SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Jhk) 577

IN THE HIGH COURT OF JHARKHAND AT RANCHI
SUJIT NARAYAN PRASAD, SUBHASH CHAND, JJ.
M/s Gautam Construction - Petitioner
Versus
State of Jharkhand & Ors. - Respondents
L.P.A. No. 108 of 2021
Decided On : 21-12-2022

Advocates Appeared:
For the Appellant : Mr. Kalyan Roy.
For the Respondents: Mr. P.A.S. Pati, GA-II.

The central legal point established in the judgment is the requirement to provide an opportunity for the parties to be heard before rescinding a contract, in accordance with the principles of natural justice.

Headnote:

rescind - contract - [Section 10 of the Letters Patent] - The court discussed the rescinding of the contract between the parties and the recommendation for blacklisting the writ petitioner firm. The legal provisions related to the principles of natural justice were highlighted, and the court's decision was influenced by the lack of opportunity for the writ petitioner to be heard before rescinding the contract.

Fact of the Case:

The writ petitioner firm was awarded a construction contract by the Rural Works Department, but faced difficulties in completion due to non-cooperation from the respondents. The contract was rescinded without providing an opportunity for the writ petitioner to be heard.

Finding of the Court:

The court found that the decision to rescind the contract without providing an opportunity for the writ petitioner to be heard violated the principles of natural justice. The court also noted that the order for blacklisting was premature.

Issues: Violation of principles of natural justice, premature order for blacklisting

Ratio Decidendi: The court held that the decision to rescind the contract without providing an opportunity for the writ petitioner to be heard violated the principles of natural justice. The court also emphasized the need for a logical end to any allegations against the writ petitioner, which could only be achieved through a decision based on a show cause notice.

Final Decision: The court quashed the order to rescind the contract and remitted the matter to the authority for issuing a show cause notice to the writ petitioner and taking a decision in accordance with law.

JUDGMENT :

Sujit Narayan Prasad, J.

1. This intra court appeal under Clause 10 of the Letters Patent is directed against the order/judgment dated 20.01.2021 passed by learned Single Judge of this Court in W.P.(C) No. 3304 of 2015, whereby and whereunder, while dismissing the writ petition the decision taken by the Executive Engineer, Rural Works Department, Hazaribagh as contained in Letter dated 17.02.2014 appended as Annexure-5 to the writ petition by which the contract entered in between the parties has been rescinded with a recommendation to blacklist the writ petitioner firm, has refused to interfere with the impugned order.

2. The brief facts of the case as per the pleading made in the writ petition required to be enumerated, read as under:

The Rural Works Department invited a tender for construction of road from Sukul Katha to Dudhi Garha in which the writ petitioner along with other bidders have participated in which the writ petitioner has been found successful and an agreement No. 36F2 of 2011-12 has been executed in between the writ petitioner and the Rural Works Department on 17.10.2011.

It is the case of the writ petitioner that although the agreement was executed on 17.10.2011 but the work order was issued in the month of November, 2011 and immediately thereafter, the writ petitioner company started the construction work.

The writ petitioner firm, although had to face difficulties in completion of the construction of the work, has completed 70% of the work. Thereafter, for construction of road, bitumen was required which was to be purchased from the government company like Indian Oil Limited or Hindustan Petroleum etc. for which a permit was required to be issued by the government department but the respondent did not issued permit due to which the rest of the work was not completed.

The respondent no.3 vide letter dated 04.01.2014 directed the writ petitioner to appear before him by 15.01.2014 for signing final bill as the department has already published notice in daily newspaper Hindustan dated 30.11.2013 whereby the writ petitioner was informed to sign the final bill on 04.12.2013. It was further informed that if the writ petitioner does not sign the final bill, it will be presumed that it has accepted the measurement and the department will recommend for its blacklisting.

It is the case of the writ petitioner that several letter were issued to the respondents to provide permit to enable it to obtain bitumen from the government company and also requested to protect the partners and the employees from the hand of extremist with a further request to provide land in between 4th to 5th km which is Raiyati land and raiyats are obstructing the writ petitioner from connecting the construction over the said land, but, the respondents did not provide with any permit and security.

The respondents vide letter dated 04.01.2014 informed the writ petitioner that the agreement shall be rescinded and the writ petitioner would be black listed if it failed to sign the final bill. The writ petitioner vide letter dated 17.10.2014 requested the respondent no.2 to extend the period for completing the work for three months which was duly extended.

Thereafter, the respondent no.3 took steps for cancellation of the agreement and directed the writ petitioner to sign the final bill by 04.12.2013 and vide order dated 17.02.2014 has rescinded the agreement and also forfeited the security deposit and also recommended for its black listing without giving the writ petitioner with any opportunity of hearing.

3. It is the grievance of the writ petitioner that even though there is latches on the part of the respondent for not providing bitumen and other infrastructure but without taking into consideration the fact that the work has been initiated and 70% of the work has been completed, bill has been submitted periodically, the money has been disbursed but due to the non-supply of the bitumen, the work could not have been completed in entirety.

4. The writ

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top