2005 Supreme(P&H) 1136

PUNJAB & HARYANA HIGH COURT
D.K.Jain and Hemant Gupta JJ.
Sharma And Associates
Versus
State Of Punjab
Civil Writ Petition No. 15857 of 2005,
Decided On : OCTOBER 28, 2005

Headnote

Arbitration - Dispute over Final Bill - Clause 41 of the Agreement - [Sutlej Yamuna Link Project Punjab] - [Clause 41 of the Agreement] - The court discussed the provisions of Clause 41 of the Agreement, which outlined the process for payment and certification of work done by the contractor. It emphasized that the final bill was to be submitted by the contractor within one month of the completion of the project, and the certificate of measurement of the Executive Engineer would be final and binding if the final bill was not submitted. The court concluded that the dispute raised by the petitioner regarding the non-preparation of the final bill after 15 years of completing the project was beyond the period of limitation, and the termination of proceedings by the Arbitrator was not suffering from any patent illegality or material irregularity warranting interference in the exercise of the powers of judicial review.

Fact of the Case:

The petitioner completed a contract agreement for the Sutlej Yamuna Link Project Punjab in 1988 and raised various claims against the respondent State. The dispute was referred to an Arbitrator, and the petitioner later sought adjudication of the dispute arising from the non-preparation of the final bill after 15 years of completing the work.

Finding of the Court:

The court found that the dispute raised by the petitioner regarding the non-preparation of the final bill after 15 years of completing the project was beyond the period of limitation. It concluded that the termination of proceedings by the Arbitrator was not suffering from any patent illegality or material irregularity warranting interference in the exercise of the powers of judicial review.

Issues: The main issue was whether the petitioner could raise a dispute of non-preparation of the final bill after 15 years of completing the work.

Ratio Decidendi: The court applied the provisions of Clause 41 of the Agreement, which outlined the process for payment and certification of work done by the contractor. It emphasized that the final bill was to be submitted by the contractor within one month of the completion of the project, and the certificate of measurement of the Executive Engineer would be final and binding if the final bill was not submitted. The court concluded that the dispute raised by the petitioner regarding the non-preparation of the final bill after 15 years of completing the project was beyond the period of limitation.

Final Decision: The court dismissed the writ petition in limine, finding no merit in the petitioner's claim regarding the non-preparation of the final bill after 15 years of completing the project.

Judgment

Hemant Gupta, J.

1. The present writ petition is directed against communication dated 10.5.2005 whereby, Superintending Engineer, Upper Bri Doab Canal Division, Amritsar has closed an arbitration case as sought by the petitioner.

2. On March 15, 1985 a contract agreement was signed between the petitioner and the respondent State for the work of Sutlej Yamuna Link Project Punjab (earth work, drainage behind lining and cement concrete lining) Reach RD 78.0 KMS to 78.5 KMS and similar adjoining works. The said work was completed by the petitioner somewhere in the year 1988. The petitioner raised a claim for extra items and loss to Executive Engineer etc. for payment on 11.3.1988. Since the dispute arose between the parties, the matter was referred to an Arbitrator at the instance of the petitioner. The award given by the Arbitrator was published on 12.6.1995. The proceedings to make the award as "Rule of the Court" is pending before this Court in Civil Revision No. 757 of 2002 filed by the State. In the claim petition in the year 1992 giving rise to said award, as Annexure P. 17, the petitioner has raised dispute inter-alia regarding delay in handing over exclusive clear reach uninterrupted and unimpeded, delay in handing over the exclusive site, delay in supply of basic data. The petitioner has also made grievance of non-supply of electric power, delay in making running payments as well as non issuance of cement and other materials for preliminary and enabling works. The petitioner has also made grievance of delay in payment of mobilisation and other advances, non provision of open drain for dewatering of water on one side of Canal, non providing complete instructions for execution of work etc. raising claim of 42 items in a claim petition running into 59 pages.

3. The petitioner on 27.11.2003 for the first time agitated its claim for the release of the final bill as it was the case of the petitioner that the respondents have failed to prepare the final bill. It is the case of the petitioner that he made a reference to the Executive Engineer in terms of the contract agreement. Since the Executive Engineer failed to convey any decision on the representation, the petitioner appealed to the Superintending Engineer, Construction Division, Sutlej Yamuna Link Canal Project (Punjab). Thereafter, the petitioner invoked the arbitration as per the contract agreement. Since the security and the payment of the final bill was not being released, the petitioner filed a Writ Petition No. 19962 of 2003 before this Court for issuance of writ of mandamus directing the respondents to prepare the ultimate final bill. On 18.12.2003, this Court directed the respondents to take final decision on the representation. The respondents denied the claim of the petitioner on 12.2.2004 while declining the representation of the petitioner.

4. The petitioner, thereafter, sought appointment of arbitrator in terms of Clause 63 of the Contract Agreement on 17.3.2004. In the said communication addressed to Chief Engineer, Construction Division, Sutlej Yamuna Link Canal Project (Punjab), the petitioner sought list of 3 officers of the rank of Superintending Engineer or higher so that the petitioner is able to select one of the officers to act as sole arbitrator. In response to the said letter, the Chief Engineer on 7.4.2004 communicated that the Arbitrator has already announced the award and has decided all the claims and that there exist no other dispute. The petitioner was also informed that in terms of the orders of the High Court, the representation of the petitioner was considered and rejected on 12.2.2004, thus, the Arbitrator cannot be appointed under Clause 63 of the Contract Agreement and the petitioner has no right to seek appointment, of the arbitrator. But on 27.4.2004, the petitioner sought selection of one of the officers out of 3 names communicated by the petitioner. The Chief Engineer, in response to the said letter on 6.5.2004 informed the p























1
2
3
4
5
6
7
8
9
10
11