SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Mad) 5029

IN THE HIGH COURT OF JUDICATURE AT MADRAS
J.Nisha Banu, R. Sakthivel, JJ.
M/s. Alliance Projects, Represented by its POA and ors. - Appellants
Versus
Uma Maheshwari - Respondent
C.M.S.A.No.38 of 2022 and C.M.P.No.8563 of 2022
Decided On : 08-04-2025

Advocates Appeared:
For the Appellant : Mr.P.H.Manoj Pandian
For the Respondent: Mr.N.Alagu Narayanan

Developers cannot concurrently invoke different remedies in an agreement regarding termination and compensation; once a choice is made, it binds subsequent actions.

Headnote:(A) Real Estate (Regulation and Development) Act, 2016 - Sections 18, 71, 72; Tamil Nadu Real Estate (Regulation and Development) Rules, 2017 - Rule 19(2) - Jurisdiction of TNRERA - Completion of project prior to RERA; Compensation for Delay - Respondent sought refund after the construction was stalled and Agreement was cancelled; Appellants failed to deliver possession as per terms of the agreement. (Paras 2, 4, 6, 12)

(B) Jurisdictional Challenges - The appellants raised questions on the jurisdiction of TNRERA and TNREAT regarding projects completed before RERA; The court held that jurisdiction was correctly exercised. (Paras 2, 8, 22)

(C) Doctrine of Election - The court emphasized that having opted to receive unpaid sums with interest under the discretion clause precludes the appellants from also invoking the termination clause for deducting liquidated damages. (Paras 20, 22)

Facts of the case:
Appellants, developers, cancelled an agreement with the respondent after construction stalled despite the respondent having paid a substantial amount for a flat. The respondent filed a complaint seeking refunds and compensation post agreement cancellation.

Findings of Court:
The Tribunal ruled in favor of the respondent for refunds plus interest and compensation.

Issues: Whether TNRERA and TNREAT had jurisdiction; applicability of liquidated damages; the relevance of the doctrine of election; and principles of natural justice concerning termination of agreement.

Ratio Decidendi: The court confirmed that the appellants could not simultaneously rely on different remedies stipulated in the agreement, aligning with the doctrine of election, which asserts that one must choose between mutually exclusive options.

Result: Appeal dismissed; appellants directed to pay the disputed amount of Rs.11,17,477/- with interest.

JUDGMENT :

J. NISHA BANU, J.

This Civil Miscellaneous Second Appeal is preferred as against the order dated 28.01.2022 passed in Appeal No.30 of 2021, on the file of the Tamil Nadu Real Estate Appellate Tribunal (TNREAT), whereby, the order dated 23.02.2021 passed in C.C.P.No.263 of 2021 on the file of Tamil Nadu Real Estate Regulatory Authority (TNRERA), has been confirmed.

2. In this appeal, the appellants/developers have raised the following substantial questions of law:

“a) Whether the learned Adjudicating Officer, TNRERA and the Hon'ble Tamil Nadu Real Estate Appellate Tribunal can exercise jurisdiction in respect of a project blocks that was completed prior to 01.05.2017.

b) Whether the “Orchid Springs” project not being a project registered/registrable under RERA and consequently, whether the same cannot be subject to any proceedings under the Act, having applied for the completion certificate prior to the commencement of the Act or the Rules and having subsequently obtained the completion certificate?

c) Whether the impugned order is passed beyond the scope of the appeal itself, without hearing the parties on the orders passed, thereby rendering the impugned order null and void for violation of principles of natural justice and the principles of audi alteram partem, forming part thereof?

d) Whether an allottee is entitled to receiving compensation under Section 18 of the Act when they are hit by the provisions of Rule 19(2) provision of the Rules?

e) Whether the learned Adjudicating Officer and the Hon'ble TNREAT have failed to consider the implications of the judgment of this Court in Subashini Thulasirani Vs SPR and RG Constructions Private Limited (2020 SCC Online Mad 2020 : (2020) 4 LW 865) and the order of the Hon'ble Supreme Court in M/s. New Tech Promoters Vs. The State of Uttar Pradesh and others (2021 SCC Online SC 1044), which was binding on the said authorities and have consequently passed judgments, which are per incuriam?”

3. The appellants are the developers and the respondent is the complainant. The respondent availed a housing loan for the purchase of a flat and booked a flat with the appellants. They entered into an agreement of sale dated 16.07.2012 and also entered into a tripartite agreement with the finance company. The respondent in total paid a sum of Rs.74,49,847/- to the appellants. Subsequently, the finance company refused to release further amount as the construction work was stalled. On 22.01.2014, the 1st appellant cancelled the agreement alleging default in payment and stated that a cheque was attached for refund of the amount. Thereafter, on 03.05.2016, the appellants sent another letter for choice of flooring and further assured to hand over the property within 24 months with a grace period of six months. The respondent has been paying EMI to the finance company and living in a rental accommodation on payment of monthly rent of Rs.18,000/-. Since the appellants failed to register the agreement of sale and to hand over possession of the flat as per the terms of the agreement, the respondent filed a complaint before the Tamil Nadu Real Estate Regulatory Authority (TNRERA) vide C.C.P.No.263 of 2019, seeking refund of the amount with interest, compensation and cost.

4. The Tamil Nadu Real Estate Regulatory Authority (TNRERA) ruled in favour of the respondent/complainant vide its order dated 23.02.2021, directing the appellants/developers to pay the amount of Rs.74,49,847/- with 10.05% interest; Rs.5,00,000/- towards compensation for mental agony and inconvenience and Rs.20,000/- toward legal expenses.

5. Challenging the said order passed by the Regulatory Authority, the appellants/developers filed appeal before the Tamil Nadu Real Estate Appellate Tribunal (TNREAT) in Appeal No.71 of 2021.

6. The Appellate Tribunal, after considering the case of the parties, held that having received the unpaid amount with interest, the appellants cannot choose the termination clause by sending termination notice dated

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top