2022 Supreme(Mad) 3590
IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
M/s. KHEC Technologies (India) Pvt. Ltd., Chennai - Appellant
Versus
Corporation of Chennai - Respondent
O.P. No. 1041 of 2017
Decided On : 08-09-2022
For the Petitioner:M/s. B. Sudarshan, Advocate. For the Respondent: G.T. Subramanian, SC (Corpn.).
The main legal point established in the judgment is the requirement for evidence to support escalation and loss of profit claims in construction contracts, as well as the application of relevant legal principles to interpret and uphold the arbitral award.
Headnote:
Arbitration - Construction Contract - Arbitration and Conciliation Act, 1996 - [ESCALATION, LOSS OF PROFIT] - Section 34 of Arbitration and Conciliation Act, 1996 - Summary of the acts and sections referenced and discussed by the court: The court discussed the legal provisions related to escalation claims and loss of profit claims in the context of construction contracts. It referred to the relevant contract law and the requirement for evidence to support such claims. The court highlighted the principles established in P.M.Paul v. Union of India and other relevant case laws to interpret the legal framework applied in reaching its decision.
Fact of the Case:
The dispute arose from a construction contract for a dispensary. The petitioner challenged the arbitral award in relation to two disallowed claims: escalation and loss of profit. The respondent terminated the contract due to delays, and the petitioner raised the dispute, leading to the arbitral tribunal's decision.
Finding of the Court:
The court found that the rejection of the escalation and loss of profit claims by the arbitral tribunal did not constitute a patent illegality warranting interference. It emphasized the need for evidence to support such claims and upheld the arbitral award.
Issues: The issues involved the challenge to the arbitral award in relation to the escalation and loss of profit claims, the evidence presented to support these claims, and the legal principles governing such claims.
Ratio Decidendi: The court held that the rejection of the claims by the arbitral tribunal was based on a reasonable appraisal of the evidence and did not constitute a patent illegality. It emphasized the requirement for evidence to support escalation and loss of profit claims in construction contracts.
Final Decision: The Original Petition was dismissed without any order as to costs.
JUDGMENT
(Prayer: Original Petition filed under Section 34 of Arbitration and Conciliation Act, 1996, pleased to set aside the award in so far as Claim Nos.11, 14 and 17 and direct the respondent to pay Rs.8,27,278/- towards the said claims with interest at 18% from 04.11.2015 till date of realization.)
1.The dispute relates to and arises out of a contract awarded by the respondent to the petitioner for the construction of a dispensary. The contract was required to be executed in ten months and the contract price was Rs.52,53,399.55/-. The execution of work was delayed on account of multiple reasons, including re-location of the site. Eventually, after issuing a show cause notice, the respondent terminated the contract by communication dated 24.05.2011, which was received by the petitioner on 31.05.2011. In these circumstances, the petitioner raised a dispute and, upon constitution of an arbitral tribunal, submitted a claim statement in which about 26 claims were made. Out of the 26 claims, about 14 claims were allowed in part by the arbitral award dated 25.02.2017 (the Award). The petitioner has challenged the Award only in respect of three disallowed claims. Out of the three disallowed claims, one claim, namely, the claim pertaining to refund of security deposit was settled while this petition was pending adjudication. As a result, this petition survives only in respect of two claims, namely, the claims for escalation and loss of profit.
2. Learned counsel for the petitioner challenged the Award in relation to the escalation claim on the ground that the contract does not contain a clause prohibiting the grant of escalation and, therefore, the refusal of the arbitral tribunal to grant escalation calls for interference. After referring to the petitioner's pleadings in relation to escalation, whereby the basis of claim was communicated, he pointed out that the only response of the respondent to such claim was that the contract does not contain a clause for escalation. He contended that the ten month contract could not be executed as per schedule on account of various reasons attributable to the respondent, and turned to the findings of the arbitral tribunal with regard to attribution of responsibility for delay. With specific reference to paragraphs 4.15, 4.20 and 4.26 of the Award, learned counsel pointed out that the arbitral tribunal concluded that the delay was not attributable to the claimant, and that, therefore, the respondent had no right to terminate the contract on the ground of delay by the claimant. After recording such findings, learned counsel submitted that the conclusions at paragraphs 15.3 to 15.5 of the Award are patently illegal. By drawing reference to the judgment of the Hon'ble Supreme Court in P.M.Paul v. Union of India (P.M.Paul), AIR 1989 SC 1034, learned counsel submitted that escalation is the natural consequence of passage of time and that an escalation claim may be awarded unless prohibited by the relevant contract. By relying on the judgment in K.N.Sathyapalan v. State of Kerala (Sathyapalan), (2007) 13 SCC 43, he submitted that escalation should have been awarded once the arbitral tribunal concluded that the respondent was responsible for delay. In the context of the findings on delay and termination, learned counsel contended that the findings of the arbitral tribunal on escalation warrant interference in as much as such findings are directly contrary to the law laid down in P.M.Paul and Sathyapalan.
3. Learned counsel dealt with the loss of profit claim next. By referring to the pleadings in relation thereto, he submitted that loss of profit was claimed at 20% of the incomplete contract value. By turning to the counter statement of the respondent, he stated that the respondent did not deal with the claim for loss of profit. With reference to paragraph 18.4 of the Award, learned counsel submitted that the conclusion arrived at by the arbitral tribunal is not a plausible conclusion in as much as the t