SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2019 Supreme(Jhk) 752

IN THE HIGH COURT OF JHARKHAND AT RANCHI
SUJIT NARAYAN PRASAD, J.
M/s Himanchal Construction Company Private Limited - Petitioner
Versus
The State of Jharkhand represented through the Deputy Commissioner, & Ors. - Respondents
W.P.(C) No.3655 of 2019
Decided On : 14-10-2019

Subject

Civil Law - Amendment of Pleadings

Act Referred

CIVIL PROCEDURE CODE : O.6 R.17, S.151

Headnote

(A) Civil Procedure Code, 1908—Order VI Rule 17 read with Section 151—Amendment of plaint—Amendment cannot be claimed as a matter of right and under all circumstances, but courts while deciding such prayers should not adopt a hypertechnical approach—Liberal approach should be general rule, particularly in cases where other side can be compensated with costs—Normally, amendments are allowed in pleadings to avoid multiplicity of litigations—Question of prejudice is also to be looked into. (Paras 10, 17 and 18)

(B) Civil Procedure Code, 1908—Order VI Rule 17 read with Section 151—Amendment of plaint—Money suit—Merely by allowing amendment no adjudication can be said to be done rather amendment is for proper adjudication of issues raised by parties by providing proper opportunity to other side—Documents which has been sought to be incorporated being Government Circulars is having direct nexus with pleading made in plaint and have got bearing for proper adjudication of issues—Amendment petition allowed. (Paras 24, 29, 30 and 31)

Advocates Appeared:
For the Petitioner:Mr. Shresth Gautam, Advocate
For the Respondent: Mr. Chandhal Jain, AC to AG, Ms. Shristi Sinha, AC to AG

JUDGMENT :

1. This writ petition is under Article 227 of the Constitution of India by which the order dated 11.06.2019 passed in Original Suit No.17 of 2018 by the Court of District Judge-I-cum-Commercial Court, Jamshedpur has been assailed whereby and whereunder a petition filed under Order VI Rule 17 read with Section 151 of CPC has been rejected.

2. The brief facts of the case of the petitioner as per the pleadings made in the writ petition is that a money suit has been filed being Money Suit No.09 of 2011 praying inter alia for a decree of amount of Rs.10,17,45,402/-along with interest and cost of suit which the petitioner/plaintiff is claiming.

Such claim has been agitated by virtue of notice inviting tender being 1/2005-06 dated 22.10.2005 by which the applications have been invited from one or the other bidders for construction of cut and cover from km.16.250 to km. 16.745 and residual open channel of Chandil Left Bank Canal.

3. The petitioner has been awarded the work vide decision taken as contained in Letter No.539 dated 17.03.2006, in pursuance thereto, the agreement has been executed in between the petitioner and the respondent No.2 for execution of work within the time stipulated under the aforesaid agreement.

The petitioner has taken efforts to execute the work but due to the fact that the area where the work was to be executed since is falling under the forest coverage area, the hindrance had come which ultimately resulted into non-performance of the terms and conditions of the contract, ultimately the work could not have been completed. The petitioner, therefore, has filed a suit for money claim.

Subsequent to filing of the suit, the petitioner came to know about certain documents which has been obtained by someone else under the provision of Right to Information Act which the petitioner has intended to bring on record by way of amendment invoking the jurisdiction of the Court as conferred under Order VI Rule 17 of the CPC, which reads hereunder as:-

“After para 1 of the Plaint, para 1(a) be added with following contents:

1(a) The Defendants published Notice Inviting Tender with respect to Forest Land in utter violation of the Gazette of India dated 10/01/2003 and in violation of the (Forest Conservation) Act, 1980 as well as Forest (conservation) Rules, 2003. Even the decision taken in the meeting of the standing committee of National Board for Wildlife held on 06/04/2005 in pursuance to order passed in I.A. No. 35 of 2003 in W.P.(C) No. 337/1995 and communicated on 12/05/2005 has also been violated.

After para 1 (a) of the Plaint, para 1(b) be added with following contents:-

1(b) Special Secretary to the Govt. of Jharkhand Mr. Ravi Shankar Verma had issued instructions to all the Principal Secretary/Head of the Department/Divisional Commissioners, DDCs vide Memo No. 2097/A dated 05/09/2005 Vide this letter the Special Secretary has instructed all the concerning offices to invite ad execute tenders in view of the direction given by the Hon’ble Jharkhand High Court in LPA No.524 of 2003 wherein the Hon’ble Jharkhand High Court has directed the State Govt. to invite tenders in the principles laid down by the Hon’ble Supreme Court of India in the case of Ramna Daya Shetthy vs. International Airport Authority of India & Others (1979) 3 Supreme Court Cases – 489. The incorporation of Clause 14 in the NIT was in utter violation of the standing instruction of the State Govt., Hon’ble Jharkhand High Court and the Hon’ble Supreme Court of India.

After para 4 and before Para 5 of the Plaint, para 4A be added with following contents:-

4A. “The then Project Administrator (Mr. Bijay Kumar Tripathy I.A.S.) had written letter no.277 dated 22/02/2006 to all the Chief Engineers, all the Superintending Engineers and all the Executive Engineers under the subject ^^ou Hkwfe esa fcuk vuqefr ds dk;Z ugh djkus ds laca/k esa** Vide this letter the Project Administrator directed not to do any construction work over the Forest Land prior to the

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top