IN THE HIGH COURT OF ORISSA AT CUTTACK
K.R.MOHAPATRA, SANJAY KUMAR MISHRA, JJ.
M/s Sterlite Iron & Steel Company and Another - Petitioners
Versus
State of Odisha and others - Opp. Parties
W.P.(C) No. 15495 of 2015
Decided On : 09-02-2026
| Table of Content |
|---|
| 1. land acquisition and refund procedures (Para 2 , 3 , 4) |
| 2. arguments against refund claim (Para 5 , 6) |
| 3. withdrawal request impacts entitlement (Para 7 , 8) |
| 4. petitioner initiated withdrawal process (Para 9 , 10 , 11) |
| 5. dismissal of the writ petition (Para 12) |
JUDGMENT :
1. This matter is taken up through hybrid mode.
2. Petitioner, in this Writ Petition, prays for a direction to set aside the letter No.14493 dated 2nd August, 2012 (Annexure-11) issued by the Land Officer, Odisha Infrastructure Development Corporation (for brevity, ‘IDCO’), Bhubaneswar forfeiting the amount deposited by the Petitioner towards administrative charges and land acquisition establishment contingencies as per the decision taken in the 66th meeting dated 4th October, 2005 (Annexure-12) of the Board of Directors and the Circular No.32463/R dated 14th June, 1999 (Annexure-13) of the Government of Odisha issued by the Department of Revenue and Disaster Management.
3. Mr. Mohanty, learned Senior Advocate for the Petitioner submits that on 15th October, 2004, a Memorandum of Understanding (MoU) was signed between the Petitioner and the State Government to set up a 5 million tons per annum (MTPA) steel plant in Odisha. Accordingly, on the requisition of IDCO land acquisition proceeding was initiated covering nine villages of Keonjhar district identified for establishment of steel plant proposed by the Petitioner and IDCO directed the Petitioner, vide its letter No.1182 dated 20th January, 2007 (Annexure-4) to deposit certain amount on different heads. Since the project proponent-the Petitioner had already deposited Rs.8.00 crores with IDCO, it was required to deposit the balance amount of Rs.6,81,49,857/- with IDCO. Accordingly, the project proponent, namely, the Petitioner deposited the same with IDCO. For acquisition of land, Gram Sabha was held, but ultimately, due to stiff opposition of the local inhabitants, the possession of the acquired land could not be delivered to the project proponent. However, by then, the award in the land acquisition proceeding had already been passed. As it was not possible on the part of IDCO to deliver possession of the required land, the Petitioner, vide its letter dated 6th June, 2012 (Annexure-9) requested as under:-
“In view of the above, we request you to take appropriate steps, to withdraw land acquisition proceeding in respect of entire project site under Section 48 of Land Acquisition Act 1.894. We also request IDCO to allocate a minimum of 800 to 1000 acres of land, in the form of alternate, site, from an industrial area for 1.5 MTPA steel plant, for going ahead with the implementation of the project in a phase-wise manner, the capacity of which could be expanded to 5 MTPA steel plant at the later date.”
(emphasis supplied)
Thus, the request of the Petitioner was processed and ultimately vide impugned letter under Annexure-11, the proposal submitted by the Petitioner was accepted by IDCO subject to forfeiture of administrative charges and land acquisition establishment contingencies as per the decision taken in the 66th meeting of the Board of Directors (Annexure-12) and Circular of the Revenue and Disaster Management Department (Annexure-13) referred to above supra.
4. Mr. Mohanty, learned Senior Advocate drew attention of this Court to the Circular of Revenue and Excise Department No. 32463 dated 14th June, 1999 (Annexure-13), relevant portion of which is reproduced hereunder.
“It is sometimes observed that the requisitioning authorities file application for withdrawal of the land acquisition proceedings and consequently claim refund of the sum deposited by them towards establishment cost, law charges and printing charges etc. In such cases, no clear-cut policy guidelines had been, hitherto, enunciated by the State Govt. for deciding upon the entitlement of the requisitioning authorities for refund. In this connection, a draft policy was circulated by the Revenue & Excise Department vide letter No. 2788

The forfeiture of administrative charges due to withdrawal of land acquisition is valid when initiated by the project proponent as per established policy guidelines.
The court clarified that a party cannot be treated as abandoning a project due to delays in acquiring land by the authority responsible, highlighting the entitlement to a refund under specific circum....
Approval conditions for land acquisition must be met to establish vested rights; public interest considerations prevail in land allocation disputes.
The main legal point established in the judgment is that for the acquisition proceedings to lapse under Section 24(2) of Act of 2013, both the contingencies of non-possession and non-payment of compe....
The court established that adherence to procedural fairness and the right to a hearing are fundamental in land acquisition processes under the Land Acquisition Act, 1894.
Point of law: Absence of an award in terms of the provisions of the Act, the reference as made to the L.A.R.R. Authority as was done by the District Level Negotiations Committee would have no legal e....
Lapse of land acquisition proceeding – Drawing of Panchanama of taking possession is mode of taking possession in land acquisition cases – Land vests in Government and any re-entry is unlawful.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.