SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(J&K) 343

IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
SINDHU SHARMA, J.
Ab. Rashid Malik - Petitioner
Versus
Union Territory of J&K & Ors. - Respondents
WP(C) No. 873 of 2021
Decided On : 07-05-2022

Advocates Appeared:
For the Petitioner: Irfan Khan.
For the Respondent: Ravinder Gupta.

The lack of administrative approval and technical sanction for the works does not absolve the respondents from their liability to pay for the executed works, especially when the liability is admitted and their actions are deemed arbitrary and unfair.

Headnote:

Construction Works - Payment Dispute - NABARD - PWD Act, Section 3 - Summary: The court discussed the execution of road construction works by the petitioner, the admission of liability by the respondents, and the dispute over the payment for the executed works. The court highlighted the lack of administrative approval and technical sanction for the works, the admission of liability by the respondents, and the arbitrary and unfair actions of the respondents. The court allowed the petition and directed the respondents to pay the balance amount for the executed works along with interest.

Fact of the Case:

The petitioner, a contractor, executed construction works of road allotted to him by the respondents. The payment due to him for the works has not been made, despite the admission of liability by the respondents.

Finding of the Court:

The court found that the works were executed by the petitioner, the liability for payment was admitted by the respondents, and the lack of administrative approval and technical sanction for the works. The respondents' actions were deemed arbitrary and unfair.

Issues: Dispute over payment for executed works, lack of administrative approval and technical sanction for the works, admission of liability by the respondents.

Ratio Decidendi: The lack of administrative approval and technical sanction for the works does not absolve the respondents from their liability to pay for the executed works. The admission of liability by the respondents and their arbitrary and unfair actions support the petitioner's entitlement to payment.

Final Decision: The petition is allowed, and the respondents are directed to pay the petitioner the balance amount for the executed works along with interest.

JUDGMENT :

1. The petitioner, a contractor by profession claims to have executed different construction works of road which were allotted to him after participating in the tendering process issued by the respondents. That pursuant to different work orders, the petitioner has executed the construction of road works from Kotli to Shikari Road situated at Village Kotli/Shikari, Tehsil Mahore, District Reasi.

2. The Assistant Executive Engineer, PWD (R&B) Spl. Sub Division, Mahore-respondent No. 5 herein and Executive Engineer, PWD (R&B) Spl. Sub-Division, Mahore i.e. respondent No. 4 after on spot enquiry and measurement of different types of road works executed by the petitioner had prepared detailed estimate of the entire road construction work done from Kotli to Shikari under NABARD with cost overrun scheme.

3. The Superintending Engineer PWD (R&B), Reasi-Udhampur vide his communication dated 03.10.2015 conveyed post-facto approval for execution of work for construction of B/wall and R/wall in Km 1st RD 0-100, 725-775 on Kotli to Shakri Road in Km 2nd RD 75-225, on the same rates, terms and conditions as already approved vide office allotment No. 2296-97, dated 19.10.2014. Similarly, on 26.02.2018 post-facto approval was conveyed for construction of 6 meter long scupper in Km 2nd RD 225-275, RD 425-450 and construction of B/wall in Km 1st RD 725--775 Km 2nd RD 950-1000 and Km 3rd RD 825-850 on Kotli to Shakari Road 225-300 and then an approval was conveyed for construction of B/wall in Km 1st RD 225-300 on Kotli to Shakari Road on 07.07.2017.

4. The petitioner submits that although he has executed all these works but the payment due to him for successful execution of the aforesaid works has not been made to him till date. The respondent No. 4 has admitted the claim of the petitioner and vide his communication dated 17.07.2020 had requested respondent No. 3-Superintending Engineer, PWD (R&B) Udhampur for allocation and sanction of an amount of Rs. 53.03 lacs to enable the respondents to settle pending claims of the contractor. It appears that the respondent No. 5 again allotted restoration of works to the petitioner vide allotment order No. PWD/R&B/M/2020-21/284-287, dated 05.06.2020 but subsequently vide communication dated 11.06.2020, there were handed over to PMGSY Division, Mahore for up gradation.

5. The grievance of the petitioner is that even though he has successfully executed all the works allotted to him to the entire satisfaction of the respondents but the respondents, despite admitting their liability to make payments have not released amount due to him till date.

6. The respondents in their objections submitted that the petitioner has raised a belated claim of Rs. 23.19 lakh and, therefore, the same is required to be rejected. The respondents have not denied the execution of the aforesaid work by the petitioner. It is also admitted by the respondents in their objections that there was balance payment of Rs. 10,01,017 in respect of the following works; the details of which are given in para 5 which reads as under:-

    "(1) Construction of B/Wall and R/Wall 6.0 in Km 2nd RD 0-100, RD 725-775 & Km 2nd RD 75-225 where the original allotment was for Rs.2,58,000/-, and thereafter, Superintending Engineer accorded approval for an amount of Rs.5,42,000/- for the wok executed excess of original allotment amount, totaling to Rs.8,00,000/- only and out of which Rs.6,79,205/- stood paid and only an amount of Rs.1,20,795/- is outstanding. Though the petitioner has executed the work amounting to Rs.9,76,991/- but there is no approval from the competent authority to execute the excess work over and above the amount of Rs.8,00,000/- in favour of the petitioner, therefore, the petitioner has no right to claim that excess amount of Rs.1,76,991/-.

(2) Construction of 6.00 mtr long scupper in Km 2nd RD 425-450 & construction of B/wall in Km 3rd 825-850 on Kotli to Shakari road, where the original allotted amount was Rs.6,39,481/- and thereafter

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top