HIGH COURT OF JAMMU AND KASHMIR AND LADAKH
SINDHU SHARMA, J.
Mukesh Singh – Appellant
Versus
Union Territory of J&K & Ors. – Respondent
WP(C) No. 1747/2021
Decided on : 12-10-2023
| Table of Content |
|---|
| 1. petitioner executed work assigned after tender process. (Para 1 , 2) |
| 2. petitioner made claims for payment of work executed. (Para 3 , 4 , 5) |
| 3. respondents admit work execution and liability, dispute funding. (Para 6 , 7 , 8) |
| 4. court questions execution approval and administrative authority. (Para 9 , 10) |
| 5. liability for payment cannot be denied by respondents based on technicalities. (Para 11 , 12) |
| 6. court orders payment of remaining due amount to petitioner. (Para 13) |
JUDGEMENT
1. The petitioner, who is "A" Class Government contractor by profession, claims to have executed the construction work which was allotted to him after participating in the tendering process issued by the respondents. That pursuant to work order, the petitioner has executed the construction of road works of improvement/ restoration of Rohi Minor breached at RD 900-1200M by way of plugging at various places, plugging of leakage between RD 7000-7100 M of D-9 by way of concreting and restoration of damages/plugging of leakage and cuts of Katyal Minor of D-10A RD 2300-2600M.
2. The Superintending Engineer, Hydraulic Circle, Jammu in reference to the letter No. JID/II/2320 dated 11.12.2019 vide his communication dated 13.12.2019 accorded sanction/approval for execution of the aforesaid work.
3. The said work was executed and completed by the petitioner well within time and up to the satisfaction of the respondents, however, an amount to the tune of Rs. 10,58000/- is to be paid to the petitioner for the execution of the aforementioned work. The respondents were avoiding the payment to the petitioner on one pretext or the other. Thereafter, on 05.03.2021 the petitioner served a legal notice upon the respondents through his counsel for release of the amount and upon this, an amount to the tune of Rs. 4,25,000/- was released out of the total amount of Rs. 10,58,000/-
4. The petitioner submits that although he has executed the aforesaid work but the payment due to him for successful execution of the work has not been made to him till date. The respondent No. 3 vide communication dated 14.07.2021 admitted that the said work was executed by the petitioner and further admitted the work done claim of the petitioner to the tune of Rs. 10,47,000/-. It is admitted by respondent No.3 that out of Rs. 10,47,000/-, an amount to the tune of Rs. 4,25,000/- already stands released and an amount to the tune of Rs. 6,22,000/- is still outstanding.
5. The grievance of the petitioner is that even though he has successfully executed the works allotted to him to the entire satisfaction of the respondents but the respondents, despite admitting their liability to make payments, have not released amount due to him till date.
6. The respondents in their objections submitted that the works had been executed by the petitioner vide approval issued by SE Hydraulic Circle Jammu's No. SE/Hyd/DB/7452 dated 13.12.2019 and SE/Hyd/DB/7451, dated 13.12.2019 and these are the contractual matters and the claims can be settled only in the light of the terms and conditions of the allotment order. They further submitted that the work which had been claimed executed is subject to verification, the verification committee had also been constituted by Chief Engineer (I&FC) Jammu vide No. IFCJ/Legal/5285-88, dated 17.06.2023 to verify the work done claim in the light of the terms and conditions of the contract. They further submitted that the verification stands accomplished by the committee and the report had been submitted to the Chief Engineer (I&FC), Jammu for onwards submission to the Administrative Department for final disposal of the claim. However, the further payment could not be made to the contractor because of non- availability of Accord of Administrative Approval.
7. As per these objections, an amount of Rs. 6,22,000/- is yet to be paid to the petitioner and the only reason for denial of payment of the amount is because of non-availability of Accord of Administrative Approval.
8. The
ABL International Ltd. & Ors. Versus Export Credit Guarantee Corporation of India Ltd. & Ors.
A contractor's entitlement to payment for executed works cannot be denied based on alleged lack of administrative approval when such works were accepted, confirming the principle of accountability in....
Contractors are entitled to payment for work performed in good faith, regardless of the absence of formal Administrative approval for excess work.
Contractual payments must not be unduly delayed by the state without valid justification.
Delay and laches cannot be invoked by the government to deny an admitted claim for payment, emphasizing the need for timely compensation to contractors.
Contractors executing government work are entitled to payment based on the belief of proper authorization, and the State must act justly in fulfilling its contractual obligations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.