IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. ANAND VENKATESH, J.
SBI General Insurance Company Ltd., Represented by Power of Attorney Mr. Leo John - Petitioner
Versus
Saravana Global Energy Ltd. – Respondent
Arb O.P(Com.Div.) No.266 of 2024
Decided On : 18-12-2025
| Table of Content |
|---|
| 1. claimant's insurance policy and subsequent flooding damages. (Para 2 , 3 , 4 , 6) |
| 2. insurer's legal arguments against the arbitral award. (Para 11 , 12) |
| 3. court's issues for review on arbitral award. (Para 15 , 18 , 30) |
| 4. regulatory compliance regarding interest rate in arbitration. (Para 39) |
| 5. court's final decision and order regarding the arbitral award. (Para 45 , 46) |
ORDER :
N. ANAND VENKATESH, J.
This original petition has been filed under Section 34 (2)(a)(iii) of the Arbitration and Conciliation Act, 1996 (for brevity, hereinafter referred to as ‘the Act’) challenging the arbitral award dated 02.02.2024 passed by the sole Arbitrator.
2. The respondent herein was the Claimant before the Arbitral Tribunal. The Claimant is a public limited company incorporated under the Companies Act, 1956 , engaged in the manufacture of porcelain and composite insulators, with manufacturing units at Cuddalore and Madhuranthakam. The Claimant had obtained an Industrial All Risk (IAR) Insurance Policy from the insurer bearing Policy No.150591-0000-00, which covered buildings, plant & machinery, stock and equipments for a total insured value of Rs.170.50 crores, effective from 31.07.2015 to 30.07.2016.
3. On 09.11.2015, catastrophic floods caused significant damage to the stock and fixed assets located at the Claimant’s factory in Cuddalore. In accordance with the Insurance Policy, the Claimant lodged a claim for Rs.12.57 crores from the insurer. The insurer, as per the Insurance Regulatory and Development Authority of India (Insurance Surveyors and Loss Assessors) Regulations, 2015, appointed M/s.Mehta and Padamsey as the Surveyor to assess the extent of the damages. Based on the surveyor's assessment, the Respondent made two tranches of interim payments viz.,Rs. 3 crores on 17.12.2015 and Rs.2 crores on 29.09.2016.
4. The dispute arose upon the submission of the Surveyor's Final Adjustment Report dated 11.03.2017, which assessed the insurer's net liability at Rs.5,40,95,535/-, calculating the loss entirely on a market value (MV) basis. Relying on this report, the insurer made a final settlement payment of Rs.40,51,284/- on 30.03.2017. The Claimant challenged this, asserting that the policy terms mandated a settlement based on a part reinstatement value (RIV) and part market value (MV) basis. The Claimant further contended that the Surveyor's methodology was flawed by erroneously applying the principle of underinsurance to damaged items not reinstated and by improperly inflating the escalated value by adding Rs.13.59 crores to arbitrarily reach an underinsurance of 19.31%, which exceeded the 15% waiver permitted under the policy.
5. With respect to depreciation, the Claimant relied upon a certification from Anna University regarding the useful life of the kiln furniture and also considering the operational cycles asserted that the depreciation should be fixed at 30%. Whereas the Surveyor had fixed an exorbitant depreciation value of 75% without assigning any reasons. Furthermore, the Claimant contended that the Surveyor misconstrued the phrase "under each of the items" in Section 2.2(3) of the Special Provisions of the IAR Policy, interpreting it as broader categories of items listed in the policy rather than the individual damaged items intended by the Claimant. The Claimant also contended that the Surveyor had relied on the Fixed Assets Register (FAR) to calculate underinsurance, but rejected the same for determining the fixed assets and thereby operating as an estoppel against such rejection.
6. The Claimant, vide letter dated 09.08.2017, invoked arbitration over the disputes arising out of the acceptance of the survey report and settlement of the claim. The insurer resisted arbitration on the ground that a full and final settlement had already been effected. This Court vide order dated 02.04.2019, appointed a sole Arbitrator.
7. The insurer filed the statement of defence and stated that the claimant delayed in providing the lo





Haris Marine Products v. Export Credit Guarantee Corporation Limited
Ssangyong Engineering & Construction Company Limited v. NHAI
The court annulled the arbitral award for misinterpretation of insurance policy terms, improper calculation of depreciation, and lack of independent reasoning in affirming mixed assessments for claim....
Arbitral awards can be set aside only for patent illegality or public policy violations, not mere erroneous application of law or re-appreciation of evidence.
The main legal point established in the judgment is the deference to the learned Arbitrator's decisions based on a reasonable interpretation of facts and materials on record, as well as the entitleme....
Point of law: Court is unable to accept that the impugned award suffers from any patent illegality that strikes at the root of the said matter. It is also not contrary to the fundamental policy of In....
Consent obtained under economic duress can invalidate contractual agreements in arbitration; courts respect arbitral awards barring serious legal flaws.
Insurance – In absence of any ambiguity no scope for applying doctrine of contra proferentem – Insurer can write letter to Surveyor to re-assess settlement amount.
The tribunal can appoint an expert to aid its understanding, and an insurer is not bound by the surveyor's report if it relies on valid grounds to depart from it.
The claimant lacked legal standing to pursue insurance claims as rights had transferred to another entity, rendering the arbitration ineffective.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.