafter, a supplementary agreement too was executed between the parties containing new terms and conditions. It is claimed that the firm M/s G.R.Nagvi and Co. which later on amalgamated with respondent No.1 had executed a considerable quantity of work by the end of year 2013. However, during the year 2014-15 the appellant had some issues with the employer and because of that the payments for the work executed by M/S G.R.Nagvi and Co. were not made. A sum of Rs.9,50,00,000/- was the amount that was payable by the appellant for the work executed including the rental amount of installation of plant and machinery. The respondent No.1 claimed that the appellant did not discharge its liability nor did it permit the respondent No.1 to go ahead with the execution of the balance work. Series of requests and reminders issued b respondent No.1 too could not evoke any response from the appellant. Lastly, before the Court below the respondent No.1 submitted that the liability which is admitted by the appellant towards respondent No.1 be directed to be discharged and also the accounts maintained by the appellant with the bank be frozen. The application under Section 9 of the Act was filed before the Court below in the context of aforesaid factual backdrop.

The application was contested by the appellant on numerous grounds. The maintainability of the application was disputed by the appellant on the ground that there was no arbitration agreement between the parties which is sine qua non for filing an application under Section 9 of the Act. The appellant even challenged the territorial jurisdiction of the Court below to entertain the application. It was also the submission of the appellant before the Court below that in the absence of respondent No.1 having demonstrated prima facie case in its favour along with balance of convenience and irreparable injury in the application, interim relief as prayed for was not maintainable. The Court below after considering the rival contentions disposed of the application finally vide its order dated 25.11.2017 directing the Chief Engineer/Garrison Engineer to make payment of Rs.9,36,38351/- in favour of respondent No.1 with further condition that respondent No.1 shall submit an undertaking that in case the arbitral tribunal makes any direction for reimbursing the appellant, t
















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top