SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 384

IN THE HIGH COURT OF JUDICATURE AT MADRAS
D.BHARATHA CHAKRAVARTHY, J.
Kamarajar Port Limited, Rep by General Manager (Operations) – Petitioner
Versus
Tamil Nadu Building and Other, Represented by its Secretary – Respondent
W.P.No.36544 of 2025
Decided On : 03-02-2026

Advocates Appeared:
For the Petitioner: Mr. Menon
For the Respondent: Ms. S.Valliammal, Ms.Shruti Khanijow, Ms. P.J. Anitha, Senior Panel Counsel

Dredging activities fall within the definition of construction work under the BOCW Act, affirming cess obligations for such activities.

Headnote:(A) Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 - Section 2(d) - Refund claim of cess under BOCW Act by petitioner for dredging work awarded to the respondent contractor - Petitioner contended that dredging does not constitute construction work under the Act and sought refund - Authority held that dredging includes navigation works and was subject to cess payment - Court affirmed that the activity falls under the definition of 'building or other construction work' and dismissed the petitioner's claim for refund. (Paras 22, 28, 33)

Facts of the case:
The petitioner sought to refund Rs.3,14,58,004/- remitted under the BOCW Act, alleging that the capital dredging activity did not qualify as construction work. A past order indicated that the dredging work was not subject to the Act, prompting the petitioner's claim for a refund. The Labour Enforcement Officer had previously indicated existing liabilities under the Act were not properly maintained.

Findings of Court:
The court found that the activity of dredging indeed falls within the scope of 'construction work' as per the legislative definitions and emphasized the importance of maintaining records of employment and compliance with the statutory requirements.

Issues: Whether dredging activities constitute 'building and other construction work' under the BOCW Act and the implications of the prior arbitral award on these proceedings.

Ratio Decidendi: The court highlighted that the definition of construction incorporates dredging and navigation works, and reiterated that the authority's earlier findings on non-applicability were unsupported and erroneous, leading to the dismissal of the petitioner's refund claims.

Result: Writ Petition dismissed.

Table of Content
1. factual background of the case (Para 1 , 2 , 3 , 4 , 5 , 6)
2. arguments presented by the parties (Para 7 , 8 , 9 , 10 , 11 , 12)
3. court's analysis of the arbitration award (Para 13 , 14 , 15 , 16)
4. analysis of statutory provisions (Para 17 , 18 , 19 , 21 , 22)
5. jurisdiction and obligations under bocw act (Para 23 , 24 , 25 , 26 , 27)
6. determination of refund claims and compliance (Para 28 , 29 , 30)

ORDER :

D.BHARATHA CHAKRAVARTHY, J.

A. The Petition:

1.This Writ Petition is filed for a mandamus directing the first respondent to refund a sum of Rs.3,14,58,004/- to the petitioner in view of the inapplicability of the Building and Other Construction Workers Cess (Regulation of Employment and Conditions of Service) Act, 1996 (hereinafter referred to as ‘BOCW Act’) for the work undertaken by the second respondent contractor.

B. The Factual Matrix:

2. The brief facts leading to filing of this writ petition are, that the petitioner owns and operates the Port at Ennore under the Ministry of Ports, Shipping and Waterways, Government of India. The Chennai Ports Authority holds the entire shares of the petitioner. In the year 2014/2015, the petitioner proposed to expand the Port by dredging the Port Basin and the shore to create additional berths. After issuing global tenders, the petitioner had awarded the contract to the second respondent by an agreement, dated 12.08.2015 for the execution of Capital Dredging Phase – III at the Port.

3. During the execution of the project, the Chief Technical Examiner of the organization made a technical inspection of the project from 02.08.2016 to 05.08.2016. While so, he observed that as per the Act, the capital dredging work will come within its purview. Even during the pre-bid clarification, the tenderer sought for waiver of the payment of cess, which was not granted and as per the conditions of the tender, the contractor was required to pay all the taxes, duties etc. However, the cess payable under the Building and Other Construction Workers’ Welfare Cess Act, 1996, (hereinafter referred to as ‘the CESS Act’) was not deducted from the contractor’s bills. On the strength of the above report, the Chief Technical Examiner of the organization, advised the petitioner to comply with the statutory liability and remit the cess.

4. Accordingly, in order to avoid any penal action and to comply with the statutory liability, the petitioner had remitted a sum of Rs.2,96,26,374/- and another sum of Rs.27,56,053/- towards the cess payable under the CESS Act with the first respondent Board. The above payments were duly acknowledged by the receipts, dated 22.02.2018 and28.08.2018.

5. In the meanwhile, a complaint was filed by the Labour Enforcement Officer, the third respondent, under Section 50 of the BOCW Act against the second respondent before the Director General of Inspection/Deputy Chief Labour Commissioner (Central), the fourth respondent, alleging breach of Section 7 and Rule 240 and prayed for imposing fine under the provisions of of the BOCW Act. Pursuant to the said complaint, proceedings were initiated by the Director General of Inspection/Deputy Chief Labour Commissioner (Central) under the BOCW Act. On 16.11.2018, the fourth respondent passed an order that the dredging of the seaport will not be a ‘construction’ activity under Section 2 (d) of the BOCW Act and held that no fine could be levied. Under the said circumstances, the petitioner made a representation to the first respondent on 19.03.2019 to reimburse the said sum of Rs.3,14,58,004/- in view of the order passed by the fourth respondent.

6. In the meanwhile, the second respondent - contractor had also initiated arbitration proceedings. On 07.03.2024, an award was also passed by the Arbitral Tribunal directing the petitioner to pay to the second respondent the amount of cess deducted and remitted to the first respondent. The said award is also under challenge in O.P.No.335 of 2024, which is pending on the file of this Court. Af

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top