IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
VINOD S. BHARDWAJ, J.
Shashi Bhushan – Petitioner
Versus
State of Haryana & Ors. – Respondents
CWP-9884 of 2024
Decided On : 01-05-2024
JUDGEMENT
Vinod S. Bhardwaj, J. (Oral)
The instant petition has been instituted under Articles 226/227 of the Constitution of India, 1950 seeking issuance of a writ in the nature of Mandamus directing the respondents to release the payment of running bill of the petitioner alongwith 18% interest from the date of bills till actual realization.
2. Learned counsel for the petitioner contends that despite having completed the allotted work well within the prescribed time, the respondents have withheld the legitimate dues of the petitioner. He further submits that with regard to his grievance, the petitioner has submitted various request letters including the last one dated 31.05.2023 (Annexure P-7), however, the respondents have neither released the amount in question nor have they taken any action upon the said request letter. He further submits that the respondents are habitual of withholding the legitimate dues of the contractors without any cogent and valid reason, which unnecessarily forces the contractors to knock at the doors of this Court by filing repeated writ petitions. Some of such and similar writ petitions are as under:
3. It is further submitted that the respondents resort to withholding of the legitimate, admissible and payable dues of the contractors for the reasons best known to them. It is their modus oprendi to force the contractors into filing multiple cases adding to unnecessary litigation, wasting time of the Court and compelling the Contractor to incur expenses for litigation which was never required at first instance.
4. Notice of motion.
5. Mr. Vivek Saini, Addl. A.G., Haryana accepts notice on behalf of the respondents and prays for some time to complete instructions and file response, if necessary.
6. Learned counsel for the petitioner, however, submits that at this juncture, he would be satisfied if respondent No.5- Executive Engineer, Panchayati Raj, Public Works, Haryana, Mini Secretariat, Panchkula is directed to treat the present petition as a representation and to consider and decide the same in a time bound manner.
7. Learned State Counsel does not oppose the prayer made by learned counsel for the petitioner.
8. Accordingly, in view of the above; with the consent of the parties and without commenting on the merits of the case, the present petition is disposed of directing respondent No.5 to treat the present petition as a representation and to decide the same by passing a reasoned and speaking order after affording an opportunity of hearing to the respective parties within a period of three months of the receipt of certified copy of this order.
9. Needless to mention that upon considering the said representation, if any amount is found due and payable to the petitioner, the same shall be disbursed in favour of the petitioner within a further period of three months.
10. Before parting with the matter, this Court would like to express its anguish and concern towards the act and conduct of the respondents in unreasonably withholding the legitimate and admissible dues of the contractors. On various earlier occasions, this Court has come across numerous instances where the contractors have to knock at the doors of this Court for seeking release of their admissible dues for no fault on their part, which escalates their financial burden and creates unnecessary litigation. It is further observed that it has seemingly become a routine practice of the respondents to not release the due payments unless there is an order of the Court. Every week, this Court receives an average of 10-15 cases only for seeking release of their undisputed liability and in many such cases, the respondents have already admitted their liability but express inability to release the same for paucity of fund
The court directed the respondents to treat the petition as a representation and resolve the payment issue within a specified timeframe, highlighting concerns over habitual withholding of dues.
The court has the authority to direct the release of payment for work done by a contractor within a specified timeframe.
State cannot withhold admitted dues for executed works from which it benefited, citing procedural lapses or paucity of funds; such arbitrary action violates Article 14, attracting writ jurisdiction u....
The court mandated that administrative bodies must consider representations and issue reasoned decisions within a specified timeframe, ensuring procedural fairness.
Writ petitions against State entities for payment of due amounts are maintainable even with disputed facts; contract completion obligates the State to release funds promptly.
Writ petitions against State for contractual obligations are maintainable even with disputed facts; non-payment of dues despite work completion warrants judicial intervention.
A writ petition can be maintained against the State for contractual obligations even in the presence of disputed facts, ensuring fair treatment under Article 14.
Writ petitions against the State for contractual obligations are maintainable even with disputed facts; courts can direct payment when liability is clear.
State cannot withhold admitted dues for executed and accepted public works citing paucity of funds or lack of privity among instrumentalities; violates Article 14, warrants interest on delay.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.