IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. ANAND VENKATESH, J.
M/s. China Datang Technologies and Engineering Company Limited – Appellant
Versus
M/s. NLC India Limited – Respondent
Arb.O.P.(Com.Div.) Nos.141 & 333 of 2023
Decided On : 28-11-2025
| Table of Content |
|---|
| 1. parties involved in arbitration. (Para 1 , 2 , 4) |
| 2. jurisdiction issues and consent. (Para 5 , 9) |
| 3. court's appointment of arbitrator. (Para 6 , 12 , 13 , 14) |
| 4. effects of inherent lack of jurisdiction. (Para 22 , 27 , 28 , 37) |
| 5. setting aside of the arbitral award. (Para 52 , 53) |
ORDER :
Arb.O.P.(Com.Div.) No.141 of 2023 is a petition filed under Section 34 (2)(b)(iii) of the Arbitration and Conciliation Act, 1996 (for brevity, the Act) by one M/s.China Datang Technologies and Engineering Company Limited seeking to set aside an arbitral award dated 09.11.2022 and for a direction to M/s.NLC India Limited to restore the contract performance guarantee amounting to Rs.55.65 Crores encashed on 11.11.2022.
2. Arb.O.P.(Com.Div.) No.333 of 2023 is a petition filed under Section 34 (2) of the Act by the said M/s.NLC India Limited questioning the same award in so far as awarding claims IV and V in favour of the said M/s.China Datang Technologies and Engineering Company Limited and rejection of the counter claim made by said M/s.NLC India Limited were concerned.
3. For the sake of convenience, the parties will be referred to as per their respective rank before the Arbitral Tribunal.
4. The brief facts leading to filing of the above petitions are as follows:
(i) The respondent was required to develop a lignite based thermal power station called Neyveli New Thermal Power Project consisting of two units having the capacity of 500 MW each at Neyveli. The respondent issued a tender dated 19.12.2018 and invited bids for installation of the flue gas de-sulphurisation system. The claimant also submitted its bid on 27.5.2019.
(ii) The respondent issued a letter of award dated 31.8.2019 to the claimant for the works as described in the scope of work for an amount of Rs.556,50,00,000/-. The effective date of the contract was 31.8.2019. The periods stipulated for completion of trial operation and whole of the works for the first unit of 500 MW were 27 months and 30 months respectively from the date of the letter of award. With respect to the second unit of 500 MW, the periods stipulated for completion of trial operation and whole of the works were 33 months and 36 months respectively from the date of the letter of award.
(iii) There were delays in the execution of the works and ultimately, the respondent issued a show cause notice dated 07.7.2020 to the claimant granting 30 days time to them to take appropriate measures to the satisfaction of the respondent, failing which, it was made clear that the contract would be terminated in terms of Clauses 10.30(i) and 10.25 of the contract.
(iv) On receipt of the said show cause notice, a reply was given by the claimant explaining as to why they were not able to mobilise their resources owing to spread of novel corona virus in China and thereafter in India and the subsequent lock downs imposed by the Government of India. The claimant also pointed out certain delays, which were attributable to the respondent. The claimant was also corresponding with the respondent regularly and had commenced the procurement activities and kept the respondent updated.
(v) The claimant, through e-mail dated 25.7.2020, intimated the respondent that they had planned to commence the construction of their site office by 29.7.2020 and requested for gate passes from the respondent. But, the respondent was not convinced with various steps that were taken by the claimant. Further, the respondent issued a letter dated 07.9.2020 terminating the contract. The respondent also invoked the contract performance guarantee and encashed the amount deposited towards it.
(vi) Pursuant to that, the claimant filed O.A.No.493 of 2020 before this Court under Section 9 of the Act seeking to stay the invocation of the contract performance guarantee. The said original application was disposed of by a learned Single Judge of this Court on 12.10.2020. For proper appreciation, the relevant portions in the said order dated 12.10.2020 are extracted
Amway India Enterprises (P) Ltd. Vs. Ravindranath Rao Sindhia
The High Court lacks jurisdiction to appoint an arbitrator in international commercial arbitration, as such powers lie exclusively with the Supreme Court, making any award from improperly appointed t....
An arbitrator's appointment by consent recorded in court meets legal requirements, and jurisdictional challenges based on alleged lack of procedure cannot invalidate prior agreements.
The main legal point established in the judgment is that objections to jurisdiction must be raised at the appropriate stage, and the findings of the arbitrator on the point of jurisdiction, if not ch....
The appointment of a sole arbitrator deviated from the statutory requirements and terms of the arbitration agreement, making proceedings invalid under the Arbitration and Conciliation Act, 1996.
Jurisdictional objections to arbitration awards must be raised during proceedings, not at execution; failure to do so leads to unenforceable awards.
Participation in arbitration without objection constitutes a waiver of the right to challenge the appointment of the arbitrator, as per Sections 4 and 12 of the Arbitration and Conciliation Act.
Point of law: As per the legal position settled by the Supreme Court in catena of judgments, the High Court has the jurisdiction under Section 11(6) of the said Act to nullify the appointments made b....
The court emphasized the necessity for impartiality in arbitration, ruling that automatic appointments of arbitrators undermined the arbitration clause, rendering the award invalid.
The High Court's appointment of an arbitrator under Section 11(6) does not grant it jurisdiction over objections to the arbitral award under Section 34; objections must be heard in the proper princip....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.