IN THE HIGH COURT OF JUDICATURE AT MADRAS
D.BHARATHA CHAKRAVARTHY, J.
Kamarajar Port Limited, Rep by General Manager (Operations) – Petitioner
Versus
Tamil Nadu Building and Other, Represented by its Secretary – Respondent
W.P.No.36544 of 2025
Decided On : 03-02-2026
| Table of Content |
|---|
| 1. factual background of the case (Para 1 , 2 , 3 , 4 , 5 , 6) |
| 2. arguments presented by the parties (Para 7 , 8 , 9 , 10 , 11 , 12) |
| 3. court's analysis of the arbitration award (Para 13 , 14 , 15 , 16) |
| 4. analysis of statutory provisions (Para 17 , 18 , 19 , 21 , 22) |
| 5. jurisdiction and obligations under bocw act (Para 23 , 24 , 25 , 26 , 27) |
| 6. determination of refund claims and compliance (Para 28 , 29 , 30) |
ORDER :
D.BHARATHA CHAKRAVARTHY, J.
A. The Petition:
1.This Writ Petition is filed for a mandamus directing the first respondent to refund a sum of Rs.3,14,58,004/- to the petitioner in view of the inapplicability of the Building and Other Construction Workers Cess (Regulation of Employment and Conditions of Service) Act, 1996 (hereinafter referred to as ‘BOCW Act’) for the work undertaken by the second respondent contractor.
B. The Factual Matrix:
2. The brief facts leading to filing of this writ petition are, that the petitioner owns and operates the Port at Ennore under the Ministry of Ports, Shipping and Waterways, Government of India. The Chennai Ports Authority holds the entire shares of the petitioner. In the year 2014/2015, the petitioner proposed to expand the Port by dredging the Port Basin and the shore to create additional berths. After issuing global tenders, the petitioner had awarded the contract to the second respondent by an agreement, dated 12.08.2015 for the execution of Capital Dredging Phase – III at the Port.
3. During the execution of the project, the Chief Technical Examiner of the organization made a technical inspection of the project from 02.08.2016 to 05.08.2016. While so, he observed that as per the Act, the capital dredging work will come within its purview. Even during the pre-bid clarification, the tenderer sought for waiver of the payment of cess, which was not granted and as per the conditions of the tender, the contractor was required to pay all the taxes, duties etc. However, the cess payable under the Building and Other Construction Workers’ Welfare Cess Act, 1996, (hereinafter referred to as ‘the CESS Act’) was not deducted from the contractor’s bills. On the strength of the above report, the Chief Technical Examiner of the organization, advised the petitioner to comply with the statutory liability and remit the cess.
4. Accordingly, in order to avoid any penal action and to comply with the statutory liability, the petitioner had remitted a sum of Rs.2,96,26,374/- and another sum of Rs.27,56,053/- towards the cess payable under the CESS Act with the first respondent Board. The above payments were duly acknowledged by the receipts, dated 22.02.2018 and28.08.2018.
5. In the meanwhile, a complaint was filed by the Labour Enforcement Officer, the third respondent, under Section 50 of the BOCW Act against the second respondent before the Director General of Inspection/Deputy Chief Labour Commissioner (Central), the fourth respondent, alleging breach of Section 7 and Rule 240 and prayed for imposing fine under the provisions of of the BOCW Act. Pursuant to the said complaint, proceedings were initiated by the Director General of Inspection/Deputy Chief Labour Commissioner (Central) under the BOCW Act. On 16.11.2018, the fourth respondent passed an order that the dredging of the seaport will not be a ‘construction’ activity under Section 2 (d) of the BOCW Act and held that no fine could be levied. Under the said circumstances, the petitioner made a representation to the first respondent on 19.03.2019 to reimburse the said sum of Rs.3,14,58,004/- in view of the order passed by the fourth respondent.
6. In the meanwhile, the second respondent - contractor had also initiated arbitration proceedings. On 07.03.2024, an award was also passed by the Arbitral Tribunal directing the petitioner to pay to the second respondent the amount of cess deducted and remitted to the first respondent. The said award is also under challenge in O.P.No.335 of 2024, which is pending on the file of this Court. Af
Dredging activities fall within the definition of construction work under the BOCW Act, affirming cess obligations for such activities.
Statutory liability to pay welfare cess under labor legislation falls upon the contractor as the employer. Such liability is inherent to the statute, cannot be reallocated via contract clauses based ....
The court held that deductions for the cess on construction payments are valid under the relevant welfare legislation, affirming that activities like laying pipelines constitute construction work.
The interpretation of the Building and Other Construction Workers Act and the Cess Act requires the establishment of welfare boards for the effective levy and collection of cess; until then, contract....
The imposition of 1% cess under the Building and Other Construction Workers Act is a statutory obligation aimed at benefiting workers, and is applicable despite claims regarding the Factories Act exe....
(1) Cess could only be recovered in the manner stipulated in Cess Act and Rules framed thereunder.(2) A contractor who enters into a pure Supply Contract is statutorily exempted from levy under BOCW ....
The main legal point established in the judgment is the importance of interpreting the statute by considering the text and context, and the applicability of the enabling provision of section 3(1-A) a....
Taxes not to be imposed save by authority of law - Article 265 of Constitution is the source of power for the Union and States to impose taxes in accordance with law. Article 265 of the Constitution ....
The main legal point established in the judgment is that the labour cess is not leviable on the supply of materials and consultancy charges under the Building and Other Construction Workers' Welfare ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.