SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Mad) 5601

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. ANAND VENKATESH, J.
M/s. China Datang Technologies and Engineering Company Limited – Appellant 
Versus
M/s. NLC India Limited – Respondent
Arb.O.P.(Com.Div.) Nos.141 & 333 of 2023
Decided On : 28-11-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr.S.Ravi, Mr.K.P.Pramodh Kumar, Ms.Jayshri Durga
For the Respondent: Mr.AR.L.Sundaresan, Mr.N.Nithianandam

The High Court lacks jurisdiction to appoint an arbitrator in international commercial arbitration, as such powers lie exclusively with the Supreme Court, making any award from improperly appointed tribunals nullities.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34, 11(2), 11(6), 2(1)(f) - International Commercial Arbitration - Petitions to set aside the award dated 09.11.2022 - High Court lacks jurisdiction to appoint arbitrator in international arbitration; power resides exclusively with the Supreme Court - Award rendered by a tribunal appointed without jurisdiction declared a nullity. (Paras 1-52)

(B) Jurisdiction - Appointment of Arbitrator - Consent of parties cannot confer jurisdiction where it does not exist - Inherent lack of jurisdiction cannot be cured by waiver or consent of parties. (Paras 19-41)

(C) Interim Relief - Manifest intention to arbitrate - Protection of contract performance guarantee pending arbitration sought - Interim orders are continued till final resolution by arbitrator. (Paras 9-10)

Facts of the case:
The disputes relate to the appointment of an arbitrator under a contract concerning the Neyveli New Thermal Power Project. The claimant, a company incorporated in China, sought to set aside an arbitral award made in its favor regarding claims IV and V, while the respondent challenged the award concerning its counterclaims and encashment of a performance guarantee.

Findings of Court:
The Court concluded that the High Court did not have the jurisdiction to appoint an arbitrator in an international arbitration context, rendering the award a nullity.

Issues: Whether the High Court could appoint an arbitrator in an international commercial arbitration and the implications of such an appointment.

Ratio Decidendi: The Court ruled that the appointment of an arbitrator in international commercial arbitration must be made by the Supreme Court, and any appointment made by the High Court without jurisdiction results in a voidable award.

Result: Petitions allowed; the impugned arbitral award is set aside in its entirety.

Table of Content
1. parties involved in arbitration. (Para 1 , 2 , 4)
2. jurisdiction issues and consent. (Para 5 , 9)
3. court's appointment of arbitrator. (Para 6 , 12 , 13 , 14)
4. effects of inherent lack of jurisdiction. (Para 22 , 27 , 28 , 37)
5. setting aside of the arbitral award. (Para 52 , 53)

ORDER :

Arb.O.P.(Com.Div.) No.141 of 2023 is a petition filed under Section 34 (2)(b)(iii) of the Arbitration and Conciliation Act, 1996 (for brevity, the Act) by one M/s.China Datang Technologies and Engineering Company Limited seeking to set aside an arbitral award dated 09.11.2022 and for a direction to M/s.NLC India Limited to restore the contract performance guarantee amounting to Rs.55.65 Crores encashed on 11.11.2022.

2. Arb.O.P.(Com.Div.) No.333 of 2023 is a petition filed under Section 34 (2) of the Act by the said M/s.NLC India Limited questioning the same award in so far as awarding claims IV and V in favour of the said M/s.China Datang Technologies and Engineering Company Limited and rejection of the counter claim made by said M/s.NLC India Limited were concerned.

3. For the sake of convenience, the parties will be referred to as per their respective rank before the Arbitral Tribunal.

4. The brief facts leading to filing of the above petitions are as follows:

(i) The respondent was required to develop a lignite based thermal power station called Neyveli New Thermal Power Project consisting of two units having the capacity of 500 MW each at Neyveli. The respondent issued a tender dated 19.12.2018 and invited bids for installation of the flue gas de-sulphurisation system. The claimant also submitted its bid on 27.5.2019.

(ii) The respondent issued a letter of award dated 31.8.2019 to the claimant for the works as described in the scope of work for an amount of Rs.556,50,00,000/-. The effective date of the contract was 31.8.2019. The periods stipulated for completion of trial operation and whole of the works for the first unit of 500 MW were 27 months and 30 months respectively from the date of the letter of award. With respect to the second unit of 500 MW, the periods stipulated for completion of trial operation and whole of the works were 33 months and 36 months respectively from the date of the letter of award.

(iii) There were delays in the execution of the works and ultimately, the respondent issued a show cause notice dated 07.7.2020 to the claimant granting 30 days time to them to take appropriate measures to the satisfaction of the respondent, failing which, it was made clear that the contract would be terminated in terms of Clauses 10.30(i) and 10.25 of the contract.

(iv) On receipt of the said show cause notice, a reply was given by the claimant explaining as to why they were not able to mobilise their resources owing to spread of novel corona virus in China and thereafter in India and the subsequent lock downs imposed by the Government of India. The claimant also pointed out certain delays, which were attributable to the respondent. The claimant was also corresponding with the respondent regularly and had commenced the procurement activities and kept the respondent updated.

(v) The claimant, through e-mail dated 25.7.2020, intimated the respondent that they had planned to commence the construction of their site office by 29.7.2020 and requested for gate passes from the respondent. But, the respondent was not convinced with various steps that were taken by the claimant. Further, the respondent issued a letter dated 07.9.2020 terminating the contract. The respondent also invoked the contract performance guarantee and encashed the amount deposited towards it.

(vi) Pursuant to that, the claimant filed O.A.No.493 of 2020 before this Court under Section 9 of the Act seeking to stay the invocation of the contract performance guarantee. The said original application was disposed of by a learned Single Judge of this Court on 12.10.2020. For proper appreciation, the relevant portions in the said order dated 12.10.2020 are extracted

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top