IN THE HIGH COURT OF JHARKHAND AT RANCHI
Gautam Kumar Choudhary, J.
M/s. Tata Steel Limited - Appellant
Versus
M/s Naveen Transport Company and ors. – Respondents
F.A. No.52 of 2012
Decided On : 05-05-2022
Code of civil procedure,1908 - Section 34 - Appeal - Money Suit - Interest - Whether there is any breach of contract - Whether the defendant is entitled to deduct the amount from the bills for short supply to the extent of Rs.19,06,200/- and whether it is refundable to defendant - Whether the plaintiffs are entitled to the decree sought for - Held, judgment has been assailed on the ground that on the basis of the Public Analyst Report (Exhibit ‘B’ series), the plaintiffs had committed breach of contract and not the defendant. Exhibit B-16 to B-32, was also not considered by the Trial Court when these letters were regularly sent by the defendants to the plaintiffs - As per the terms of the contract, the deduction had to be made from each bill within 30 days of receipt of consignment and if such deductions were wrongly made, then cause of action for such deduction would arise against each bill after 30 days from the date of bill - The plaintiffs were therefore required to prove their claim within three years from the date of such deduction - The last bill was submitted on 31.03.1994 and date of cause of action should have been 30 days from the said date- Appeal partly allowed.
JUDGMENT :
The appellant-defendant has preferred the First Appeal against judgment and decree passed in Money Suit No.51 of 1998 whereby the suit has been decreed for a sum of Rs.32,78,664/- pendente lite and future interest at the rate of 18% per annum.
2. The plaintiffs’ case is that it is a partnership firm in transportation business, was engaged by defendant Company for transportation of Hard Coke from F.C.I., Sindri to Jamshedpur by Work Order No. RMPO/11/93/730956 dated 12.11.1993 for transportation of 6000 metric ton of Hard Coke per month at the rate of 232 per ton for the period of one year commencing from 01.10.1993 to 30.09.1994.
3. The terms and conditions of the contract inter alia provided as under:-
ii. Each truck loaded with Hard Coke, would be covered with double tarpaulin and sealed at the transporter’s cost and would be sampled individually at loading and unloading point by a public analyst.
iii. Penalty charge at the rate of Rs.4000/-per metric ton to be imposed in the event of any variation on account of quality and quantity of Hard Coke.
4. It is the case of the plaintiffs that the said consignment was transported within the contracted period but the defendant company deducted a total amount of Rs.25,41,600.00 during the period from August, 1994 to February, 1995. On representation, a sum of Rs.6,35,400.00 has been refunded on 19.12.1995 keeping a balance of Rs.19,06,200.00.
5. The case of the appellant-defendant is that as per the purchase order dated 12.11.1993, the penal charges were fixed at Rs.4000/-per metric ton. The break-up of this penalty amount was Rs.3000/-as the cost of coke and Rs.1000/-as penalty towards difference in quality of the coke received at the delivery point and in accordance with the report of the analyst. Out of the total deduction of Rs.25,41,600/- calculated at the rate of Rs.4000/-per metric ton, Rs.19,06,200/-was price of the coke found deficit in quantity at the delivery point at the rate of Rs.3000/-per metric ton. The penal charge of Rs.6,35,400/-regarding the deficiency, which was earlier imposed, has now been released.
6. On the basis of the pleadings of the parties, the following main issues were framed:-
vi. Whether the defendant is entitled to deduct the amount from the bills for short supply to the extent of Rs.19,06,200/- and whether it is refundable to defendant?
vii. Whether the plaintiffs are entitled to the decree sought for?
viii. Is it fact that every truck was sampled individually by public analyst M/s. S.G.S. India Ltd.?
7. The learned Trial Court recorded a finding in favour of the plaintiffs for a money decree of Rs.19,06,200/-with interest at the rate of 18% per annum from 19.12.1995 till the institution of the suit.
8. The Trial Court held that in terms and condition of contract (Exhibits 1 & 2) in the event of any complaint regarding quantity or quality, it was to be made known to the plaintiffs in respect of each truck and within 30 days of the receipt of consignment, payment was to be made after adjustment of penalty, if any. As per para 20 of the written statement, the deductions were made after 30 days from receipt of consignment. Since the payment had to be made by the defendant company within 30 days, therefore, the Clause providing for imposition of penalty, was rendered redundant. The Trial Court also noted that each truck was not sampled individually. With regard to different letters (Exhibit ‘B’ series) regarding deficiency of quality and quantity, it has been noted by the Trial Court that these were addressed to S.G.S. India Ltd., not to the plaintiffs. The Trial Court concluded the defendant had failed to prove that any information with respect to shortage of material
DDA & Others Versus Joginder S. Monga & Others
Clariant International Ltd. & Another Versus Securities & Exchange Board of India
Penalty clause under Section 74 requires proof of actual loss for reasonable compensation; unproven forfeiture invalid.
The obligation of the state to act fairly and reasonably in contractual disputes, and the importance of respecting the specific terms of a contract.
The imposition of a penalty under the Bihar Finance Act was found to be unjustified when the goods were tax-paid and no road permit was required, establishing the principle that penalties must be leg....
The contractor is not liable for destination shortages absent sufficient evidence, affirming the court's findings on liability for withheld amounts.
The court established that CWC was required to prove the actual damage or loss only if it was possible to establish the same, and upheld the Arbitral Tribunal's decision based on the evaluation of ev....
The Arbitral Tribunal's interpretation of contract clauses is upheld, confirming that allegations of simple fraud do not render the claims non-arbitrable under Section 34 of the Arbitration and Conci....
Damages for loss of expected profits can be claimed in breach of contract cases, provided the breach is established and the loss is evidenced.
Unilateral deductions of demurrage charges from a contractor's bills are impermissible without proper determination of liability as per contractual obligations.
The court established that mere omission from income disclosures does not signify concealment without intent to hide income, reinforcing distinctness between assessment and penalty proceedings.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.