SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(P&H) 2684

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
AVNEESH JHINGAN, J.
M/s. Chandi Contractors Pvt. Ltd. – Petitioner
Versus
Executive Engineer & Ors. – Respondents
CIVIL REVISION NO. 3877 of 2018
Decided On : 15-05-2023

Advocates Appeared:
Mr. Dheeraj Mahajan, Advocate; For the Petitioner
For the Respondent: Mr. Sharad Aggarwal, DAG, Haryana.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 31(7)(a) and (b) - Interest on arbitral award - The petitioner sought execution of the award, claiming interest on principal amount and on interest pendente lite, which was rejected. Court clarified that award of interest is inclusive of principal, allowing interest calculation accordingly. (Paras 2, 8, 10)

(B) Legal Position - Interest awarded till the passing of the award includes the principal amount for further interest calculation, establishing that the arbitral tribunal may grant interest on the sum inclusive of awarded interest. (Paras 8, 9)

Facts of the case:
The case involves a petition seeking execution of an arbitral award regarding a contract for construction, following termination of the project. The petitioner contested the lower court’s dismissal of the execution due to ambiguity in the award on interest.

Findings of Court:
The impugned order was set aside, and executing court to proceed with execution as per clarified interest provisions from initial ruling.

Issues: The key issue was whether interest under Section 31(7)(b) applies to both principal and awarded interest.

Ratio Decidendi: The court determined that interest awarded becomes part of the sum for future interest calculations under the Act, reaffirming the tribunal's authority to grant interest.

Result: Petition allowed.

JUDGMENT

Mr. Avneesh Jhingan, J. (Oral)

This revision petition is filed seeking setting aside of order dated 22.3.2018 dismissing the execution petition.

2. The relevant facts are that the parties on 10.10.1997 entered into an agreement for replacing of head regulator/bridge at RD No. 144895. As a result of dispute between the parties, the work allotted was terminated on 8.7.1998. The arbitration proceedings at the instance of the petitioner, culminated in award dated 5.12.2003. The award was clarified on 19.12.2003. The objections filed by the respondents were dismissed on 1.12.2006. The award was set aside in the review filed by the respondent. The petitioner succeeded in appeal under section 37 of the Arbitration and Conciliation Act, 1996 (for short, 'the Act') and the award was upheld.

Operative part of the order passed by this Court is reproduced below:

    "In view of the aforesaid discussions, this appeal is accepted. Impugned judgment is set aside and the review petition is dismissed. Since the Arbitrator had awarded interest @12% per annum, but had not made it clear as to up to which date it was awarded, therefore, necessity to clarify the ambiguity has arisen. Thus, while exercising the powers under section 31(7) of the Arbitration and Conciliation Act, 1996, it is ordered that the appellant would be entitled to interest @12% per annum up to the date of award and at the rate of 18% per annum from the date of award till realization of the award amount."

3. In the execution proceedings, the petitioner claimed interest @ 12% on principal amount of Rs.1,62,26,211/- quantified at Rs.1,02,70,736/-. The claim of interest on the interest pendente lite was rejected by observing that this Court had not ordered compounding of interest.

4. Learned counsel for the petitioner relies upon the decision of the Supreme Court in M/s Hyder Consulting (UK) Ltd. v. Governor, State of Orissa through Chief Engineer, 2015(2) SCC 189 and UHL Power Company Ltd. v. State of Himachal Pradesh , 2022(1) RCR (Civil) 677 to submit that the petitioner was entitled to interest on interest pendente lite.

5. Learned counsel for the respondents defends the impugned order.

6. It is undisputed fact that this court while allowing the appeal specifically awarded interest under Section 31 (7)(a) and (b) of the Act.

7. The only issue involved in the present petition is as to whether interest as per Section 31 (7)(b) of the Act is to be awarded on interest granted till the date of passing of the award or not?

8. The issue is no longer res integra. The Supreme Court in M/s Hyder Consulting (UK) Ltd.'s case (supra) held that the word 'sum' used in Section 31 (7)(a) of the Act does not restrict it to the principal amount. Rather the interest awarded under Section 31 (7)(a) of the Act will take the colour of 'sum' and there shall be no distinction between the principal amount and the interest awarded under Section 31 (7)(a) of the Act for the purpose of calculating interest under Section 31 (7)(b) of the Act. The relevant paragraphs are reproduced below:

    "In the result, I am of the view that S.L. Arora's case is wrongly decided in that it holds that a sum directed to be paid by an Arbitral Tribunal and the reference to the Award on the substantive claim does not refer to interest pendente lite awarded on the "sum directed to be paid upon Award" and that in the absence of any provision of interest upon interest in the contract, the Arbitral Tribunal does not have the power to award interest upon interest, or compound interest either for the pre-award period or for the post-award period. Parliament has the undoubted power to legislate on the subject and provide that the Arbitral Tribunal may award interest on the sum directed to be paid by the Award, meaning a sum inclusive of principal sum adjudged and the interest, and this has been done by Parliament in plain language.

    xx xx xx

    Therefore, for the purposes of an award, there is no distinction between a "sum" with i

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon telegram-icon
        whatsapp-icon Back to top