IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
M/s Metal Engineering And Forging Company - Appellant
Versus
Central Warehousing Corporation & Anr. - Respondents
FAO (COMM) 5 of 2023 & CM APPL. 886 of 2023, CMAPPL. 884 of 2023
Decided On : 22-11-2023
penalty - Arbitration and Conciliation Act, 1996 - Section 34 - Clause 3 of the Agreement
Fact of the Case:
The appellant, M/s Metal Engineering and Forging Company (MEFC) challenged an Arbitral Award rendered by an Arbitral Tribunal comprising of a Sole Arbitrator, which rejected MEFC's application preferred under Section 34 of the Arbitration and Conciliation Act, impugning an order rendered by the learned Commercial Court. The disputes between the parties essentially relate to MEFC's claim for a refund of the amounts withheld/recovered by respondent no.1, Central Warehousing Corporation (CWC) on account of delay in transporting cargo.
Finding of the Court:
The court found that CWC had suffered a loss of goodwill and upheld the Arbitral Tribunal's decision to accept CWC's contention, rejecting MEFC's claim for the remaining amount and assailed the impugned award to the said extent.
Issues: The principal question addressed was whether the decision of the Arbitral Tribunal to accept CWC's contention vitiates the impugned award on the ground of patent illegality.
Ratio Decidendi: The court applied Section 74 of the Indian Contract Act, 1872, and established that CWC was required to prove the actual damage or loss only if it was possible to establish the same. The court found that CWC had claimed loss on account of goodwill and upheld the Arbitral Tribunal's decision based on the evaluation of evidence.
Final Decision: The appeal was dismissed, and the court found no fault with the learned Commercial Court declining MEFC's application under Section 34 of the A&C Act.
JUDGMENT
Vibhu Bakhru, J. - The appellant, M/s Metal Engineering and Forging Company (hereafter `MEFC') has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an order dated 13.09.2022 (hereafter `the impugned order') rendered by the learned Commercial Court.
2. By virtue of the impugned order, the learned Commercial Court had rejected MEFC's application preferred under Section 34 of the A&C Act, being OMP(Comm.) No. 1/19 captioned M/s Metal Engineering & Forging Company v. Central Warehousing Corporation & Anr., whereby MEFC had challenged an Arbitral Award dated 29.09.2018 (hereafter `the impugned award') rendered by an Arbitral Tribunal comprising of a Sole Arbitrator.
3. The disputes between the parties essentially relate to MEFC's claim for a refund of the amounts withheld/recovered by respondent no.1, Central Warehousing Corporation (hereafter `CWC') on account of delay in transporting cargo. MEFC claims that CWC is not entitled to recover any amount as it has not proved that it has suffered any loss on account of any delay in transportation of the goods. MEFC also claims that delays were on account of reasons beyond its control. CWC claims that in terms of the contract between the parties, it is entitled to impose a penalty. It disputes that it has not suffered any loss and claims that it has suffered loss of goodwill, which cannot be precisely quantified or proved. The Arbitral Tribunal accepted CWC's contention. However, since the Committee constituted by CWC had quantified that a penalty in the sum of Rs.22,00,000/- was imposed on account of delays that were for justifiable reasons, the Arbitral Tribunal had allowed MEFC's claim to the said extent against MEFC's claim for a sum of Rs.49,89,124/- along with interest. MEFC is aggrieved to the extent that its claim for the remaining amount was not allowed and assailed the impugned award to the said extent.
4. There is no serious dispute that CWC had recovered transportation charges from its customers, and that, the penalty levied for the delay in transportation of goods does not correspond to any monetary loss suffered by CWC, on account of any deduction or discount in the charges payable by CWC's customers for the transportation of goods. However, CWC has sought to justify the levy of penalty on the ground of loss of goodwill suffered by it.
5. The principal question to be addressed is whether the decision of the Arbitral Tribunal to accept CWC's contention vitiates the impugned award on the ground of patent illegality.
6. MEFC is a proprietorship concern and is stated to possess technical expertise in the business of handling and transportation of cargo and manufacturing of defence stores. MEFC is carrying on the business of providing the aforesaid services to government organisations, semi-government organisations and public sector companies, in terms of the respective contracts entered into with them.
7. On 17.09.1997, CWC invited tenders for appointment of contractors (H&T Contractors) (on regular basis) for providing handling and allied services, and transportation by road of Import and Export Cargo at ICD Kanpur. MEFC submitted its offer pursuant to the aforesaid notice and was successful. On 09.10.1997, an ad hoc contract for the aforesaid work was entered into between MEFC and CWC, which was extended on a month-to-month basis till 09.12.1997.
8. On 17.12.1997, CWC awarded the regular contract to MEFC for the period of two years for handling and transportation of containers from ICD Kanpur to JNP, Navi Mumbai and vice versa. The agreement dated 17.12.1997 (hereafter `the Agreement') stipulated that the transportation period would be seven days, commencing from the date of the job order. CWC reserved the right to impose penalty at the rate of Rs.2,000/- per Twenty Equivalent Units (TEU) per day for delay in transportation of container(s) beyond seven days.
9. CWC recovered various amounts on ac
Indian Oil Corporation Vs. M/s Lloyds Steel Industries Ltd.
Kailash Nath Associates v. Delhi Development Authority & Anr.
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.
Vishal Engineers and Builders Vs. Indian Oil Corporation Limited
Indian Oil Corporation Vs. M/s Lloyds Steel Industries Ltd.
Kailash Nath Associates v. Delhi Development Authority & Anr.
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.
Vishal Engineers and Builders Vs. Indian Oil Corporation Limited
The court emphasized that an arbitral award must be reasoned and address core contractual issues, with judicial intervention restricted to cases of patent illegality under Section 34 of the Arbitrati....
The scope of interference by a court in an arbitration award is limited to the grounds specified in Section 34 of the Arbitration and Conciliation Act, 1996. A court cannot set aside an award on the ....
The court emphasized that for liquidated damages to be enforceable, the claimant must prove actual loss and the clause must represent a genuine pre-estimate of damages.
The main legal point established in the judgment is the limited grounds for challenging arbitral awards under Section 34 of the A&C Act, emphasizing the principles of public policy and fundamental In....
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
The court can set aside an arbitral award under Section 34 if it violates substantive law, contract terms, or public policy, especially when procedural requirements aren't met or if the award is pate....
An Arbitral Tribunal must adhere to explicit contractual terms without imposing external fairness standards, as such actions may result in rewriting the contract, which is impermissible under arbitra....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
An arbitral award is not subject to re-evaluation of the merits as long as it does not contravene public policy; parties are entitled to payments as per contractual obligations fulfilled, irrespectiv....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.