SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 815

IN THE HIGH COURT OF JUDICATURE AT MADRAS
A.D.MARIA CLETE, J.
Kesavaraman, S/o. Ramaiya – Appellant
Versus
Narayanan (died) – Respondent
A.S. No.636 of 2019
Decided On : 02-01-2026

Advocates Appeared:
For the Appellant : Mr.R.Rajarajan
For the Respondents: M/s.V.Srimathi

If a plaintiff fails to demonstrate continuous readiness and willingness to perform a contract, relief for specific performance can be denied despite filing within the limitation period.

Headnote:(A) Specific Relief Act, 1963 - Section 22(2) - Suit for specific performance - Plaintiff entered into agreement of sale but failed to show readiness to complete the sale within the stipulated period - Plaintiff’s claims of incorrect survey number and delay were not substantiated - Relief of specific performance denied as plaintiff showed inactivity and lack of continuous readiness to perform - Refund of advance amount improperly granted by trial court. (Paras 3, 16, 21, 24)

(B) Contract Law - Necessity for readiness and willingness - Continuous readiness and willingness to perform contract essential for seeking specific performance - Mere filing of suit within limitation insufficient without showing diligent effort to perform contract - Plaintiff's unexplained delay and lack of action were critical in denying relief. (Paras 17, 19, 20)

Facts of the case:
The appellant and deceased first defendant entered into a sale agreement related to property with a stipulated sale consideration; disputes arose over performance and property description, leading to this appeal after the trial Court denied specific performance.

Findings of Court:
The appellant’s inactivity and delay were highlighted as factors for denial of the specific performance claim, while the trial Court's order for refund was found to conflict with legal provisions and thus set aside.

Issues: (i) Whether the plaintiff was ready and willing to perform his part of the contract? (ii) Whether the plaintiff is entitled to the relief of specific performance? (iii) Whether the trial Court correctly granted refund of advance amount?

Ratio Decidendi: The court determined the plaintiff's lack of continuous readiness to perform the contract within a reasonable time frame as grounds for denying specific performance, and ruled that the trial Court's issuance of a refund was not supported by a formal claim in the plaint.

Result: Appeal dismissed with costs and trial court’s decree affirmed, granting no refund of advance amount.

Table of Content
1. factual background of the plaintiff's case. (Para 3 , 4 , 5 , 6)
2. plaintiff's arguments and claims on appeal. (Para 8 , 10)
3. court's analysis of readiness and willingness. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17)
4. ratio decidendi regarding advance refund and specific performance. (Para 20 , 21 , 22 , 23)
5. conclusion and order on the appeal. (Para 26 , 27)

JUDGMENT :

A.D.MARIA CLETE, J.

This appeal is directed against the judgment and decree dated 29.03.2019 passed by the learned Principal District Judge, Puducherry, in O.S. No. 73 of 2007.

2. The plaintiff instituted the suit for specific performance of the contract of sale dated 18.08.2004. The trial Court declined to grant the relief. Aggrieved thereby, the plaintiff has preferred the present appeal. For convenience, the parties are referred to according to their rank before the trial Court.

3. Brief facts of the plaintiff’s case: The first defendant (since deceased) was the owner of the suit property. On 18.08.2004, the plaintiff entered into a registered agreement of sale with the first defendant, in which the re-survey number and extent were described as 110/3 and 2240 sq. ft. respectively. On the same date, the earlier agreement of sale dated 19.11.2001 executed by the first defendant in favour of one S. Ravi was cancelled.

4. According to the plaintiff, the total sale consideration was fixed at Rs.5,30,000/-, of which a sum of Rs.2,00,000/- was paid as advance. The agreement stipulated a period of three months from the date of execution for completion of the sale on payment of the balance consideration. It further provided that, in the event of failure on the part of the defendant to execute the sale deed after receipt of the balance amount, the plaintiff would be entitled to deposit the balance sale consideration before Court and secure execution of the sale deed through Court under the provisions of the Specific Relief Act . Significantly, the agreement contains no recital stipulating the consequence or course open to the first defendant in the event of the plaintiff’s failure to complete the sale by payment of the balance sale consideration.

5. The plaintiff asserts that the defendant failed to hand over the original title deeds as agreed and that the documents were delivered only in June 2006, after considerable delay. On examining the documents, the plaintiff claims to have discovered that the re-survey number mentioned in the agreement as 110/3 was incorrect and that the correct re-survey number was 110/10B/1B. Thereafter, from January 2007 onwards, the plaintiff requested the defendant to rectify the said defect. Although the defendant allegedly promised to do so, he neither rectified the error nor came forward to execute the sale deed upon receipt of the balance sale consideration. Consequently, the plaintiff issued a legal notice dated 10.07.2007 calling upon the defendant to rectify the re-survey number and execute the sale deed. In reply, according to the plaintiff, false allegations were made. The plaintiff claims that he was at all times ready and willing to perform his part of the contract and that, owing to the defendant’s failure to comply, the suit came to be instituted.

6. Brief facts of the defendants’ case: The defendants contend that from the date of the agreement the plaintiff never evinced any intention to complete the sale by paying the balance sale consideration and, consequently, forfeited not only his right to seek specific performance but also the advance amount. They assert that the re-survey number mentioned in the agreement is correct and is duly reflected in the encumbrance certificate, and that the plea of an incorrect survey number was raised only to create confusion. According to the defendants, the plaintiff has miserably failed to perform his part of the contract and is therefore not entitled to the equitable relief of specific performance.

7. The trial Court, upon consideration of the issues and evidence, declined the r

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top