2009 Supreme(Mad) 4435
High Court of Judicature at Madras
THE HONOURABLE MR. JUSTICE M. VENUGOPAL
Manickam
Versus
Nirmala Devi & Another
C.R.P.(NPD).No.2827 of 2009 & M.P.No.1 of 2009
Decided on: 27-10-2009
Important Points
Subject
Civil Law - Execution Proceedings
Act Referred
Headnote
Comparison of Signatures - Civil Revision Petition - Indian Evidence Act - Section 73, Order 21 Rule 32 - The court discussed the comparison of disputed signatures, the admissibility of uncertified payments, and the requirement for obtaining the opinion of a handwriting expert. The decision was influenced by the interpretation of Section 73 of the Indian Evidence Act and relevant case law.
Fact of the Case:
The court considered a Civil Revision Petition filed against an order related to the settlement of proclamation to determine the value of properties in an execution petition. The petitioner claimed to have paid lifetime maintenance to the respondent, while the respondent denied receiving the payment.
Finding of the Court:
The court found that the petitioner had not taken necessary steps to prove the alleged signature of the respondent and directed the petitioner to obtain the opinion of a handwriting expert within a specified period.
Issues: The issues revolved around the admissibility of disputed signatures, the requirement for proof of payments, and the admissibility of uncertified payments in execution proceedings.
Ratio Decidendi: The court emphasized the need for obtaining the opinion of a handwriting expert to prove disputed signatures and highlighted the admissibility of uncertified payments in execution proceedings.
Final Decision: The Civil Revision Petition was disposed of with directions for the petitioner to take necessary steps to obtain the opinion of a handwriting expert.
For the Petitioner:Gandhi, Senior Counsel, for R.G. Narendhran, Advocate.
For the Respondents:A.K. Kumarasamy, Advocate.
The petitioner/first respondent/judgment debtor has filed this Civil Revision Petition as against the order dated 27. 2009 in E.P.No.81 of 2007 in O.S.No.700/1996 and the consequential auction notice dated 28. 2009 passed by the learned Principal District Munsif, Erode.
2. The Executing Court, while passing orders in E.P.No.81 of 2007, has, inter alia, come to the conclusion that the plea of the revision petitioner/husband/judgment debtor that he has paid a sum of Rs.25,000/-as lifetime maintenance to the respondent/wife/decree holder has not been proved and rejected the said plea and further ordered for settlement of proclamation in order to determine the value of the execution petition mentioned properties and posted the matter to 04.08.2009.
3. The learned counsel for the revision petitioner/ husband submits that the Executing Court has committed an error in not considering Ex.R.1 one time settlement receipt in a proper and real perspective when R.W.2 and R.W.3 have categorically deposed that the respondent/wife has received a sum of Rs.25,000/-towards one time settlement for which she has issued a receipt on 25.08.2002 and thereby a substantial injustice has been caused to the revision petitioner and as a matter of fact, R.W.2 and R.W.3 have spoken about the genuineness of Ex.R.1 without any ambiguity and added further, the respondent/decree holder has remained silent for well over 8 years after the closure of the second execution petition viz., E.P.No.39 of 2000 on 21.03.2000 and the present E.P.No.81 of 2007 has been filed only to grab ransom under the guise of maintenance and in Ex.R.1 the first witness is none other than the father of the respondent/decree holder and he has refused to receive the Court summons and indeed, the claim in the present execution petition is only Rs.1,15,500/-but the total market value of the schedule properties in the execution petition is about Rs.40 lakhs and therefore, there is nexus or proximity or any valid reason in bringing the entire properties for auction sale and therefore, prays for allowing the civil revision petition.
4. It is the specific contention of the learned counsel for the revision petitioner that the Executing Court has compared the signature of the respondent/decree holder in Ex.R.1 receipt with that of the signature seen in the execution petition filed by the respondent/decree holder and has come to the conclusion that there is a market difference in regard to the two signatures and when Ex.R.1 receipt is very much denied on the side of the respondent/ decree holder to the effect that she has not executed the same then the revision petitioner/husband has not taken any steps to send the signatures for comparison to be made by a Forensic Science Department/Expert and in law, a Court of law should not itself compare the disputed signatures without assistance of any expert and in this regard, in the present case the comparison done by the Executing Court is against the tenor of the decision of Honourable Supreme Court in O. Bharathan V. K. Sudhakaran and Another (1996) 2 Supreme Court Cases 704 wherein it is held that Court should not itself compare the disputed signatures without assistance of any expert when the signatures with which the disputed signatures are to be compared are themselves not the admitted signatures.
5. He also cites the decision of this Court in Ammani Ammal V. 1. Dhanalakshmi Bank Limited, Tiruppur and 6 Others 2008 (1) CTC 816 at page 817 wherein it is held as follows:
Though Section 73 empowers Court to compare signatures it would be advisable for Court to refer matter to expert when there is a serious dispute with regard to signature and where signatures are found in many documents and even execution of mortgage deed is in dispute and moreover, signature can be compared with admitted signature available prior in point of time and contemporaneous as lapse of time may result in difference in signature of a person."
6. In response, the le