2022 Supreme(Mad) 2113

IN THE HIGH COURT OF JUDICATURE AT MADRAS
ABDUL QUDDHOSE, J.
K. Subramaniyan - Appellant
Versus
The Executive Engineer, Operation and Maintenance Tamil Nadu Generation and Distribution Corporation Limited, Perambalur & Others - Respondent
W.P. No. 14476 of 2022
Decided On : 13-06-2022

Important Points

The court's decision emphasized the importance of fair hearing and consideration of applications for public services, taking into account any pending disputes or legal proceedings related to the property in question.

Subject

Administrative Law - Mandamus

Act Referred

CONSTITUTION OF INDIA : Art.226

Headnote

Mandamus - Electricity Service Connection - The court directed the respondent to pass final orders on the petitioner's application for free electricity service connection within twelve weeks, considering the ownership dispute and pending Civil Suit.

Fact of the Case:

The petitioner filed a Writ Petition seeking a Mandamus to direct the respondent to provide free 3 HP electricity power supply to a well situated on agricultural land. The petitioner claimed that despite applying for the service in 2003, it had not been granted due to a long delay.

Finding of the Court:

The court directed the respondent to consider the petitioner's application for electricity service connection on its merits and in accordance with the law, after affording a fair hearing to the petitioner and the parties involved in the ownership dispute and pending Civil Suit.

Issues: Delay in granting free electricity service connection and ownership dispute over the property.

Ratio Decidendi: The court emphasized the need for a fair hearing and consideration of the petitioner's application for electricity service connection, taking into account the ownership dispute and pending Civil Suit.

Final Decision: The Writ Petition was disposed of with the direction for the respondent to pass final orders on the petitioner's application for free electricity service connection within twelve weeks.

Advocates appeared:
For the Petitioner:S. Gunasekaran, J. Milton Arul Rajendran, Advocates. For the Respondents: Abul Kalam, Standing Counsel.

JUDGMENT

(Prayer: Writ Petition filed under Article 226 of the Constitution of India to issue a Writ of Mandamus directing the 1st respondent to give 3 HP free electricity power supply to Well situated at Survey No.203/9B, Agricultural land an extent of Hectare are 57.50, Nattarmangalam Village, Alathur Taluk, Perambalur District, Patta No.229 in pursuant to the 1st respondent.)

1. This Writ Petition has been filed for a Mandamus seeking for a direction to the 1st respondent to give free 3 HP electricity power supply to a Well situated at Survey No.203/9B, Agricultural land with an extent of Hectare 57.50, Nattarmangalam Village, Alathur Taluk, Perambalur District.

2. By consent of both the parties, the main writ petition is taken up for final disposal at the admission stage itself.

3. The petitioner claims that he has applied for free electricity service connection on 29.09.2003. He has also submitted documents for getting free electricity service connection and the same has also been enclosed along with this writ petition. It is the contention of the petitioner that despite the long passage of time, till date, the free electricity service connection has not been granted by the respondents. In such circumstances, he has filed the present writ petition.

4. Heard Mr.S.Gunasekaran, the learned counsel for the petitioner and Mr.Abul Kalam, learned Standing counsel for the TANGEDCO who accepts notice on behalf of the repsondents.

5. On instructions, the learned standing counsel for the respondents would submit that pertaining to the ownership of the property, there is a dispute and a Civil Suit is pending.

6. No prejudice would be caused to the respondent if the petitioner's application seeking for grant of electricity service connection is considered on merits and in accordance with law, after affording a fair hearing to the petitioner and the rival claimants and any other necessary party whom the respondent deems fit to enquire.

7. For the forgoing reasons, this Court directs the 3rd respondent to pass final orders on the petitioner's application dated 29.09.2003 seeking for grant of free electricity service connection in his name for the aforementioned property within a period of twelve weeks from the date of receipt of a copy of this order, after affording a fair hearing to the petitioner and the parties who have filed the Civil suit in respect of the very same property and any other party whom the 3rd respondent deems fit to enquire.

8. With the aforesaid directions, the Writ Petition is disposed of. No costs.