SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2019 Supreme(Mad) 2676

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Sathish Kumar, J.
M/s. Kone Elevator India Pvt. Ltd., Rep. by its Company Secretary, C.V.S. Krishna Kumar, Aynambakkam, Chennai - Petitioner
Versus
M/s. Indo Pacific Software and Entertainment Limited, Nagpur & Another - Respondent
Original Petition No. 198 of 2011
Decided On : 04-09-2019

Advocates Appeared:
For the Petitioner:R. Murari (Sr. Counsel), K.K. Muralitharan, Advocate.
For the Respondents:H. Karthik Seshadiri for M/s. Sayee and Thomas, Advocates.

The subsequent contract did not supersede the previous contract, and the damages awarded were prohibited by the contract.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 34 - The petitioner challenged the arbitration award under Section 34 of the Arbitration and Conciliation Act, 1996, on various grounds, primarily arguing that the subsequent contract superseded the previous contract and that the damages awarded were prohibited by the contract. The court analyzed the terms of the contracts and found that the subsequent contract did not supersede the previous contract and that the damages awarded were indeed prohibited by the contract. The court set aside the award in respect of the counter claim and confirmed the rest of the award.

Fact of the Case:

The petitioner, a manufacturer and supplier of elevators and escalators, entered into agreements with the respondent for the supply, erection, and installation of elevators and escalators. The respondent failed to make payment for the escalators, leading to a dispute. The matter was referred to arbitration. The arbitrator rejected the petitioner's claim for cancellation charges and allowed the respondent's counter claim for compensation for loss of business income. The petitioner challenged the award on various grounds, primarily arguing that the subsequent contract superseded the previous contract and that the damages awarded were prohibited by the contract. The court analyzed the terms of the contracts and found that the subsequent contract did not supersede the previous contract and that the damages awarded were indeed prohibited by the contract. The court set aside the award in respect of the counter claim and confirmed the rest of the award.

Finding of the Court:

The court analyzed the terms of the contracts and found that the subsequent contract did not supersede the previous contract. The court also found that the damages awarded were prohibited by the contract. The court set aside the award in respect of the counter claim and confirmed the rest of the award.

Ratio Decidendi: The subsequent contract did not supersede the previous contract, and the damages awarded were prohibited by the contract.

Result: The court set aside the award in respect of the counter claim and confirmed the rest of the award.

JUDGMENT :

Prayer: This Original Petition has been filed under section 34 of the Arbitration and Conciliation Act that the Award of the second respondent dated 20.10.2010 extent that it rejects the claim of the petition for cancellation charges and allows the counter claims of the first respondent may be set aside.

Aggrieved over the Award of the Sole Arbitrator rejecting the major claim and allowing the counter claim, the present petition has been filed challenging the Award on various grounds.

2. Brief facts leading to filing of this petition is as follows :

The petitioner has been engaged in manufacturing and supply of elevators and escalators and maintenance thereon under the collaboration with Kone Corporation, Finland. The respondent approached the claimant for supply, erection and commissioning of 5 elevators and 7 escalators for their projects one at Poonam Mall and other at Multiplex complex at Wardhaman Nagar, Nagpur. After negotiation, two base agreements were entered into between the claimant and the respondent on 19.12.2005 one in respect of supply, erection and installation of one goods cum passenger elevator and 4 passenger elevators along with service specification and other in respect of supply, erection and installation of escalators. Subsequently, two supplemental agreements were entered into on 16.02.2006 both relating to the designing and supply of escalators with technical specifications and for installation, testing and commissioning.

3. As per the terms of the agreement, the contract price for 7 escalators was Rs.1,22,95,000/- and the price for 5 escalators was Rs.70,50,000/-. The payment schedule for the elevators is as follows :

(i) 30% of the Contract value fixed free advance along with order

(ii) 20% of the Contract value at the time of submission of the general arrangement drawing [GAD]

(iii) 40% of the contract value upon intimation that the materials are ready to despatch

(iv) 5% of the contract value upon commencement of intimation.

So far as escalators are concerned, the schedule of payment as per the supplemental agreed letter 31.12.2005 is as follows :

(i) 30% of the contract value as fixed free advance along with order

(ii) 60% of the contract value upon intimation that the materials are ready for despatch

(iii) 5% of the contract value upon commencement of the installation

(iv) 5% of the contract value upon completion of the installation.

In the event of the respondent's failure to make payment within the stipulated period, the respondent would be liable to pay interest % 24% p.a. from the day of default on the overdue amount.

In the event of cancellation of the contract by the respondent, the claimant would be charging the respondent as follows :

(a) 15% of the contract value, if the order is cancelled before the General Agreement Drawing is prepared.

(b) 25% of the Contract value, if the order is cancelled within one month after General Agreement Drawing is approved

(c) 80% of the Contract value, if the order is cancelled after two months of the approval of general agreement drawing

(d) 90% of the Contract value, if the Order is cancelled after intimation that materials are ready for despatch.

Accordingly, job orders were given for manufacture and supply of 7 escalators in their China Office on 28.03.2006 and which was confirmed by the Claimant's China office on 04.04.2006. The claimant completed installation and erection of elevators and the escalators at the multiplex complex site at Wardhaman Nagar. During the process of installation and erection of escalators and elevators, the claimant underwent lot of difficulties as the site was not made available by the respondent with the following defects :

(a) The margin home was not ready shaft's brick work on the ground floor was not completed

(b) shaft was not lasted and scaffolding was not provided

(c) entrance hall was not provided and three phase, two phase electric power supply was not provided.

With the above difficulties, the claimant completed the erection/in

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top