IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Arun Monga, J.
Haryana Urban Development Authority(Now Haryana Shahri Vikas Pradhikaran – HSVP) – Appellant
Versus
Raj Nakra & Anr. – Respondents
CR No. 959 of 2023
Decided On : 21-02-2023
| Table of Content |
|---|
| 1. factual background of case proceedings. (Para 2 , 3) |
| 2. the main controversy revolves around interests on delayed payments. (Para 4 , 5) |
| 3. interpretation of terms related to interest payment in allotment letter. (Para 6 , 7 , 8) |
| 4. court's reasoning on legality of interest claims. (Para 9 , 10 , 11) |
| 5. court's final order regarding payments and possession. (Para 12 , 13 , 14 , 15) |
Judgment
Mr. Arun Monga, J. (Oral):- Vide this common order and judgment, above-mentioned two revision petitions are being disposed of, since the issues and facts raised therein are common. For brevity, recitals are taken from CR-959-2023.
2. Revision petition arises out of pending execution proceedings before the learned Additional Civil Judge (Senior Division), Panchkula. Impugned herein is an order dated 15.10.2022 (Annexure P-6), whereby, respondent-decree-holders have been directed to pay Rs.1,28,278/- and petitioner-judgment debtor has been directed to hand over possession of SCO-116, Sector 5, Panchkula, within 7 days.
3. Succinct factual background first, as pleaded in the petition.
3.1. Respondents purchased a commercial plot No.116, Sector 5, Panchkula in an open auction and allotment letter dated 20.04.1989 was issued. However, respondents failed to adhere to the schedule of payment as per allotment letter. Thereafter, site in question was resumed by petitioner vide order dated 30.12.1998. Respondents challenged said resumption order in an appeal before learned Administrator, HUDA, Panchkula. Resumption was set aside vide appellate order dated 26.09.2001. It was ordered that development works should be taken as completed in August-2000 for all intents and purposes and calculation etc. be made accordingly. Aggrieved, respondents filed a revision before learned Financial Commissioner, which was dismissed and respondents were directed to make payment of dues within 30 days from the date of demand, failing which resumption proceedings would revive. Petitioner issued another notice dated 04.09.2002 to respondents. Against said notice, respondents preferred CWP-19098-2002, which was disposed of vide order dated 01.12.2003. Department filed SLP-4517-2004, which was disposed of vide order dated 09.07.2007 modifying order dated 01.12.2003 to the extent that respondents are liable to pay compound interest @ 10% per annum.
3.2 Respondents subsequently filed a civil suit seeking declaration against the petitioner not to recover penalty and challenged the demand raised by the Department, inter alia, on the ground that same is not as per Apex Court order dated 09.07.2007 ibid. Said suit was disposed of vide order dated 08.10.2007 (Annexure P1) holding that “the plaintiff is ordered to make payment from the date of order of possession i.e., August 2000 with interest as per the order of Hon’ble Supreme Court i.e., 10% compound interest along with penalty as per the rules and regulations of the HUDA Act.”
3.3. Both plaintiffs and Department preferred cross appeals before learned Additional District Judge, Panchkula which were dismissed vide judgment/decree dated 24.09.2009 (Annexure P-2) upholding notices dated 04.09.2002 and 09.10.2002 in which demand was raised by the Department. Said judgment/ decree has attained finality having been not challenged further. Instead of depositing the amount calculated by the Department, respondents filed an application for execution of judgment/ decree dated 24.09.2009 (Annexure P-2) before learned Executing Court. Said execution was dismissed vide order dated 01.10.2015 (Annexure P-3) and objections of the Department were accepted. Aggrieved, respondents preferred an appeal before learned Additional District Judge, Panchkula which was allowed vide order dated 08.11.2017 (Annexure P-4) holding that learned Executing Court travelled beyond the decree passed by learned Civil Judge as well as learned Appellate Court and directing learned Executing Court to enforce judgment/ decree dated 08.10.2007 (Annexure P
Haryana Builders Ltd. Vs. Haryana Urban development Authority and Others
The cancellation of allotment was justified due to the petitioner's failure to comply with payment terms, emphasizing the importance of adhering to auction conditions and public interest.
The 'as is where is' clause in the brochure was deemed unconscionable and void under Section 23 of the Indian Contract Act, 1872. The allottee is entitled to interest for every month of delay in poss....
1. Interest will be calculated after the period of assured possession has elapsed – from when cause of action has arisen2. Arbitration is not a bar to consumer complaint
Non-payment of lease salami within stipulated time does not automatically cancel allotment; requires active governmental cancellation, establishing a directory interpretation of time limits.
The Jharkhand State Housing Board cannot charge compound interest on amounts already paid; only simple interest on outstanding amounts is permissible.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.