BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
N. SESHASAYEE, P. VADAMALAI, JJ.
M.K. Srinivasan – Appellant
Versus
R. Ramasamy – Respondent
A.S. (MD) No. 104 of 2016, C.M.P. (MD) No. 6660 of 2016
Decided On : 23-09-2024
JUDGMENT :
N. SESHASAYEE. J.
PRAYER: Appeal filed under Section 96 of the Civil Procedure Code r/w Order 41 Rules 1 and 2 of C.P.C., against the judgment and decree dated 19.01.2016 in O.S.No. 6 of 2011 on the file of the Principal District Judge, Karur.
1. Challenging a decree dismissing their suit for specific performance in O.S.No. 6 of 2011 on the file of the Principal District Court, Karur, the plaintiffs therein have preferred the present appeal. Instead of granting a decree for specific performance, the learned District Judge has directed the first defendant to pay the plaintiffs the advance amount of Rs.50.0 lakhs which the plaintiffs had paid, with interest at 6% p.a. There is neither any cross objection, nor any cross appeal by the first defendant. For narrative convenience, parties would be referred to by their rank before the trial court.
2. A brief statement on the case of the plaintiffs may now be stated:
(b) On 06.07.2009, vide Ext.A.1, defendants 2 to 11 had executed a General Power of Attorney authorising the first defendant to deal with the property. On the strength of this Power of Attorney, on 23.01.2010, under Ext.A.2, the first defendant had received Rs.1.0 lakh from the first plaintiff and had executed a receipt for the said sum. Ext.A2 evidences that the sale consideration for the purchase of 48.18 acres was fixed at Rs.3,02,500/- per acre.
(c) Subsequently on 24.02.2010, the first plaintiff had executed Ext.A3 document where in he had stated that on 03.03.2010, he undertook to pay Rs.49.0 lakhs as additional advance, upon which a formal sale agreement should be executed on that very day, and that the sale deed itself should be executed on 05.04.2010. Ext.A3 also reflects two additional facts: (i) that the first defendant had demanded an additional sum of Rs.7,00,000/- over and above the sale price, something the first plaintiff had agreed to pay; and (ii) that other than the documents which the first defendant had in his possession, first plaintiff would obtain the rest at his expenses.
(d) On 02.03.2010, the first plaintiff paid another sum of Rs.49.0 lakhs (in all Rs.50.0 lakhs including Rs.1.0 lakh paid under Ext.A.2). This brought into existence Ext.A.4 sale agreement dated 03.03.2010 as was contemplated in Ext.A3.
(e) Ext.A4 sale agreement (on which the cause of action would be found later), inter alia provided:
(i) that the first defendant had to survey and measure the suit properties to ascertain the actual extent available based upon which the total sale consideration payable might have to be ascertained;
(ii) that the plaintiffs should pay the balance sale consideration on 05.04.2010 and upon receiving the same, the first defendant would execute the sale deed, and if the plaintiffs default in performing their part of the contractual obligations, then they are liable to forfeit the entire advance amount;
(iii) that the first defendant should deliver the notarised copies of the documents available with him to the first plaintiff which would include a notarised copy of the receipt for payment of sale consideration to the owners of the property, the defendants 2 to 11; and
(iv) that the first defendant would execute the sale deed free of encumbrance and would also deliver the original title deeds of the property then.
(f) On 28.03.2010, the first defendant made arrangements to survey the property in the presence of the first plaintiff. However, when survey commenced, a third party objected to measure the property and claimed some share in the property, as a result of which the the survey operation aborted. It is in this backdrop, the plaintiffs issued Ext.A.5-paper publication, informing the public about Ext.A.4 sale agreement to the effect that if any
The court affirmed that time is an essential term in contracts for specific performance, and failure to perform on the stipulated date justifies termination of the contract.
In a contract for sale with reciprocal promises, a buyer's obligation to perform arises only after the seller fulfills their pre-requisite duties. The seller's failure to perform their part constitut....
Continuous readiness and willingness to perform the contract is a condition precedent for obtaining the relief of specific performance under Section 16(c) of the Specific Relief Act.
The readiness and willingness of the parties to perform their part of the contract, as per the agreement of sale, is crucial in determining the entitlement to the discretionary relief of specific per....
In a suit for specific performance, the plaintiff must demonstrate both readiness and willingness to perform the contract, and failure to do so within the stipulated time can bar the relief, regardle....
In a suit for specific performance, plaintiffs must prove continuous readiness and willingness to perform their part of the contract, supported by cogent evidence; mere assertions are insufficient.
Time is an essence of the contract in specific performance cases, and plaintiffs must prove continuous readiness and willingness to perform their obligations.
Time is of the essence in contracts for sale of immovable property; failure to act within stipulated time undermines claims for specific performance.
Plaintiff's failure to prove continuous readiness and willingness to perform contract negates entitlement to specific performance under Specific Relief Act.
The plaintiff's failure to prove readiness and willingness to perform his part of the contract within the stipulated time precluded him from obtaining the relief of specific performance.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.