SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(J&K) 123

IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT SRINAGAR
Javed Iqbal Wani, J.
Union of India – Petitioner
Versus
Mohammad Yousuf Mir and Ors. – Respondents
CFA No.02/2015, IA No.1/2015 and CM No.4968/2020
Decided On : 08-02-2022

Advocates:
Advocate Appeared:
For the Petitioner:Mr. Nazir Ahmad Bhat, Advocate
For the Respondent:Mr. Manzoor Ahmad Dar, Advocate

Headnote:

J&K Arbitration & Conciliation Act, 1997-Sections 34 and 37-Appeal against arbitral award-Appellant herein while throwing challenge to arbitral award did not file proceedings in terms of Section 34 of Act, but filed objections/counter claims before court below praying therein for setting aside of award and making of a fresh reference to an independent Arbitrator for deciding disputes afresh in accordance with law-Objector/appellant herein for making out a case for setting aside of award has to have a case in line with grounds referred in Section 34 of Act-Objector/appellant has not pleaded that it was under some incapacity or agreement which is genesis in arbitral proceedings, was not capable of enforcement or was otherwise invalid-Court below has rightly noticed that objector/appellant herein had not pleaded that it was not given proper notice by Arbitrator during arbitration proceedings-Court below has rightly held award to be reasoned and speaking one and not against any public policy, while holding that Arbitrator has rightly acted in fairness and objectively and returned finding in award after providing proper and sufficient opportunity to contesting parties. (Paras 10, 11 and 13)

Result-Appeal dismissed.

ORDER :

Javed Iqbal Wani, J.-The appellant through the medium of the instant appeal filed under Section 37 of the J&K Arbitration & Conciliation Act, 1997 (for brevity ‘the Act’) has thrown challenge to the order dated 27.05.2015 (for brevity ‘impugned order’) passed by learned Principal District Judge, Srinagar (for brevity ‘court below’) passed in File No. 08/Arb. titled “Ab. Salam Mir vs. Union of India and others”.

2. It is pertinent to mention here that during the pendency of the appeal the original contractor/respondent herein, namely, Abdul Salam Mir died and consequently, his legal heirs came to be substituted as respondents 1 to 5.

3. Before adverting to the grounds of challenge, a brief description of the facts is summarized as under:-

    i) That upon issuance of a NIT by the Chief Engineer HQ 31 Zone, C/o 56 APO /appellant herein, a contract bearing No. CESZ-33/93-94 came to be awarded for provision of Security Wall, Fencing, Watch Towers and Security Lights at Khundru station to the contractor/ predecessor-in-interest of the respondents herein. Post issuance of letter of award, the contractor claimed to have mobilized his men, machinery, equipment and other resources for speedy execution of the contract work within the stipulated time, being 18 months prescribed in the tender from the date of commencement of the contract which however, got delayed and consequently, resulted into prolongation in the period of contract.

ii) That the said delay in completion of the contract was attributed to the acts of omission and commission on the part of the department/appellant herein as the period of completion had been extended without levy of any compensation.

iii) That despite the aforesaid delay during the currency of the contract various disputes arose in connection with the subject contract between the department/appellant herein and the contractor and upon pressing into service the arbitration clause, an arbitrator, namely, Sh. Krishan Kumar (Chief Engineer) from amongst the panel of arbitrators (Pune) came to appointed by the Engineer-in-Chief in terms of of condition 70 of the IAFW-2249, forming part of the contract agreement;

iv) That the arbitrator so appointed entered upon the reference, adjudicated upon the disputes and passed an arbitral award on 25.09.2002;

v) That during the pendency of the proceedings before the arbitrator the contractor had sought adjudication of various disputes including the one pertaining to the damages sustained on account of “Prolongation of Contract” which claim in the estimation of the department/appellant herein was not open to the arbitration, however, the arbitrator on the strength of the provisions contained under Section 16 of the Act, opined that the claims raised are capable of being adjudicated before the arbitrator.

vi) That the contractor had sought adjudication of 18 claims out of which 06 claims came to be granted partially by the arbitrator.

A brief description of the claims made and allowed by the arbitrator for brevity and convenience are detailed out hereunder:-

C. No.

Nature of Claim

Amount Claimed

Amount allowed by Arbitrator

Claim No. 1

Change in place of issue of schedule “B” Stores

Es. 1,44,000   

 

Es. 24,600

Claim No. 2

Drastic changes in alignment of security Wall/ Fencing and Extra approaches by providing retaining walls and change of GE’S Office

Rs. 8,36,500

Rs. 83,600

Claim No. 3

Damages sustained due to disallowing dismantling of existing fencing

Rs. 1,40,825

Rs. Nil

Claim No. 4

Damages sustained due to third party interference

Rs. 19,18,000

Rs. 2,54,000

Claim No. 5

Extreme restriction at site

Rs. 18.76,363

Rs. Nil

Claim No. 6

Damages sustained due to non issue of water

Rs. 16,20,000 

 

Rs. 1,84,012

Claim No. 7

Complete stoppage of work by FAD

Rs. 69,940

Rs.

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top