IN THE HIGH COURT OF JUDICATURE AT MADRAS
P.T. Asha, J.
M. Selvaraj, S/o. Marappagounder - Petitioner
Versus
The State Represented By., Principles Secretary to Government, Department of Energy – Respondent
WP No. 2438 of 2026 and WMP Nos.2685 and 2687 of 2026
Decided On : 24-02-2026
| Table of Content |
|---|
| 1. petitioners' claims of land ownership and hardship due to tower erection. (Para 1 , 2) |
| 2. court's legal analysis on statutory authority and rights. (Para 4 , 5 , 6 , 7 , 8) |
| 3. legal interpretations of the electricity act and telegraph act. (Para 9 , 10 , 11 , 12) |
| 4. petition dismissed; petitioners can seek compensation. (Para 13) |
ORDER :
P.T. Asha, J.
The above writ petition is filed for a mandamus directing the second respondent to consider the petitioners’ objections dated 18.09.2025 and consequently to forbear the respondents 1 to 4 from erecting High Tension Electricity Tower in the petitioners’ agricultural land situated in Survey Field No.573, in patta No.1198, Emmampatti Village, Nambiyur Taluk, Erode District.
2.The petitioners would submit that the lands in question are their ancestral properties and the petitioners who are brothers are joint owners of the said land and they have been cultivating crops thereon and they have been in continuous possession of the same. Their livelihood is dependant on these lands. In the year 1981, two high tension electric towers were erected in their lands by the respondents’ board for carrying 250 KW of power and the cable is passing right in the middle of the land from East to West. This has caused excess hardship to the petitioner for cultivating crops and in carrying out their agricultural activities and since the overhead lines are running through their land, their agricultural activities are restricted.
2.1.While so, without any prior notice, the respondents board officials unauthorisedly entered their lands and started measuring it and when questions were raised, they were informed that such measurements were part of the process of constructing a new 110 KW high tension electricity tower and line once again through their property. The petitioners would submit that the construction of these towers would ring a death knell to their agricultural operations and they would be forced to stop their agricultural activities and if their agricultural activities are stopped, they would be declared as defaulters as they have taken loans from banks to carry on their agricultural operations.
2.2.The petitioners would submit that to add to their hardship, two acres had been acquired by the Government for the purpose of establishing Athikadavu-Avinashi Water Supply Project and it was only the remaining lands that is in the enjoyment of the petitioners. The petitioners would further submit that as per the original plan, the tower was not intended to pass through their land, but only through the government lands that is adjacent to their property and it is well open to the respondent to stick to the original plan. Further, the respondents board had not followed due process by issuing proper notice prior to approving or commencing the project. If they had issued notice, the petitioner would have submitted their objections. Therefore, the action of the respondents board is arbitrary.
2.3.The petitioners had therefore, made an objection by way of representation dated 13.08.2025 to the second respondent. Till date, there is no response for the same and the respondents are continuing with their work to erect the high tension towers as per the schedule. This prompted the petitioners to sent yet another objection on 18.09.2025 to the fourth respondent. Despite receiving the objections / representation, the fourth respondent did not respond to the same. Therefore, the petitioner is constrained to approach this Court. 3.The fourth respondent has filed a counter affidavit inter alia contending that the Government of Tamil Nadu had permitted the fourth respondent as per Section 68 and 164 of the Electricity Act, 2003, for executing 11 schemes throughout the State and one of the schemes is the erection of 110 KV DC line on DC tower for making LILO of the existing Karuvallur – Nambiyur feeder at Malayampalayam 110/33-11 kV Substation. They would contend that they are the deemed transmission lincensee
Power Grid Corporation of India Limited Vs. Century Textiles and Industries Limited and others
Statutory authorities can erect high-tension electricity towers on private land without prior consent, provided they ensure minimal damage and compensate affected parties, in adherence to public inte....
When the element of expertise is involved and the same is undertaken by the statutory body as per law, the power of judicial review will have to be entertained with extreme caution. Judicial Review -....
The authority of the respondent to shift transmission towers under the Electricity Act and the entitlement of aggrieved parties to compensation under the Indian Telegraph Act.
The court affirmed the legality of the procedures for erecting transmission towers and highlighted public interest in electricity provision over private landowner objections.
No prior notice required for erecting transmission lines under Electricity Act; compensation is the only remedy for property owners.
The court upheld the validity of the District Magistrate's order permitting the laying of a transmission line, affirming that adequate notice and opportunity were provided to affected farmers, thus a....
Section 164 of Electricity Act, 2003, no land owner or person interested can seek for shifting or realigning of the route, on the premise that the District Collector-cum-District Magistrate, has powe....
The court upheld the authority of the licensee to lay transmission lines under public interest, dismissing the petitioner's objections as untimely and unfounded.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.