IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
VINOD S. BHARADWAJ, J.
Pankaj Nandwani - Appellant
Versus
Permanent Lok Adalat - Respondent
CWP No. 1637 of 2019
Decided On : 20-08-2024
Legal Services - Permanent Lok Adalat - Section 22C - The court interpreted Section 22C of the Legal Services Authorities Act, 1987, emphasizing the right of an allottee to choose between an alternative plot or a refund, ultimately ruling in favor of the refund due to non-delivery of possession.
Fact of the Case:
The petitioner booked a residential plot but faced delays and non-delivery of possession. After years of waiting and communication with the developer, the petitioner sought a refund, leading to a dispute resolved by the Permanent Lok Adalat.
Finding of the Court:
The court found that the developer's inability to deliver possession justified the petitioner's request for a refund, as the allottee cannot be compelled to accept an alternative plot.
Issues: Whether the allottee can be compelled to accept an alternative plot instead of seeking a refund for the non-delivery of the originally allotted plot.
Ratio Decidendi: An allottee cannot be forced to accept a counter offer for an alternative plot, as this would constitute a novation of the original contract, and the right to a refund is upheld when possession is not delivered.
Result: The award by the Permanent Lok Adalat is set aside, and the developer is directed to refund the entire deposited amount with interest.
JUDGMENT :
(Vinod S. Bhardwaj. J.) :
The present petition challenges the award dated 15.11.2018 (Annexure P-1) passed in case no.168 by the Permanent Lok Adalat (Public Utility Services), Sonipat, whereby the application under Section 22C of The Legal Services Authorities Act, 1987 (for short the 1987 Act) filed by the petitioner has been partly allowed and the respondent developer has been directed to allow the petitioner to choose a plot from the available plots, of same size and in the same location, at the initially agreed price instead of directing a refund of the entire deposited amount, along with interest.
2. Learned counsel for the petitioner contends that the petitioner had booked a residential plot at TDI City, Kundli, District Sonipat in the project developed by respondents no.2 and 3 in the name and style of Tuscan Royale, measuring 250 sq. yards bearing plot no.A-1 Block, Tuscan City in Tuscan Royale City at the basic sale price of Rs.37,500/- per sq. yard. Registration form was submitted by the petitioner on 14.05.2012 and a sum of Rs.18,75,000/- was duly deposited. A letter of allotment dated 05.02.2013 for plot no. A-1-104 was stated to have been issued to the petitioner but the same was actually never delivered to the petitioner. The same was actually collected by the petitioner only in November, 2013. While raising objections to the said letter of allotment, having been issued with terms and conditions at variance that what had been agreed to, the petitioner none-the-less deposited an additional amount of Rs.14,06,250/- on 05.12.2013 in compliance of the conditions of the letter of allotment. Learned counsel for the petitioner further contends that even though, as per the registration form, the letter of allotment was to be issued within a period of six months from the date of application, however, the above said ante dated letter of allotment was actually delivered to the petitioner only on 02.11.2013, i.e. much after the said period.
3. The petitioner waited for a further period of four years for the progress to be made and possession to be offered by the developer, however, no such development took place but a communication dated 20.06.2016 was sent to the petitioner, as per which the respondents expressed their inability to hand over possession of the plot to the petitioner and gave him the following options:-
Or
Adjustment of entire deposit in any of our other projects, in a unit of your choice.”
4. On receipt of the said letter, the petitioner inquired whether the respondents are in a position to offer possession of the plot of a choice of the petitioner or else, the amount deposited by him be refunded to him along with interest. No action was however initiated on the said request, whereupon an application under Section 22(C) of the 1987 Act was filed by the petitioner before the Permanent Lok Adalat.
5. In the reply filed before the Permanent Lok Adalat, the respondents admitted that they were unable to complete the development works as some miscreants had filed a suit and therefore they were unable to offer the possession to the petitioner. The relevant extract of the reply filed by the respondents reads as under:-
An allottee has the right to choose a refund over an alternative plot when possession is not delivered, reinforcing the principle of contractual freedom.
The principle of unjust enrichment and the doctrine of legitimate expectations were central to the court's decision, emphasizing the obligation of the Development Authority to act fairly and reasonab....
(1) Breach of reciprocal contractual obligations – A commercial document ought not to be interpreted in a manner that arrives at a complete variance with what may originally have been intention of pa....
Authorities must clarify payment structures and ensure timely refunds, as consumer rights are pivotal in contractual agreements.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.