SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1401

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SANDEEP V. MARNE, J.
New India Assurance Co. Ltd. – Appellant
Versus
Shirdi Industries Limited – Respondent
Arbitration Petition No. 375 of 2024, Interim Application (Lodging) No. 7794 of 2024
Decided On : 09-12-2025

Advocates Appeared:
For the Appellants : R.S. Vidyarthi, Mohit Turakhia, Asim S. Vidyarthi
For the Respondents: Rohan Savant, Abirban Sen, Ranjan Dwivedi

The tribunal can appoint an expert to aid its understanding, and an insurer is not bound by the surveyor's report if it relies on valid grounds to depart from it.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Insurance Act, 1938 - Section 64-UM - Challenge against arbitration award - Unanimous award granted compensation of Rs.30,99,555/- with interest @12.5%, and costs - Tribunal justified in appointing Expert under Section 26; decision to disregard Surveyor's opinion based on evidential inadequacies. (Paras 1, 6, 18, 24, 30)

(B) Legal Principles - The Surveyor's report is not binding on the insurer and can be departed from, provided valid rationale is established. Tribunal's determinations based on material evidence and testimonies are not subject to re-evaluation in court as long as they remain within the scope of permissible judgments under the Arbitration Act. (Paras 24-28)

Facts of the case:
The petitioner, an insurance company, challenged an arbitration award resulting from a fire incident at the respondent's factory, which caused significant damage and led to claims for loss under an insurance policy. (Paras 1-2)

Findings of Court:
The Tribunal's awarding method for compensation was consistent with the contractual obligations and adequately substantiated by facts presented, justly departing from the Surveyor's assessment which lacked thorough analysis. (Paras 30, 34)

Issues: The main questions addressed included whether the Tribunal's judgment in appointing an Expert was justified and whether the claims awarded were appropriate given the evidence. (Paras 26-29)

Ratio Decidendi: The appointed Expert's findings and the overall evidence justified the award granted by the Tribunal. The approach undertaken by the Tribunal to arrive at 70% compensation for certain claims was based on adequate examination and thus valid. (Paras 19-20, 28)

Result: Arbitration Petition dismissed. (Para 35)

Table of Content
1. overview of the parties and matter of arbitration. (Para 1 , 2)
2. details on claims awarded by the arbitral tribunal. (Para 4 , 5)
3. petitioner's contention against the award. (Para 6 , 8)
4. respondent's defense against the petition. (Para 9 , 10 , 11 , 12)
5. expert appointment and relevance in arbitration. (Para 16 , 18)
6. arbitral tribunal's rationale for awarding claims. (Para 24 , 25)
7. legal principles governing arbitration claims. (Para 26 , 29)
8. court's endorsement of tribunal's findings. (Para 30 , 32)

JUDGMENT :

SANDEEP V. MARNE, J.

1. Petitioner-Insurance Company has filed the present Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (Arbitration Act) challenging unanimous Award of the Three-Member Arbitral Tribunal dated 20 September 2022. By the impugned Award, the Tribunal has awarded a sum of Rs.30,99,555/- in favour of the Respondent alongwith interest @ 12.5% p.a. from 16 August 2016 till realisation. The Arbitral Tribunal has also awarded costs of Rs.29,44,021/- to the Respondent.

2. Petitioner is a nationalised general insurance company. The Respondent is an incorporated entity engaged in manufacturing of various types of wooden boards. The Respondent has its manufacturing plants at Pantnagar (Uttarakhand), Coimbatore (Tamilnadu) and Bhiwandi (Maharashtra). The Respondent availed insurance cover under the Policy named -Industrial All Risk Policy dated 7 February 2015 from the Petitioner, which covered its factory at Pantnagar (Uttarakhand). On 6 April 2015 a fire broke out in Respondent’s plant at Pantanagar. The fire took place in the hot press loader and un-loader section of MDF production. Although the main plant was not damaged, there was substantial damage to the parts and components and some damage was also caused to six Platens and there was loss of Hydraulic Oil and Thermic Fluid. On the date of the incident, Respondent informed the Petitioner about the same. As per the provisions under Section 64-UM of the Insurance Act, 1938 (Insurance Act) a Surveyor was appointed by the Petitioner for assessment of loss/damage caused to the Respondent. On 8 April 2015, the Surveyor carried out first physical verification of the affected site. The Surveyor visited the site on 6th and 7th July 2015 for second verification. He thereafter visited the affected site on 13/14th April 2016 for the third time. On 30 May 2016, Surveyor issued final survey report assessing net loss payable by the Petitioner to the Respondent at Rs.39,82,897/-. Petitioner paid to the Respondent sum of Rs.31,91,305/-. The Respondent invoked arbitration clause and a three-member Arbitral Tribunal was constituted by the Respondent comprising of former Chairman and former Assistant General Manager, who in turn nominated the Presiding Arbitrator. The Respondent filed Statement of Claim claiming sum of Rs.55,07,924/- in following terms:-

3. The Petitioner filed its Statement of Defence. Upon completion of the pleadings, the Arbitral Tribunal in its second meeting opined that appointment of Expert was warranted and proceeded to finalise the points for determination. Petitioner objected to appointment of Expert and the objection was rejected by the Arbitral Tribunal. By order dated 25 March 2018, Arbitral Tribunal appointed Mr. Milind Bhatavdekar, as an Expert. The Expert visited the site of the incident and prepared report dated 31 August 2018. The Expert also participated in the meeting of Arbitral Tribunal. The Respondent filed affidavit of evidence. Petitioner also examined witnesses. The Expert appointed by the Arbitral Tribunal was also questioned by the Tribunal.

4. The Arbitral Tribunal thereafter made an Award dated 20 September 2022 partly allowing the claim of the Respondent. The Arbitral Tribunal has awarded total sum of Rs.30,99,555/- in favour of the Respondent in respect of following claims:

a) Platens a sum of Rs.9,39,000/-

b) Hydraulic Oil Rs.18,04,807/-.

c) Thermic Fluid Rs.8,47,896/-;

d) VFD AC Drive

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top