IN THE HIGH COURT OF ORISSA AT CUTTACK
BISWANATH RATH, J.
Biswanath Agrawala - Petitioner
Versus
State of Odisha and others - Opposite Party
W.P.(C) No.27400 OF 2022
Decided On : 20-10-2022

Advocates:
Advocate Appeared:
For the Appellant : Mr.A.Pal,Adv.
For the Respondent: Mr. S.Ghose, AGA Mr.D.Mohapatra,Adv.

The court determined that there should be interim protection for parties appealing against orders under Section 91, highlighting the need for legislative amendment to facilitate effective appeal processes.

Headnote:(A) Odisha Development Authorities Act, 1982 - Section 91(2) - Interim protection under appeal - Petitioner sought interim protection against demolition during the pendency of an appeal. Court observed that Section 91(2) provides no provision for interim protection; however, execution of orders under Section 91(1) may prejudice appeal rights. Court highlighted the need for legislative amendment to incorporate such interim provisions. (Paras 3, 6, 7, 8)

(B) Appeals - Mechanism - The Court emphasized that in the absence of an interim mechanism, executing authorities should await the final outcome of appeals, ensuring remedies are effective. Court urged timely adjudication of appeals to prevent prejudice to aggrieved parties. (Paras 8, 9)

Facts of the case:
The Writ Petition was filed by an individual against the Development Authority concerning a demolition order and sought interim relief until the appeal was resolved.

Findings of Court:
The Court noted there is currently no provision for interim protection under the Act and suggested amending the Act to prevent wrongful execution of orders during appeals.

Issues: The main issue was whether interim protection should be granted during the pendency of an appeal against an order of the Development Authority.

Ratio Decidendi: The Court ruled that pending statutory appeal should dictate staying the order of the lower authority to preserve effective remedies, pending a legislative amendment to address interim provisions.

Result: Writ Petition disposed of with directives.

Table of Content
1. petitioner fears demolition during appeal. (Para 2)
2. arguments on interim protection under section 91. (Para 3 , 4 , 5)
3. court's observations on appeal and interim protection. (Para 6 , 7 , 8 , 9)
4. disposal of the writ petition. (Para 10 , 11)

ORDER :

1. Heard learned counsel fo r the Parties.

2. The Writ Petition is filed on an apprehension against the Development Authority in working out their own order in UAP Case No.261 of 2015 by effecting demolition of alleged structure of the Petitioner, if any, during pendency of Appeal.

3. Mr.Pal, learned counsel for the Petitioner taking this Court to the provision at Section 91 (2) of the Odisha Development Authorities Act, 1982, reading through the allegation herein made an attempt to satisfy the court that for the restricted provision under (2) of the Act, there is even no scope for grant of interim protection by the competent authority exercising appellate power.

4. It is in the circumstance, Mr.Pal, learned counsel for the Petitioner submitted the Petitioner has no other remedy than to approach the High Court for interim protection at least till disposal of the Appeal.

5. Mr.Mohapatra, learned counsel appearing for Development Authority while not disputing the contentions raised by Mr.Pal, learned counsel for the Petitioner involving Section 91 (2) of the Act that there is no scope with the appellate authority but for the limited provision therein to enter into interim aspects involved therein, it is in the circumstance, Mr. Mohapatra, learned counsel for the Development Authority contended for there is absence of an interim protection provision, no fault can be found with the Development Authority in undertaking such exercise, in the circumstance entertaining the Writ Petition is challenged. There is however no dispute in the Bar that pendency of a statutory Appeal should create a restrain in implementing the lower authorities order. Learned State Counsel also supports the contentions raised by Mr.Mohapatra, learned counsel for the Development Authority.

6. Considering the rival contentions of the Parties, this Court finds question required here to be decided as to even assuming there is no contingency for interim protection under the provision of Section 91 (2) of the Act, in the event an Appeal is preferred involving the order under (1) of the Act should the executing authority await till final outcome in the proceeding already initiated under (2) of the Act?

7. Considering the rival contentions of the Parties, this Court finds, undisputedly there has been disposal of a 91(1) proceeding in the outcome of a proceeding under UAP Case No.261 of 2015. Further undisputed facts remain Petitioner has already preferred an Appeal which is even registered as Appeal Case No.24 of 2022 and for the submission of both sides, there is already commencement of Appeal proceeding. It is at this stage looking to the question framed, this Court takes into account the provision at Section 91 of the Odisha Development Authorities Act. 91(1) of the Act which prescribes disposal of complaint by the competent authority and through (2) provides Appeal mechanism. Therefore, this Court finds, undisputedly the parties are involved in Appeal mechanism under the provision of (2) as against the orders, 91(1) of the Act and the provision at (2) of the Act reads as follows : -

(2) Any person aggrieved by an order under Sub-Section (1) may appeal to the State Government or an Officer appointed by the State Government in this behalf, against that order within thirty days from the date thereof, and the Government or the Officer, as the case may be, may after hearing the parties to the appeal either allow or dismiss the appeal or may reverse or vary any part of the order. The decision of the State Government or the Officer shall be final and shall not be questioned in any Court of law.”

Entire reading the provision of Section 91 (2), this Court finds, undisputedly there is no mechanis